Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹69.7 LAccepted-AOC CHAKKITTAPARA KOZHIKODE DISTRICT KOYILANDI TALUK P O CHAKKITTAPARA | L1 | Accepted-AOC Agreement Executed and Work Awarded | |
| 2 | L2₹71.2 L+₹1.5 L (2.15%)Rejected-AOC | L2 | Rejected-AOC Agreement Executed and Work Awarded | |
| 3 | L3₹72.1 L+₹2.4 L (3.44%)Rejected-Finance | L3 | Rejected-Finance Higher rate Quoted | |
| 4 | L4₹88.9 L+₹19.2 L (27.6%)Rejected-Finance | L4 | Rejected-Finance Higher rate Quoted | |
| 5 | L5₹92.0 L+₹22.3 L (32.1%)Rejected-Finance | L5 | Rejected-Finance Higher rate Quoted |
| Sl No | Description | Qty | Unit | ABHILASH K K L1 | T.AJAY L5 | SIDDIQUE M K L3 | Santhosh Kumar K.V. L4 | ABBAS C.M L2 |
|---|---|---|---|---|---|---|---|---|
| 1.00Construction of Building | ||||||||
| 1.00 | 15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | 3.05 | cum | 2,829.69 ₹8,633.38 Lowest | 3,600 ₹10,983.6 | 2,926.7 ₹8,929.36 | 3,608 ₹11,008.01 | 2,900 ₹8,847.9 |
| 1.00 | OD329643/2025-2026:Dismantling Interrlock work including stacking material within 50 metres lead.For thickness of interlock above 40 mm and up to 60 mm | 60 | sqm | 503.4 ₹30,204 | 150 ₹9,000 | 127.2 ₹7,632 | 156 ₹9,360 | 125 ₹7,500 Lowest |
| 1.00 | OD327623/2025-2026:Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess cement used as per design mix is not payable and less cement used as per design mix is recoverable separately .All work above plinth level upto floor V level | 60.86 | cum | 8,391.9 ₹5,10,697.47 Lowest | 13,000 ₹7,91,128 | 10,301.2 ₹6,26,889.83 | 12,701 ₹7,72,932.06 | 10,240 ₹6,23,165.44 |
| 1.00 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 129.96 | sqm | 777.22 ₹1,01,007.51 Lowest | 1,000 ₹1,29,960 | 803.9 ₹1,04,474.84 | 991 ₹1,28,790.36 | 800 ₹1,03,968 |
| 1.00 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 123.53 | sqm | 587.9 ₹72,620.35 Lowest | 750 ₹92,643.75 | 608.1 ₹75,115.55 | 750 ₹92,643.75 | 600 ₹74,115 |
| 1.01 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | 191.85 | sqm | 740.76 ₹1,42,118.51 Lowest | 950 ₹1,82,262.25 | 766.2 ₹1,46,999.3 | 945 ₹1,81,302.98 | 760 ₹1,45,809.8 |
| 1.01 | 5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges | 57.63 | sqm | 787.54 ₹45,385.93 Lowest | 1,000 ₹57,630 | 814.5 ₹46,939.64 | 1,003 ₹57,802.89 | 800 ₹46,104 |
| 1.01 | 5.9.7:Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases) | 23.62 | sqm | 755.1 ₹17,839.24 | 825 ₹19,490.63 | 657.4 ₹15,531.08 | 810 ₹19,136.25 | 650 ₹15,356.25 Lowest |
| 1.01 | 5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for:
Edges of slabs and breaks in floors and wallsUnder 20 cm wide | 60.4 | metre | 175.8 ₹10,618.32 Lowest | 250 ₹15,100 | 181.8 ₹10,980.72 | 224 ₹13,529.6 | 180 ₹10,872 |
Tender Value
₹83.0 L
EMD Value
₹50,000
Closing Date
3 Mar 2026, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Execcutive Engineer
Building Division Mananchira Kozhikode
GENERAL The construction of school building for Government Higher Secondary School Kokkallur, Kozhikode Kozhikode General Civil Work
2026_PWD_840608_1
79/EEBK/2025-26
Open Tender
Civil Works - Buildings
Item Rate
365 days
Kokkallur, Balussery
Please refer Tender documents.
8 documents required · 8 mandatory
₹2,760
Yes
₹50,000
Yes
10 Jun 2026
25 Feb 2026
5 Mar 2026
25 Feb 2026
3 Mar 2026
25 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of Building | |||||
| 1.001 | 15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | 3.05 | cum | - | - |
| 1.002 | OD329643/2025-2026:Dismantling Interrlock work including stacking material within 50 metres lead.For thickness of interlock above 40 mm and up to 60 mm | 60 | sqm | - | - |
| 1.003 | OD327623/2025-2026:Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess cement used as per design mix is not payable and less cement used as per design mix is recoverable separately .All work above plinth level upto floor V level | 60.86 | cum | - | - |
| 1.004 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 129.96 | sqm | - | - |
| 1.005 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 123.53 | sqm | - | - |
| 1.006 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | 191.86 | sqm | - | - |
| 1.007 | 5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges | 57.63 | sqm | - | - |
| 1.008 | 5.9.7:Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases) | 23.63 | sqm | - | - |
| 1.009 | 5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for:
Edges of slabs and breaks in floors and wallsUnder 20 cm wide | 60.4 | metre | - | - |
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1417146.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
sbd.pdf
Tender Documents • 1.64 MB
BOQ_1417146.xls
BOQ • 0.33 MB
officemempdf.pdf
Additional Documents • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .