Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹39.2 L
EMD Value
₹40,000
Closing Date
2 Nov 2026, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Office of the Executive Engineer, Bhavnagar Irrigation Division, Bhavnagar
Jungle Cutting, Desilting & Earth work in between mile 0 to 55 of main canal of S.L.B.M.C. Talaja for the year 2026-27
356640
21 For 2026-27
Open
Civil Works - Water Works
Works
Bhavnagar
13 documents required · 12 mandatory · 1 optional
₹1,500
EXECUTIVE ENGINEER, BHAVNAGAR IRRIGATION DIVISION BHAVNAGAR
₹40,000
18 Oct 2026
18 Oct 2026
18 Oct 2026
2 Nov 2026
18 Oct 2026
120 days
Item Rate In
specification and reference to book of Quantity Unit Amount
No figures
specifications)
ITEM NO-1 300900.00 Sq.m 1.20
Jungle clearance of specified category and bushes
for canal /dam work as directed with depositing
material etc .complete (Excluding tree of grith
above 0.5 mt. (A)upto 2 year old (b) For
1 medium dence.
ITEM NO.2 13.21 Km 40529.00
Clearing the canal by cleaning/removing the thick
weed, shrubs and all other vegetations including silt
2 upto 10cm thickness,stones,debris etc from canal
bed and side slope of canal upto outer toe of canal
bank and disposing as directed
j) For canal capacity from
ITEM NO.3 11.25 Km 36387.00
Clearing the canal by cleaning/removing the thick
weed, shrubs and all other vegetations including silt
3 upto 10cm thickness,stones,debris etc from canal
bed and side slope of canal upto outer toe of canal
bank and disposing as directed
i) For canal capacity from 300.0 to 400.0 cusecs.
ITEM NO.4 10.32 Km 30175.00
Clearing the canal by cleaning/removing the thick
weed, shrubs and all other vegetations including silt
4 upto 10cm thickness,stones,debris etc from canal
bed and side slope of canal upto outer toe of canal
bank and disposing as directed
h) For canal capacity from 200.0 to 300.0 cusecs.
ITEM NO.5 30.72 km 26329.00
Clearing the canal by cleaning/removing the thick
weed, shrubs and all other vegetations including silt
5 upto 10cm thickness,stones,debris etc from canal
bed and side slope of canal upto outer toe of canal
bank and disposing as directed
g) For canal capacity from 100.0 to 200.0 cusecs.
ITEM NO.6 6.78 Km 19525.00
Clearing the canal by cleaning/removing the thick
weed, shrubs and all other vegetations including silt
6 upto 10cm thickness,stones,debris etc from canal
bed and side slope of canal upto outer toe of canal
bank and disposing as directed
f) For canal capacity from 50.0 to 100.0 cusecs.
ITEM NO.7 4.73 Km 14791.00
Clearing the canal by cleaning/removing the thick
weed, shrubs and all other vegetations including silt
7 upto 10cm thickness,stones,debris etc from canal
bed and side slope of canal upto outer toe of canal
bank and disposing as directed
e) For canal capacity from 25.0 to 50.0 cusecs.
ITEM NO.8 3480 cum 166.00
Clearing the silt from canal /drain bed by digging
the same to the required bed level and gradient
8 including depositing the excavated earth regularly
on spoil bank for utilising the same for preparing
the bund after bracking the clods as and where
directed for lead upto 30 mt and lift as under. (
Excluding weed cutting) (a) Depth 0 to 3.0 mt
ITEM NO.9 325.00 cum 78.00
Earth work in embankment from borrow pits in all
sort of soil and soft murrum or other suitable strata
as directed incl breaking clods and dressing to the
9 design section with lead as under and all lift
incl.site clearance etc comp. For all canal capacity
& Without rolling and watering lead 200 to
ITEM NO.10 3180.00 cum 215.49
Providing murram including spreading the same
and dressing the Side slope & top surface in
10 required grade and camber with lead upto 5.0 km
etc complete.
ITEM NO.11 1 No 5000
Drone videography of work befor and after
11 completion
I/We am/are willing to carry out the work at… ....................... % above/below percent
be written in figures and words) of the estimated rate mentioned above. Amount of my
/our tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Jungle Cutting Desilting and Earth work in mile 0 to 55.pdf
BOQ Jungle Cutting Desilting and Earth work in mile 0 to 55.pdf
Tender Notice No.21 For 2026-27.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .