Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹49.0 L
EMD Value
₹97,980
Closing Date
25 Nov 2026, 6:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
GE (I) DM Visakhapatnam
GE (I) DM Visakhapatnam
PREVENTIVE MAINTENANCE OF 132 KV GIS SYSTEM AND ALLIED WORKS AT MRS AT NAVAL DOCKYARD VISAKHAPATNAM UNDER GE (I) DM VISAKHAPATNAM
2026_MES_797306_1
8616/C/E8
Open Tender
Electrical and Maintenance Works
Item Rate
270 days
Naval Dockyard Visakhapatnam
As per tender document
8 documents required · 8 mandatory
₹500
GE (I) DM Visakhapatnam
₹97,980
Yes
4 Nov 2026
4 Nov 2026
27 Nov 2026
4 Nov 2026
25 Nov 2026
18 Nov 2026
5 Nov 2026 - 16 Nov 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | M&L for carrying out M2 level preventive maintenance of 132KV GIS system including inspection , Servicing, testing and submission of detailed service and test reports for all bay/ compartments by OEM i.e service Engineer of GE T&D India Ltd (Formerly Areva) complete all as specified and directed :-
(a) SF6 Gas test & checks : Dew point measurement SF6 purity check {% measurement} Alarm check for density switches optional Gas leak test.
(b) Circuit Breaker mechanical test :- Visual inspection of spring operated mechanism mannually on/off spring-operated mechanism optical indicator( spring on/off) position check.
(c) Electrical test :- Breaker timing test, Auxiliary contact change over position, check spring charge motor current measureas & time measurement, heater current measurement. | 1 | Each Job | - | - |
| 1.01 | (d) Disconnector/Earthing switches mechanical test :- Mannually on/off with hand crank optical position indication check for change over, insulated earth switch external earthing link installation & tightness check.
(e) Contact resistance check :- Test as per circuit proposed during commissioning.
(f) Current & voltage transformer/Local control cubicle :- Terminal tightness check and wquipment operational and alram test.
(g) Interlock & scheme verification : Complete checking of elect and Mech intrlocks for safe operation of GIS eqpt.
(h) Auxiliary systems check : Checking of heaters, space haters, lighting, AC/DC supply, MCBs, fuses and healthiness of control panels
(j) Tightness & Housekeeping :- Checking of all accessible fasteners, termial connections , earhing connections and general cleaning of panels and GIS area | - | - | - | - |
| 2 | Supply of following consumable kit for M2 maint :-
(a) Isopropyl alcohol - 20 ltr
(b) Lint free tissue paper for cleaning - 10 Roll
(c) Locatitie 8103 Lubricant - 20 Kg
(d) Fomblin grease UT18 - 100 Gm
(e) Molykote 111 grease with grease gun
(f) SF6 leak detector foam spray bottles
(g) Breaker Mech door beadings. | 1 | Each Job | - | - |
| 3 | M&L for copper strip 32 x 6mm with saddle and fixing screws, including insulating block for connection of pit to bldg test point complete all as specified and directed. | 380 | RM | - | - |
| 4 | M&L for copper strip 75 x 10mm with saddle and fixing screws, including insulating block for connection of pit to bldg test point complete all as specified and directed by Eng-in-charge. | 50 | RM | - | - |
| 5 | M & L for casting Chemical earth pits with Pipe in Pipe technology 50 mm Cu bonded , 200 microns, 3 Mtr Long Earth Electrode targeted/ achieving individual earthpit result from 1.5 ohms upto maximum of 5.0 ohms for each individual pit and by maintaining of expected Grid value of 0.20 ohms but less than 0.5 ohm for grid earth pits as in around individual technical building with the following items, specifications and testing complete for each pit complete all as specified and directed.
(i) Boring 300 mm dia of earth pit in soft and loose soil upto the depth of not less than 2.5 m deep below ground level by means of any method i.e boring/ digging including removal of excavated material to a distance of 50 m as directed by Engr-in-charge in each pit.
(ii) Filling the each bore hole with 10 kg thick compacted layer of earth enhancing compound to reduce the soil resistivity as per Clause 14.5d of IEEE 80:2000 (latest Edition) of make Terec+ as per manufacturers specifications. | 15 | Each Job | - | - |
| 5.01 | (iii) Placing of 3 m length of 50mm dia of copper bonded pipe-in-pipe earth electrode with welded copper plate 38mmx200mm of 12mm thick on top. The earth rod should be placed at centre of each bore hole/earth pit with minimum of 10 kg inserted in to Terec+ layer
(iv) Back filling with earth enhancing compound up to earth pit GL to reduce the soil resistivity as per clause 14.5b of IEEE 80:2000 (latest Edition) of make Earthcon upto the ground.
(v) Connecting/Jointing/brace welding each electrode of earth pit serially with copper earthing strip 25X3 mm with minimum 3 m distance between two earth pits buried below GL in trench filled with earth enhancing compound to reduce the soil resistivity as per Clause 14.5b of IEEE 80:2000 (latest edition) by enhancing its ionic properties, dispersion properties, hygroscopic properties, expansion properties, diffusion properties etc, incl earth excavation complete all as directed by Eng-in-charge. | - | - | - | - |
| 5.02 | (vi) Placing 500X500X250 mm HDPE earth pit cover (IEC 62561-5) flushed with ground placed over 100mm thick PCC (1:3:6 Type I) of size 550 x 550 mm including required earth excavation, refilling and packing. The earth pit cover should be UV stabilized, lockable jam free lid, stackable design, resistant to substances including petrol oil, diesel, bitumen and concrete etc
vii) The quoted rate is deemed to be inclusive of necessary removal of excavated soil to a distance of 50 mtr as directed by the Engr-in-Charge.
viii) Any other requirement if desired by the Engr-in-Charge as per site conditions shall be provided by the contractor without any extra cost.
Note:
a) The earth pits should have a minimum distance of 3m from each other and a minimum distance of 2m from building walls
b) If grid value is found less than 0.5 ohms then the contractor will re-execute earth pits or put addl pit with no extra cost to the Govt. | - | - | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.30 MB
8616Tender.pdf
Tender Documents • 0.99 MB
BOQ_894338.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .