Loading…
Loading…
Tender Value
₹11.2 Cr
EMD Value
₹22.5 L
Closing Date
13 Jul 2026, 2:00 pm5d left
TVC Division-Modification to existing tramway type OHE into conventional type in section between Punkunam (PNQ) and Guruvayur (GUV) to increase the section speed.
V_TRD_OT_03_2026-27item2
V_TRD_OT_03_2026-27item2
Open
12 Months
Thrissur, Kerala
₹0
₹22.5 L
19 Jun 2026
19 Jun 2026
29 Jun 2026
B-Non SOR Items
Item Breakup - A-SOR items
SOR Item no. 6(a) Erection of over head Kilometre equipment only by manual
SOR Item no. 32/6(a) Erection of over head Kilometre equipment only by manual- Work under power block
SOR Item no.7(d) Erection of 25kV feeder
SOR Item no. 32/7(d) Erection of 25kV feeder- Kilometre Work under power block
SOR Item no.9(d) Erection of anti creep with Each Cadmium Copper Catenary Wire.
SOR Item no. 32/9(d) Erection of anti creep with Each Cadmium Copper Catenary Wire- Work under power block Total 677523.60 Item- 2 Part B Steel items S No. Item Description of Item Unit Qty Rate Amount No
SOR Item no. 3a(ii) Supply only for fabricated MT mast K,B,S, T series etc.
SOR Item no.3b(i) Supply of fabricated steel MT work other than masts by manual
SOR Item no.3b(i) Erection of fabricated steel MT work other than masts by manual THIRUVANANTHAPURAM DIVISION-ELECTRICAL/SOUTHERN RLY
SOR Item no.32/3b(i) Erection of fabricated MT steel work other than masts by manual -Work under power block
SOR Item no.3(c) Supply of fabricated steel MT work(SPS).
SOR Item no.3(c) Erection of fabricated steel MT work(SPS).
SOR Item no32/3(c) Erection of fabricated steel MT work(SPS) - Work under power block Total 12087588.00 Item- 3 Part C Foundation items S No. Item Description of Item Unit Qty Rate Amount No
SOR Item no.2a(i) For Foundation and Plinth - cum Concrete in hard soil
SOR Item no.2(b) Concrete in other than hard cum soil and rock
SOR Item no.2(c) Reinforced concrete Total 3515908.00 Item- 4 Part D other items S No. Item Description of Item Unit Qty Rate Amount No
SOR Item no.1(a) Preparation of designs and Per Track drawings for overhead equipment and KM verification of purchasers Engineering plan
SOR Item no.1(b)-Preparation of designs and Each drawings for switching stations
SOR Item no.1(c)-Preparation of station working Each rule diagram and working instruction
SOR Item no.3a(i)-Erection of traction masts MT and main masts of switching stations, booster stations and LT supply Transformer stations by manual
SOR Item no.32/3a(i)-Erection of traction masts MT and main masts of switching stations, booster stations and LT supply Transformer stations by manual- Work under power block
SOR Item no.3(e)-Supply of a Guy rod assembly Each
SOR Item assembly
SOR Item no.32/3(e)-Erection of a Guy rod Each assembly- Work under power block
SOR Item no.4a(i)(b)- Supply of a single bracket Each assembly without insulator
SOR Item no.4a(i)b-Erection of a single bracket Each assembly complete with insulators
32/4a(i)b Erection of a single bracket assembly Each complete with insulator - Work under power block
SOR Item no.4a(ii)- Extra on 4(a) (i) for Each supporting two OHEs/ Supply portion
SOR Item no.4a(ii)- Extra on 4(a) (i) for Each supporting two OHEs/ Erection portion
SOR Item no.32/4a(ii)- Extra on 4(a) (i) for Each supporting two OHEs/ Erection portion -work under power block
SOR Item no.5(a)(ii)-Supply of a span wire
SOR Item no.5(a)(ii)-Erection of a span wire
SOR Item no.32/5(a)(ii)-Erection of a span wire- Metre work under power block
SOR Item no.8a(v)-Supply of regulating Each equipment (3 pulley type) with counter-weight assembly for conventional / composite OHE. THIRUVANANTHAPURAM DIVISION-ELECTRICAL/SOUTHERN RLY
SOR Item no.8a(v)-Erection of regulating Each equipment (3 pulley type) with counter-weight assembly for conventional / composite OHE.
SOR Item no.32/8a(v)-Erection of regulating Each equipment (3 pulley type) with counter-weight assembly for conventional / composite OHE. - Work under power block
SOR Item no.8b(i)-Supply of materials for Each termination of Single conductor of overhead equipment or terminating wire.
SOR Item no.8b(i)-Erection of materials for Each termination of Single conductor of overhead equipment or terminating wire.
SOR Item no.32/8b(i)-Erection of materials for Each termination of Single conductor of overhead equipment or terminating wire.- Work under power block
SOR Item no.8b(ii)-Supply of materials for Each termination of double over head equipment conductor
SOR Item no.8b(ii)-Erection of materials for Each termination of double over head equipment conductor
SOR Item no.32/8b(ii)-Erection of materials for Each termination of double over head equipment conductor - Work under power block
SOR materials/termination of 25 kV terminating wire (150 sq mm)copper cross track / along track feeder
SOR materials/termination of 25 kV terminating wire (150 sq mm)copper cross track / along track feeder
SOR materials/termination of 25 kV terminating wire (150 sq mm)copper cross track / along track feeder- work under power block
SOR Item no.10(a)-Extra on item 6(a) for supply Each of additional fittings at a turnout, diamond crossing or overlap.
SOR Item no.10 (a)-Extra on item 6(a) for Each erection of additional fittings at a turnout, diamond crossing or overlap.
SOR Item no.32/10(a)-Extra on item 6(a) for Each erection of additional fittings at a turnout, diamond crossing or overlap.- Work under power block
SOR Item no.11a(i)-Supply of a solid core cut Each insulator
SOR Item no.11a(i)-Erection of a solid core cut Each insulator
SOR Item no.32/11a(i)-Erection of a solid core Each cut insulator -Work under power block
SOR Item no.11a(ii)-Supply of a solid core Each suspension insulator
SOR Item no.11a(ii)-Erection of a solid core Each suspension insulator
SOR Item no.32/11a(ii)-Erection of a solid core Each suspension insulator -Work under power block
SOR Item insulator
SOR Item no.11(b)-Erection of 25 kV Post Each insulator THIRUVANANTHAPURAM DIVISION-ELECTRICAL/SOUTHERN RLY
SOR Item no.32/11(b)-Erection of 25 kV Post Each insulator -Work under power block
SOR Item no.12(a)-Supply of a section insulator Each assembly
SOR Item no.12(a)-Erection insulator assembly
SOR Item no.32/12(a)-Erection of a section Each insulator assembly- Work under power block
SOR Item no.13(a)-Supply of a 25 kV single Each pole isolator without earth contact assembly
SOR Item no.13(a)-Erection of a 25 kV single Each pole isolator without earth contact assembly
SOR Item no.32/13(a)-Erection of a 25 kV single Each pole isolator without earth contact assembly - work under power block
SOR Item no.15(a)-Supply of a copper jumper
SOR Item no.15(a)-Erection of a copper jumper Each
SOR Item no.32/15(a)-Erection of a copper Each jumper - Work under power block
SOR Item no.17(a)-Supply of a single earth Each electrode
SOR Item no.17(a)-Erection of a single earth Each electrode
SOR Item no.17(b)-Supply of earth bus
SOR Item no.17(b)-Erection of earth bus
SOR Item no.17(c)-Supply of copper strips for Metre equipment earthing
SOR Item no.17(c)-Erection of copper strips for Metre equipment earthing
SOR Item no.26a(i)-Supply of Aluminium bus Metre bar 36mm x 28mm
SOR Item no.26a(i)-Erection of Aluminium bus Metre bar 36mm x 28mm
SOR Item no.32/26a(i)-Erection of Aluminium Metre bus bar 36mm x 28mm- Work under power block
SOR Item no26a(ii)-Supply of Solid copper bus Metre bar 18 mm
SOR Item no.26a(ii) Erection of Solid copper Metre bus bar 18 mm
SOR Item no.32/26a(ii) -Erection of Solid copper Metre bus bar 18 mm - Work under power block
SOR Item no.26(b)(i)-Supply of aluminium bus Each bar connectors-Bus terminal (6480)
SOR Item no.26(b)(i)-Erection of aluminium bus Each bar connectors-Bus terminal (6480)
SOR Item no.32/26(b)(i)-Erection of aluminium Each bus bar connectors-Bus terminal (6480)- work under power block
SOR Item no.26(b)(ii)-Supply of aluminium bus Each bar connectors-Bus splice (6490)
SOR Item no.26(b)(ii)-Erection of aluminium bus Each bar connectors-Bus splice (6490)
SOR Item no.32/26(b)(ii)-Erection of aluminium Each bus bar connectors-Bus splice (6490)- work under power block
SOR Item no.26(b)(iii)-Bus (6500)- supply portion
SOR Item no.26(b)(iii)-Bus (6500)- erection portion
SOR Item no.32/26(b)(iii)-Bus tee connector Each (6500)- erection portion-work under power block THIRUVANANTHAPURAM DIVISION-ELECTRICAL/SOUTHERN RLY
SOR Item no.26(b)(iv)-Terminal 36/20 (6530)-Supply portion
SOR Item no.26(b)(iv)-Terminal 36/20 (6530) Erection portion
SOR Item no.32/26(b)(iv)-Terminal connector Each 36/20 (6530) Erection portion -Work under power block
SOR Item no.26(b)(v)-Tap connector (6520)- Each supply portion
SOR Item no.26(b)(v)-Tap connector (6520)- Each erection portion
SOR Item no.32/26(b)(v)-Tap connector (6520) Each erection portion - work under power block
SOR bolted type (6830-1) -Supply
SOR bolted type (6830-1) erection
SOR Item no.32/26(b)(vii)-Terminal connector Each bolted type (6830-1) erection - work under power block
SOR Item no.26c(i) - Supply of solid copper bus Each bar connectors - Bus terminal (1009)
SOR Item no.26c(i) Erection of solid copper bus Each bar connectors - Bus terminal (1009)
SOR Item no.32/26c(i) Erection of solid copper Each bus bar connectors - Bus terminal (1009) work under power block
SOR Item no.26c(ii) Supply of solid copper bus Each bar connectors - bus splice
SOR Item no.26c(ii) Erection of solid copper bus Each bar connectors - Bus splice( )
SOR Item no.32/26c(ii) Erection of solid copper Each bus bar connectors - Bus splice( )- Work under power block
SOR Item no.30(a)(i)-Supply of fencing panels Metre at switching stations
SOR Item no.30(a)(i)-Erection of fencing panels Metre at switching stations
SOR Item uprights
SOR Item uprights
SOR Item no.30(a)(iii)-supply screen for FOB/ROB.
SOR Item no.30(a)(iii)-Erection of protective Each screen for FOB/ROB.
SOR Item no.30(b)(i)-Supply of anti -climbing Metre device at switching stations
SOR Item no.30(b)(i)-Erection of anti -climbing Metre device at switching stations
SOR Item no.30(b)(iv)-Fixing of caution boards Lumpsum (supply portion)
SOR Item no.30(b)(iv)-Fixing of caution boards Lumpsum (erection portion)
SOR Item no.31(a)-Transfer of equipment from Each one mast or support to another
SOR Item no.32/31a-Transfer of equipment Each from one mast or support to another - work under power block
SOR Item no.31(d)-Dismantling of overhead Kilometre equipment
SOR Item no.32/31d-Dismantling of overhead Kilometre equipment - work under power block THIRUVANANTHAPURAM DIVISION-ELECTRICAL/SOUTHERN RLY
SOR Item no.31(e)-Dismantling of feeder/return Kilometre conductor
SOR feeder/return conductor - work under power block
SOR Item no.31(f)-Splicing and extension of an Each anchored over head equipment -supply portion
SOR Item no.31(f)-Splicing and extension of an Each anchored over head equipment -Erection portion
SOR Item no.32/31(f)-Splicing and extension of Each an anchored over head equipment -Work under power block
SOR Item no.31(g)-Dismantling of a section Each insulator
SOR Item no.32/31(g)-Dismantling of a section Each insulator - Work under power block
SOR Item no.31(i)-Dismantling of an isolator
SOR Item no.32/31(i)-Dismantling of an isolator- Each Work under power block
SOR Item no.31(k)-Dismantlement of OHE mast Each / structure by cutting
SOR Item no.32/31(k)-Dismantlement of OHE Each mast / structure by cutting -Work under power block
SOR Item no.31(l)-Dismantlement of OHE mast Each structure of breaking the foundation
SOR Item no.32/31(l)-Dismantlement of OHE Each mast structure of breaking the foundation - Work under power block
SOR Item no.31(n)- Dismantling of guy rod
SOR Item no.32/31(n)-Dismantling of guy rod - Each Work under power block
SOR Item no. 31(q)-Splicing and Extension of Each feeder/RC wire-Supply portion
SOR Item no. 31(q)-Splicing and Extension of Each feeder/RC wire-Erection portion
SOR Item no. 32/31(q)-Splicing and Extension Each of feeder/RC wire- work under power block
SOR Item no. 31(t)-Spreading of 20 mm Ballast cum in the SSP/SP Switch Yard -Supply portion.
SOR Item no. 31(t)-Spreading of 20 mm Ballast cum in the SSP/SP Switch Yard -Erection portion. Total 10054999.80
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
docpnqguv.pdf
ATTACHMENT
BGformat_1.pdf
ATTACHMENT
GCCACSno11.pdf
ATTACHMENT
GCC Works correction slip4
ATTACHMENT
GCC2022correctionslipNo.5.pdf
ATTACHMENT
GCC Works correction slip6
ATTACHMENT
jpo.pdf
ATTACHMENT
GCC_April_2022_ACS-7.pdf
ATTACHMENT
GCC Works correction slip8
ATTACHMENT
GCC Works correction slip9
ATTACHMENT
GCCcorrectionslipNo.10.pdf
ATTACHMENT
formatofAnnexureVA.pdf
ATTACHMENT
GCC2022AprilCorrectionslip3.pdf GCC Works correction slip3
ATTACHMENT
GCC2022correctionslipNo.2.pdf
ATTACHMENT
GCCApril2022Correctionslip1.pdf GCC Works correction slip1
ATTACHMENT
GCCApril2022_1.pdf
ATTACHMENT
GCCApril2022Correctionslip1.pdf
ATTACHMENT
GCC2022AprilCorrectionslip3.pdf
ATTACHMENT
GCC_April-2022_Correctionslip4.pdf
ATTACHMENT
GCC_April-2022_Correctionslip6.pdf
ATTACHMENT
GCC_Apr_2022_ACS-8_20-12-24.pdf
ATTACHMENT
GCC_Apr_2022_ACS-9_9-1-25.pdf
ATTACHMENT
Download all tender documents and submit your bid