| # | Company | Status |
|---|---|---|
| 1 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
| 2 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
| 3 | Admitted-Fee/PreQual/Technical | Admitted-Fee/PreQual/Technical |
Tender Value
₹4.1 L
EMD Value
₹10,000
Closing Date
17 Aug 2026, 1:00 pmClosed
EE/IGWTP
OFFICE OF THE EE/IGWTP, BARRACKPORE
UPLIFTMENT OF THE SURROUNDING AREAS ATTACH WITH THE MODULE 5, CHLORINE CONTACT CHAMBER AND CHLORINE STATION UNDER IGWTP.
2026_KMC_1036029_1
KMC/IGWTP/029/26-27, DT-27/07/2026
Open Tender
CIVIL WORKS
Percentage
240 days
IGWTP, MONIRAMPUR, BARRACKPORE
AS PER NIT
4 documents required · 4 mandatory
₹0
₹10,000
19 Aug 2026
4 Aug 2026
19 Aug 2026
4 Aug 2026
17 Aug 2026
10 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. II. COMPOUND DEVELOPMENT: 19) Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific permission of Engineer-in-Charge prior to execution will be necessary). (Payment to be made on area cleared) | 26,641.4 | SQUARE METER | 11 | ₹2,93,055.4 |
| 2 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 1.Surface Dressing of the ground in any kind of soil including removing vegetation inequalities not exceeding 15 cm depth and disposal of the rubbish within a lead upto 75 m as directed. | 323 | SQUARE METER | 10 | ₹3,230 |
| 3 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: B. MAINTENANCE WORKS : 12)Cleaning and removing conservancy garbage mixed with rubbish & other filthy materials from the road side flank, drain and compound including cutting, loading, unloading to and from truck or cart by Mathor labour & removing the same to any distance. | 0.75 | CUBIC METER PERCENT | 5,662 | ₹4,246.5 |
| 4 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: B. MAINTENANCE WORKS : 10)Uprooting and removing plants from the surface of walls parapet etc and making good damages. (Repairing of damages to be paid separately). (a) Small plant of girth of exposed stem upto 75 mm. lift upto 6 mtr. Note : For lift beyond initial 6 mtr. the rate will be increased @ 20% for each additional lift if 6 mtr. or part thereof. | 267 | EACH | 50 | ₹13,350 |
| 5 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: B. MAINTENANCE WORKS : 10)Uprooting and removing plants from the surface of walls parapet etc and making good damages. (Repairing of damages to be paid separately). (b) Medium size plant of girth of exposed stem above 75 mm. but not exceeding 150 mm. lift upto 6 mtr. Note : For lift beyond initial 6 mtr. the rate will be increased @ 20% for each additional lift if 6 mtr. or part thereof. | 159 | EACH | 60 | ₹9,540 |
| 6 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: B. MAINTENANCE WORKS : 10)Uprooting and removing plants from the surface of walls parapet etc and making good damages. (Repairing of damages to be paid separately). (c) Large plant of girth of exposed stem above 150 mm. but not exceeding 225 mm. lift upto 6 mtr. Note : For lift beyond initial 6 mtr. the rate will be increased @ 20% for each additional lift if 6 mtr. or part thereof. | 25 | EACH | 187 | ₹4,675 |
| 7 | SECTION 1. ------------BUILDING WORKS (J)WHITE WASH, COLOUR WASH, DISTEMPER A. ORIGINAL WORKS 2 Chalk washing (one coat) - any height. | 63.5 | SQUARE METER | 8 | ₹508 |
| 10 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. I. HORTICULTURE: 7.Planting of trees ( Avenue plants) in 0.60m dia holea, 1m deep dug in the ground, mixing the soil with decayed farm yard/sludge manure. This includes supply of labour, tools & plants including materials but excluding cost of tree. | 20 | EACH | 117 | ₹2,340 |
| 11 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. I. HORTICULTURE: 8.Maintanance of trees for one year (Avenue Plants) including watering, trimming, manuring, spraying insecticide and guarding as required. This includes supply of labour, tools & plants including materials. | 30 | EACH PER YEAR | 477 | ₹14,310 |
| 101 | Sub Total | - | - | - | - |
stage.html
html • 0.02 MB
tech_bid_open.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.23 MB
BOQ_2545075.xls
BOQ • 0.34 MB
029TECHBID.pdf
Tender Documents • 1.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .