Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹69.5 LAccepted-AOC | ₹69.5 L | L1 | Accepted-AOC Agreemant Executed |
| 2 | L2₹69.6 L+₹9,825.53 (0.14%)Rejected-AOC | ₹69.6 L+₹9,825.53 (0.14%) | L2 | Rejected-AOC Agreemant Executed |
| 3 | L3₹74.8 L+₹5.3 L (7.61%)Rejected-AOC | ₹74.8 L+₹5.3 L (7.61%) | L3 | Rejected-AOC Agreemant Executed |
| 4 | L4₹77.2 L+₹7.7 L (11.1%)Rejected-AOC | ₹77.2 L+₹7.7 L (11.1%) | L4 | Rejected-AOC Agreemant Executed |
| Sl No | Description | Qty | Unit | shihab L3 | ALI L2 | MOHAMMED SHAHEER KURIKKAL M.P L4 | HM CONSTRUCTION COMPANY L1 |
|---|---|---|---|---|---|---|---|
| 1.00Class room | |||||||
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 92.12 | cum | 359.73 ₹33,139.05 | 312.6 ₹28,797.34 | 700 ₹64,485.4 | 312.2 ₹28,760.49 Lowest |
| 1.00 | 2.26.1:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil | 27.84 | cum | 131.02 ₹3,647.6 | 113.86 ₹3,169.86 | 150 ₹4,176 | 113.7 ₹3,165.41 Lowest |
| 1.00 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 0.57 | cum | 9,235.96 ₹5,282.97 | 8,026.06 ₹4,590.91 | 8,500 ₹4,862 | 8,016 ₹4,585.15 Lowest |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 17.21 | cum | 7,932.89 ₹1,36,564.7 | 6,893.68 ₹1,18,674.7 | 7,800 ₹1,34,277 | 6,885.7 ₹1,18,537.33 Lowest |
| 1.00 | OD262975/2024-2025:Providing and laying in position machine batched and machine mixed design mix M- 30 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Minimum Cement content considered in this item is @ 390 kg/ cum. Excess cement used as per design mix is not payable separately. All work upto plinth level | 38.21 | cum | 12,400 ₹4,73,841.2 | 11,398.53 ₹4,35,572.03 | 12,000 ₹4,58,556 | 11,385.4 ₹4,35,070.29 Lowest |
| 1.01 | OD262976/2024-2025:Providing and laying in position machine batched and machine mixed design mix M- 30 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Minimum Cement content considered in this item is @ 425 kg/ cum. Excess cement used as per design mix is not payable separately. All work above plinth level | 81.52 | cum | 12,600 ₹10,27,164.6 | 11,635.32 ₹9,48,522.92 | 12,500 ₹10,19,012.5 | 11,621.9 ₹9,47,428.91 Lowest |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 4,512 | kilogram | 97 ₹4,37,664 | 97.7 ₹4,40,822.4 | 95 ₹4,28,640 Lowest | 97.5 ₹4,39,920 |
| 1.01 | 5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more | 12,453.88 | kg | 97 ₹12,08,026.36 | 97.7 ₹12,16,744.08 | 95 ₹11,83,118.6 Lowest | 97.5 ₹12,14,253.3 |
| 1.01 | 4.2.5:Providing and laying cement concrete in retaining walls, return walls, walls ( any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor, etc. up to floor five level, excluding the cost of centering, shuttering and finishing:1:3:6 (1 cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 20 mm nominal size derived from natural sources) | 0.64 | cum | 11,089.78 ₹7,075.28 | 9,637.03 ₹6,148.43 | 15,000 ₹9,570 | 9,625.9 ₹6,141.32 Lowest |
Tender Value
₹80.1 L
EMD Value
₹50,000
Closing Date
13 Oct 2025, 5:00 pmClosed
Executive Engineer
Executive Engineer PWD Buildings Division Palakkad
GENERAL-Construction of building for GLPS Pottassery East School in Kanjirapuzha Grama Panchayath-additional Classroom-General Civil Work
2025_PWD_804155_1
PWD/BLDG/TR/3085/2025_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
360 days
POTTASERI
Please refer Tender documents.
10 documents required · 10 mandatory
₹2,760
Yes
₹50,000
Yes
11 Nov 2025
29 Sept 2025
16 Oct 2025
29 Sept 2025
13 Oct 2025
29 Sept 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .