| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 LAccepted-Finance | L1 | Accepted-Finance L1 bidder | |
| 2 | L2₹1.3 L+₹12,977.75 (11.0%)Accepted-Finance 00 MUKUNDPUR PAHO DOMANPUR MUKUNDPUR PAHO MIRZAPUR UTTAR PRADESH 231306 | MIRZAPUR | UTTAR PRADESH | 231306 | L2 | Accepted-Finance L2 bidder | |
| 3 | L3₹1.4 L+₹17,044 (14.4%)Accepted-Finance | L3 | Accepted-Finance L3 bidder |
Tender Value
₹1.2 L
EMD Value
₹2,000
Closing Date
24 Jun 2022, 4:00 pmClosed
SE ETC I, lucknow
Pareshan Bhawan, Lucknow
Work of grass cutting and uprroting at 132 KV Substation Ram Sanehi Ghat and Haidergarh under ETD III, Lucknow
2022_UPTCL_702899_1
e-tender 21/2022-23
Open Tender
Miscellaneous Works
Piece-work
365 days
Lucknow
Please refer Tender documents.
2 documents required · 2 mandatory
₹236
A/c No 2408002190005438, IFS PUNB0691100, PNB, Lko
₹2,000
12 Jul 2022
25 May 2022
25 Jun 2022
25 May 2022
24 Jun 2022
25 May 2022
Amount
Clearance of dense Jungle and Cutting of Grass, Kusha & Kansa including Uprooting of the Rank Vegetation, Grass, Bushes, Shrubs etc. By Scrapping of Grass, Bush Wood & Plants etc. Above 2" over the ground level; Weeding out the wild growth Roots, Seeds etc. and collection of the foreign materials like Kankar, Ballast, Pebbles, Waste Paper etc. in Switchyard Area between Pale Fencing / Area between Chain Link Fencing & Secuirty Wall, Area around Control Room / Committee Room / Store Sheds and Open yard Store Area of the Sub Stations, then Disposal of all the removed Vegetation, Rubbish & Garbage etc. by throwing it outside the Periphery of the Sub Station Premises, with all cost of men, misc. consumables and T & P etc. required for the job, as per details below:
First Cutting between 1st July 2022 to 31st July 2022
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Second Cutting between 1st October 2022 to 31st October 2022
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Third Cutting between 1st January 2023 to 31st January 2023
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Fourth Cutting between 1st April 2023 to 30th April 2023
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Uprooting of small wild Trees in Switchyard Area between Pale Fencing / Area betwee Chain Link Fencing & Security Wall, Area around Control Room / Committee Room / Store Sheds and Openyard Store Area at the Sub Station by digging and taking out the complete Root, then disposal of all the removed Vegetation, Rubbish & Garbage etc. by throwing it outside the Periphery of the 132 KV Sub Stations premises and finally, leveling the ground, with all cost of men, misc. consumables and T & P etc. required for the job, as per details below:
First uprooting between 1st July 2022 to 31st July 2022
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Second uprooting between 1st October 2022 to 31st October 2022
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Third uprooting between 1st January 2023 to 31st January 2023
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Fourth uprooting between 1st April 2023 to 30th April 2023
132 KV S/S Ram Sanehi Ghat
132 KV S/S Haidergarh
Aditya Enterprises
M/S DINESH KUMAR
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .