| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹3.8 LAccepted-AOC | 1 | Accepted-AOC 1 | |
| 2 | 2₹3.9 L+₹16,063.67 (4.24%)Rejected-AOC | 2 | Rejected-AOC 2 | |
| 3 | 3₹4.2 L+₹40,847.42 (10.8%)Rejected-AOC | 3 | Rejected-AOC 3 |
| Sl No | Description | Qty | Unit | E.S.ABOOBACKER L3 | LEO PAUL L2 | THOMAS GEORGE L1 |
|---|---|---|---|---|---|---|
| 1.00compound wall | ||||||
| 1.00 | 2.7.2:Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Hard rock (requiring blasting) | 14.85 | cum | 815.33 ₹12,107.65 | 767.16 ₹11,392.33 | 735.94 ₹10,928.71 Lowest |
| 1.00 | OD77378/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials at site | 13.05 | cum | 3,650.02 ₹47,632.76 | 3,434.37 ₹44,818.53 | 3,294.6 ₹42,994.53 Lowest |
| 1.00 | 5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 4.35 | cum | 9,107.03 ₹39,615.58 | 8,568.97 ₹37,275.02 | 8,220.24 ₹35,758.04 Lowest |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 0.2 | cum | 7,250.66 ₹1,450.13 | 6,822.28 ₹1,364.46 | 6,544.63 ₹1,308.93 Lowest |
| 1.00 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 1.44 | sqm | 352.95 ₹508.25 | 332.09 ₹478.21 | 318.58 ₹458.76 Lowest |
| 1.01 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 5.04 | sqm | 921.51 ₹4,644.41 | 867.35 ₹4,371.44 | 832.05 ₹4,193.53 Lowest |
| 1.01 | 5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 0.98 | cum | 11,673.77 ₹11,451.97 | 10,984.07 ₹10,775.37 | 10,537.04 ₹10,336.84 Lowest |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 339.48 | kilogram | 102.76 ₹34,884.96 | 96.68 ₹32,820.93 | 92.75 ₹31,486.77 Lowest |
| 1.01 | 50.6.1.1:Solid block masonry using pre cast solid blocks ( factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part 1 of 1979 for foundation and plinth with thickness 20 cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete | 23.34 | cum | 5,856.93 ₹1,36,700.75 | 5,510.9 ₹1,28,624.41 | 5,286.62 ₹1,23,389.71 Lowest |
Tender Value
₹4.6 L
EMD Value
₹11,474
Closing Date
4 Aug 2025, 1:00 pmClosed
Assistant Engineer
Assistant Engineer LSGD, LID and EW Section, Kalloorkad G.P. 686668
Annual Plan- KALLOORKAD G.P. PRO.NO.27/26. CONSTRUCTION OF COMPOUND WALL AND YARD AT AYURVEDA HOSPITAL WARD 4.
2025_LSGD_779478_1
12/T1/26/AE/KKD/LSGD
Open Tender
Civil Works - Buildings
Item Rate
120 days
Kalloorkad G.P.
Please refer Tender documents.
11 documents required · 11 mandatory
₹1,015
Yes
₹11,474
Yes
8 Sept 2025
28 Jul 2025
5 Aug 2025
28 Jul 2025
4 Aug 2025
28 Jul 2025
Amount
compound wall
2.7.2:Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Hard rock (requiring blasting)
OD77378/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials at site
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.1.1:Solid block masonry using pre cast solid blocks ( factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part 1 of 1979 for foundation and plinth with thickness 20 cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete
13.1.2:12 mm cement plaster of mix:1:6 (1 cement : 6 fine sand).
10.25.2:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work
13.42.1:Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gms/litre, of approved manufacturer, of required shade and colour complete, as per manufacturer's specification. Two or more coats on new work Two or more coats on new work
LEO PAUL (BID ID -2268782)
E.S.ABOOBACKER (BID ID -2272189)
Bidder Name
E.S.ABOOBACKER
THOMAS GEORGE
LEO PAUL
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1277142.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .