Loading…
Loading…
Tender Value
₹40.1 L
EMD Value
₹40,100
Closing Date
28 Sept 2026, 5:30 pm5d left
Superintending Engineer., Nimapara Irr Divn.
Office of the Superintending Engineer Nimapada Irrigation Division, Nimapada Puri Odisha
Improvement to Service Road on Right bank of Gotalgram Distributary near Village Tolakpada Bhoisahi.
2026_CELBB_141145_53
e-Procurement Notice No.- 06 of 2026-27
Open Tender
Civil Works - Others
Percentage
240 days
Nimapada
Please refer Tender Documents
2 documents required · 2 mandatory
₹6,000
₹40,100
Yes
18 Sept 2026
18 Sept 2026
29 Sept 2026
18 Sept 2026
28 Sept 2026
18 Sept 2026
18 Sept 2026 - 25 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing grass and removal ; rubbish up to a distance 50 Mtr. Outside disposal of unserviceable materials with all leads, lifts and delifts with cost of all labour T&P, labour welfare cess etc.complete as per direction the Engineer-in-charge. | 12,600 | One Sqm | 2.9 | ₹36,540 |
| 2 | Collecting , supplying and stacking good quality moorum & sand at work site in irregular box heaps of size 1.50 x 1.50 x0.50M to be measured as one cum and conveying from stacks and mixing the moourm and sand in proportion 70:30(70% :30%) and spreading the admixture over the prepared surface not exceeding 100 mm in layers to required thickness including watering and compacting to required density with P.R.R including cost,conveyance,royalty and all other taxes of all materials and labour, T &P,EMF,DMF, Additional charges of materials,cess with hire and running charges of P.R.R. including all leads, lifts and delifts in all respect etc. .complete as per direction of the Engineer-in-charge. | 546.75 | one cum | 1,626.7 | ₹8,89,398.23 |
| 3 | Providing laying,spreading and compacting stone aggregates of IRC Grade-I metal of size 90 mm to 45 mm free from weathered skin and deleterious materials to water bound macadam,moorum specification including spreading in uniform thickness ,hand packing, rolling with 3 wheeled steel roller 8-10 tonns in stages to proper grade and camber ,applying and brooming requisite type of moorum screening as moorum to fill up the interstices aggregates aggregates,watering & compacting to the required density and thickness of 100 mm as per clause No- 404 of MOSRT&H specification for road and bridge works (4 th revision) including cost, conveyance, royalty, EMF,DMF, Additional charges and all other taxes of all materials and cost of labour, T&P required for the work including hire & running charges of machineries with all leads,lifts and delifts and labour welfare cess etc.complete in all respects and as per specification and direction of Engineer-in -charge. | 337.5 | One Cum | 4,010.4 | ₹13,53,510 |
| 4 | Collecting, supplying and stacking good quality laterite moorum at work site for pre-measurement, including conveying from stacks, spreading uniformly over the road surface and consolidation with PRR, complete with cost of materials, carriage, loading and unloading, royalty,EMF,DMF,additional charges, taxes, all labour, T&P and other incidental charges, complete in all respects as per technical specification and as directed by the Engineer-in-Charge. | 281.25 | One Cum | 1,678.9 | ₹4,72,190.63 |
| 5 | Earthwork in all kinds of soil except sand, sandy or slushy soil in borrow area by mechanical means and transportation of excavated earth by mechanical means with all leads, lifts, delfts, rehandling, conveyance, royalty,EMF,DMF, Additional charges of materials, labour cess, including loading and unloading the same on prepared and approved surface including rough dressing and breaking the clods to maximum 5 cm. to 7 cm. in size and laying in layers not exceeding 22.5 cm.layers to make ready for watering and compaction with sheep foot rollers and dozers but excluding watering and compaction in dams and dykes for all heights including construction, maintenance, watering and lighting of haul road and borrow area with labour, T & P etc. complete as per direction of the Engineer-in-charge. (Earth will be arranged by the bidder at his own cost and risk. Earth should be free from clods, roots, brickbats and other debris.. Measurement of the fill to be taken on the finished level section) only | 4,176 | one cum | 300.6 | ₹12,55,305.6 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.10 MB
BidDocumentNID155.pdf
Tender Documents • 1.87 MB
BOQ_610058.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .