1 Apr 2026, 6:00 pmClosed
Executive Engineer, N.P. Main Canal Division No. 19, Harij
Strengthening work of Rajpura Branch Canal (Ch. 34.800 km to Ch. 42.450 km), Nanichandur, Sipur and Taranagar Distributaries & its Minors of Rajpura Branch Canal for the Year 2025-26
285678
18 of 2025-26
Open
Civil Works - Canal
Works
Patan
9 documents required · 8 mandatory · 1 optional
₹4,248
Yes
Executive Engineer, N.P.Main Canal Division No. 19, Harij
₹1.8 L
Yes
12 Mar 2026
12 Mar 2026
12 Mar 2026
1 Apr 2026
12 Mar 2026
BILL OF QUANTITIES
BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and are
given to provide a common basis for bidding. The basis of payment will be the
actual quantities of work ordered and carried out, as measured by the Contractor
and verified by the Engineer and valued at the rates and prices tendered in the
priced Bill of Quantities, where applicable, and otherwise at such rates and prices
as the Engineer may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so
far as it is otherwise provided under the Contract, include all constructionalplant,
layout, supervision, materials, erection, maintenance, insurance, profit, taxes and
duties, together with all general risks, liabilities and obligations set out or implied
in the Contract.
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed
to enter a rate or price shall be deemed to be covered by other rates and prices
entered in the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be included
in the items provided in the priced Bill of Quantities, and where no Items are
provided the cost shall be deemed to be distributed among the rates and prices
entered for the related items of Work.
7. General direction and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. References to the relevant
sections of the contract documentation shall be made before entering rates or
prices against each item in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for Road and Bridge works. For building works specifications for
building are to be followed.
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause 29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledgehammers, or the use of compressed
air drilling for its removal, and which cannot be extracted by ripping with a tractor
of at least 150 kw with a single rear mounted heavy duty ripper.
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr. )
Name Of Work :-Strengthening work of Rajpura Branch Canal (Ch. 34.800 km to Ch. 42.450 km),
Nanichandur, Sipur and Taranagar Distributaries & its Minors of Rajpura Branch Canal for the Year
Sr.No. Item of work Unit Qty Rate (Rs.) Amount (Rs.)
Dismantling the C.C. lining
including disposing off the sq
dismentalled materials as directed
Providing and laying HYSD/TMT
Fe-415,500D steel bar
reinforcement for R.C.C. works
and anchor bars with providing
2 2 binding wires including cutting, MT 0.800 71366.00
bending, welding, binding in
position, hooking, placing in
position with all leads & lifts etc.
complete.(c) TMT Fe-500D
Providing and laying 7.5 cms
thick cast in situ cement concrete
1:2:4 grade with the use of
crushed aggregates for canal
lining works including use of all
equipments, scaffolding, centering
3 3 form work etc, with finishing as 10814.000 379.00
required to the exposed
surface,making asphalt joints as
directed and watering and curing (
without sleepers ) with all lead
and lifts etc. comp.(Including
Preparing Sub grade for lining)
Providing and laying 7.0 cms thick
cast in situ cement concrete 1:2:4
grade with the use of crushed
aggregates for canal lining works
including use of all equipments,
scaffolding, centering form work
4 4 etc, with finishing as required to m2 14645.000 365.00
the exposed surface,making
asphalt joints as directed and
watering and curing ( without
sleepers ) with all lead and lifts etc.
comp.(Including Preparing Sub
grade for lining)
Providing and laying micro-
concrete of Microkrete or
equivalent from approved
5 5 manufacturer in line and level to m2 194.000 408.00
match with exixting layer, curing
excluding form work etc complete
as directed. (10 mm thick)
Proving & fixing MS welded mesh
jali of 2.8 mm dia 65mm x 65mm
6 6 including cutting in required sizes, m2 8441.000 142.00
fixing in canal prism etc. complited
by Engineer in charge.
Providing and Laying HDPE Liner
of 750 micron in bed and slopes of
7 7 canal at required level below lining m2 8441.000 185.00
as per drawing and as directed etc.
Providing and laying CC 1:2:4
grade using cement, sand and
crushed metal incuding providing
and erecting necessary form work,
centering,vibrating, smooth
finishing,watering and curing as
directed with all leads and lifts etc
complete. (a) Sub structures
Excavation in all sorts of soil
(including wet and slushy
condition of soil) with yellow,
sandy, gravelly soil including soft
murrum & H.M. including sorting
& stacking and depositing the
9 9 excavated stuff in uniform layers m3 170.000 79.00
as and where directed upto lead of
30 m and lift as shown below
including clearing the site etc.
compute (including dewatering)
(B) For foundation trenches of
C.D. work (a) 0 to 3 Mt. depth
Backfilling with selected earth
including remaining consolidation
10 10 including watering with lead as m3 60.000 67.00
under and all lifts etc. completed
Providing and laying RCC 1:1.5:3
grade by using cement, sand and
crushed metal for different items
like copping work, pier cap,
abutment cap, Wearing coat, Skin
concrete, Solid slab upto 60 cm.
thick, Barrel of canal syphons,
barrel of R.C.C. through, & beams
for foundation and super structure
as per approved design including
providing necessary centering,
shuttering and form work,
vibrating, smooth finishing,
watering and curing as directed
with all leads and lifts etc.
TOTAL COST IN RS. Rs.
I/We am/are willing to carry out the work at… ...................... % above/belows percent (Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our
tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
(B) For Item Rate Tender (For above INR 50 Cr.):
Item Description of Item Quantity Unit Rate Amount
No (with brief specification
and reference to book of In In
specifications) figures Words
(A) Total Tendered Amount
(B) Rebate on above tendered amount (if any) % (in figure) ………………………………
(C)Net Tendered Amount (A-B) (in figure) ………………………………
1 The Contractor shall exhibit a board with detailed specification and details of work as
directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt. G.R.: CE(QC)/PB/Mix Design/04/2024 Date:20/01/2024 as stated in
S.O.R. therefore in R.C.C. items where there is a change as per actual mix design the cost
of difference of cement consumption have been deducted from the rate of original item
at the rate of input rate mentioned in all the tender.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Approved Bank list.pdf
Approved Cement.pdf
Approved Steel.pdf
BOQ Branch NST.pdf
Final SBD Branch NST.pdf
ITEM SPECIFICATION Branch NST .pdf
NIT RBC_NST.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .