Loading…
Loading…
Tender Value
₹4.5 L
EMD Value
₹5,621
Closing Date
25 Sept 2026, 5:00 pmClosed
Dr. Sunny Rao
Office of the Project Officer,WJ Area
Belt Transporting, cable hanging , cleaning, jsdb 30 switch and cable , rope transporting and laying and other misc. in Moonidih colliery, W J Area
2026_BCCL_365476_1
BCCL/WJA/MND/SUR/2026-27/29
Open Tender
Miscellaneous Works
Percentage
15 days
Moonidih Colliery, WJ Area
Please refer to NIT.
11 documents required · 11 mandatory
₹5,621
15 Sept 2026
15 Sept 2026
28 Sept 2026
15 Sept 2026
25 Sept 2026
15 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Belting Transporting,cable hanging , cleaning,jsdb 30 switch & cable , rope transporting & laying & other misc in Moonidih colliery, W J Area | |||||
| 1.01 | Belting works - 780 m belt removal from E9 dyke & transportation to zero level Manshift required= 8 manshift x 10 shift = 80 manshift, Total = 80 no | 80 | nos | 1,437.6 | ₹1,15,008 |
| 1.02 | Manual transportation of JSDB-19 winch including switch (GEB) from surface to 6th dip near JSDB 30 winch & power cable from D 18 top gate to d18 main gate near 6th dip junction. For Switch(GEB):8 Manshiftx 1shift=08 Manshift For Power cable: 8Manshiftx 1shift=8 Manshift Total: 16 no | 16 | nos | 1,437.6 | ₹23,001.6 |
| 1.03 | Cable hanging works from zero level to E9 main gate 4th rise junction near E9 Top Gate . Manshift required= 8manshift x 4shift= 32manshift(un-skilled) | 32 | nos | 1,437.6 | ₹46,003.2 |
| 1.04 | Misc job such as different matiral ie belt, chanae etc workin M1 belt Manshift required= 6 manshift × 7shift = 42 manshift (Unskilled). | 42 | nos | 1,437.6 | ₹60,379.2 |
| 1.05 | LHD 4 pump shifting, For :analysis 6 uskilled manshift transport 12m by chai pulling 1 item. cost 1 item= (1367.6 x6)/12= 683.80 . for 2 item 2 x 683.8 =1367.6/m . | 50 | m | 1,437.6 | ₹71,880 |
| 1.06 | .pump installation and commissioning - 6 manshift × 2 shift = 12 manshift | 12 | manshift | 1,437.6 | ₹17,251.2 |
| 1.07 | Rope laying and transportation from surface to DR3 ROK E9 TG to D18 BG , lay out 5th to 9 th rise D18 BG. Analysis 8 unskilled manshift and 4 shift is required | 32 | manshift | 1,437.6 | ₹46,003.2 |
| 1.08 | Endless BD motor and controller loading in trolly ,transport from 4th rise E9 TG to 0 level analysis 8 manshift 1shift is required. | 8 | manshift | 1,437.6 | ₹11,500.8 |
| 1.09 | Add CP 15% as per clause 4.17.1 of Civil Eng. Manual & BCCL SOR | 1 | Units | 58,654.08 | ₹58,654.08 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.60 MB
BOQ_378410.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .