Loading…
Loading…
Tender Value
₹46.6 L
EMD Value
₹1.1 L
Closing Date
21 Sept 2026, 5:00 pm
Executive Engineer, CD, PWD, Khatima (U.S. Nagar)
Office of The Executive Engineer, C.D., P.W.D., Khatima (U.S. Nagar)
Improvement and repair work of road number-53 under SIDCUL Sitarganj Phase-1 Block-C under deposit item.
2026_pwd_99946_1
EE TN 1751/5AC Date 03-09-2026
Open Tender
Civil Works - Roads
Item Rate
180 days
Sitarganj
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,720
EE, CD, PWD, Khatima (U.S. Nagar)
₹1.1 L
9 Sept 2026
9 Sept 2026
22 Sept 2026
9 Sept 2026
21 Sept 2026
9 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Wet Mix MacadamProviding, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. (By Mechanical Means with 1 km lead) | 450 | Cum | 2,944.2 | ₹13,24,890 |
| 2 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 | 2,250 | SQM | 40.46 | ₹91,035 |
| 3 | Providing and laying Dense Bituminous Macadam with the use of batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.25% by weight of total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.Grading II - 26.5mm nominal size | 112.5 | CUM | 8,908.1 | ₹10,02,161.25 |
| 4 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. | 4,500 | SQM | 11.2 | ₹50,400 |
| 5 | Providing and laying Bituminous Concrete with the use of batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects for Grading-II (bituminous binder @ 5.4 % of mix) | 90 | CUM | 10,407.8 | ₹9,36,702 |
| 6 | Providing and laying of hot applied thermoplastic compound of ISI Mark Approved Quality of 2.5 mm thick including reflectorising glass beads @250 gms per sqm area, as per IRC:35 .The finished surface to be level,uniform and free from streaks and holes. | 112.5 | SQM | 522.7 | ₹58,803.75 |
| 7 | Cast in Situ Cement Concrete M 20 Kerb with Channel-Construction of cement concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M15 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCCM20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 409 | 240 | RMT | 309 | ₹74,160 |
| 8 | Painting Two Coats on New Concrete Surfaces Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new, plastered / concrete surfaces as per drawing and Technical Specification Clause 1701 | 30 | SQM | 108.7 | ₹3,261 |
| 9 | Excavation for Structures Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. Upto 3 m depth. | 13.14 | CUM | 378.1 | ₹4,968.23 |
| 10 | Providing concrete for plain/ reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 P.C.C. grade M 20 | 16.2 | CUM | 6,016.3 | ₹97,464.06 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.62 MB
BOQ_117860.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .