| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.3 LAccepted-Finance | ₹20.3 L | L1 | Accepted-Finance L1 |
| 2 | L2₹20.5 LRejected-Finance MOH DESHNAGAR BAHAR CHUNGI PILIBHIT | ₹20.5 L | L2 | Rejected-Finance L2 |
| 3 | L3₹20.7 LRejected-Finance 143 SHASTRI NAGAR LAKHIMPUR KHERI | KHERI | UTTAR PRADESH | 261501 | ₹20.7 L | L3 | Rejected-Finance L3 |
| 4 | L4₹20.9 LRejected-Finance | ₹20.9 L | L4 | Rejected-Finance L4 |
Updated dates
Tender Value
₹27.7 L
EMD Value
₹2.8 L
Closing Date
18 Mar 2026, 12:00 pmClosed
ee cd1 pwd pbt
ee cd1 pwd pbt
Reconstruction work of Shahjahanpur road to ahirpura road Ganna Vibhag
2026_CEBLY_1115382_4
241/31A Date 02-02-2026
Open Tender
Civil Works - Roads
90 days
Pilibhit
Please refer Tender documents.
3 documents required · 3 mandatory
₹944
₹2.8 L
Yes
15 Apr 2026
12 Feb 2026
18 Mar 2026
12 Feb 2026
18 Mar 2026
12 Feb 2026
Excavation in foundation in ordinary soil, loame, clay or sand including lift upto 1.5 m & Iead upto 30m Including filling watering & ramming of excavated earth into the trenches or into the space between the building & the sides of foundation trenches or in to the plinth removal & disposal of surplus earth as directed by the engineer in charge upto a distance of 30m from the foundation trenches. (Including Royalty). si no 251
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203(P.C.C. Grade M 10)
Brick Masonry Work in Cement Mortar 1:4 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications Clause no.600,1200&1203
Pointing with cement mortar (1:3) on brickwork as per drawing and technical specification Clauses 613.3 and 1204
Plastering with cement mortar (1:4) , 15 mm thick on brick work in super structure as per Technical specification clause 613.4 & 1204.
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203(PCC Grade M20)
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing bymix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specificatin Clause 401.
Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802,803, 1202 & 1203 RCC grade M 25
Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 4.7-405(3)
Construction of unreinforced, dowel jointed at expension and construction joint only, plain cement concrete pavement thickness as design, over a prepare subbase, 43 grade cement for any other type as per clause 1501.2.2 M30 (grade), coarse and fine aggregates confirming to IS383, maximum size of coarse aggregate not exceeding 25mm, mixed in a concrete mixer of not less then 0.2cum capacity and appropriate weight batcher using approved mix desing, laid in approved fixed side from work (steel channel, laying and fixing of 125micron thick polythene film, wedges, steel plates including levelling the form work as per drawing), spreading the concrete with shovels rakes, compacted using needle, screed and plate vibrator and finished in continous opreation including provision of contraction and expansion, construction joint, applying debonding strips, primer, sealant, dowel bars, near approches to bridge,/culvert and construction joints, admixtures as approved curing of concrete slabs for 14 days curing compound (where specified) and water finishing to line and grade as per drawing and techenical specification clause 1501
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. carted 1 km
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
techsummary_2069557.pdf
BOQ Comparative Chart
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.67 MB
Tendernotice_2.pdf
PDF • 1.19 MB
BOQ_2069557.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid