Exe Eng R D Spl Div, Dhanbadv
Exe Eng R D Spl Div, Dhanbad
Construction of PCC Road in Bishanpur Panchayat from Shital Soren House to Jamuniya River. under Topchanchi Block, Dist Dhanbad
2026_RDSPL_119232_1
38/2026-27/RDSD/EE/Dhanbad/Gr. 01
Open Tender
Civil Works
Percentage
180 days
Topchanchi
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,000
₹82,000
28 Sept 2026
28 Sept 2026
7 Oct 2026
28 Sept 2026
5 Oct 2026
28 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery of the area By Manual Means | 0.19 | Hect | 19,760.3 | ₹3,655.66 |
| 2 | Excavation for road work in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and tranporting to the embankment location within all lifts and lead upto 1000 m. | 277.74 | M3 | 62.4 | ₹17,330.78 |
| 3 | Construction of subgrade and earthen shoulders with approved materials obtained from borrow pits or any other sources free from logs, roots, rubbish or any other ingredients likely to deteriorate or effect stability of the embankment including breaking the clods maximum to 60 mm cubes, placing the earth in layers not exceeding 225 mm loose thickness, rough dressing including cost of cutting and removing shrubs & roots in borrow area all complete job as per direction of E/I (Mode of measurement after required compaction) With initial lead of 15M & lift of 1.5M | 610.34 | M3 | 131.3 | ₹80,137.02 |
| 4 | Compacting original ground supporting subgrade (Loosening of the ground upto a level of 150mm below the subgrade level,watered,graded and compacted in layers to meet requirement of table 300-2 for subgrade construction). | 277.74 | M3 | 52.6 | ₹14,609.12 |
| 5 | By mix in Place method ( construcion of granular sub base by providing coarse graded material spreading in uniform layer with motor grader on prepared surface, mixing by mix in placed method with rotavator at OMC and compacting with vibratory power roller to achieve desire density. (Grading II Materials) | 277.74 | M3 | 1,316.7 | ₹3,65,696.11 |
| 6 | Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with approve grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing | 342.89 | M3 | 5,360.4 | ₹18,38,027.56 |
| 7 | Excavation for structure in ordinary soil (Earth work in excavation of foundation of structure as per drawing and technical specification including setting out, construction of shoring and bracing removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved materials.(Mechanical Means) | 79.25 | M3 | 57.4 | ₹4,548.84 |
| 8 | Sand filling in foundation trenches as per drawing and technical specifications. R.D.D 15.03 Page 636 | 11.89 | M3 | 567.8 | ₹6,749.55 |
| 9 | Providing random rubble stone masonary in C.M. (1:3) in foundation -do- -do- all complete as per building specification and direction of E/I. | 59.59 | M3 | 3,102.8 | ₹1,84,890.89 |
| 10 | Providing random rubble stone masonary in C.M. (1:3) in substructure -do- -do- all complete as per building specification and direction of E/I. | 45.72 | M3 | 3,129.1 | ₹1,43,062.45 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.84 MB
SBD38Gr01.pdf
Tender Documents • 4.89 MB
BOQ_161369.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .