Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.4 CrAdmitted-Finance | -16.01% | ₹1.4 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.4 Cr+₹3.4 L (2.43%)Admitted-Finance | -13.97% | ₹1.4 Cr+₹3.4 L (2.43%) | L2 | Admitted-Finance |
| 3 | L3₹1.5 Cr+₹6.4 L (4.63%)Admitted-Finance | -12.12% | ₹1.5 Cr+₹6.4 L (4.63%) | L3 | Admitted-Finance |
| 4 | L4₹1.5 Cr+₹8.4 L (6.02%)Admitted-Finance | -10.95% | ₹1.5 Cr+₹8.4 L (6.02%) | L4 | Admitted-Finance |
| 5 | L5₹1.6 Cr+₹21.8 L (15.8%)Admitted-Finance | -2.78% | ₹1.6 Cr+₹21.8 L (15.8%) | L5 | Admitted-Finance |
Tender Value
₹1.7 Cr
EMD Value
₹3.3 L
Closing Date
4 Mar 2026, 6:00 pmClosed
EE, RSAMB, Jodhpur-I
EE, RSAMB, Mandore mandi Jodhpur-I
Construction of Classroom and Laboratory in Govt. Women Polytechnic College at Jodhpur, District- Jodhpur.
2026_RSAMB_541039_1
NIT-10/2025-26(2)
Open Tender
Civil Works
Percentage
240 days
Jodhpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,000
ICICI Bank A/C No 683401030887 IFSC ICIC0006834
₹3.3 L
Yes
7 Mar 2026
21 Feb 2026
6 Mar 2026
21 Feb 2026
4 Mar 2026
21 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils | 1,785 | Cum | 178 | ₹3,17,730 |
| 2 | Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per MoRTH Specification Clause 301.3 | 493 | Cum | 31 | ₹15,283 |
| 3 | Carriage of Earth, Sand, Lime, Morrum manure or sludge For 15 Km. Lead beyond 1 Km Lead | 493 | Cum | 205 | ₹1,01,065 |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including lead up to 50 meter and with all lift. | 1,800 | Cum | 64 | ₹1,15,200 |
| 5 | Add extra for foundation/trenches/drains for every additional lift of 1.5 Mtr. or part thereof in All kinds of soil | 303 | Cum | 34 | ₹10,302 |
| 6 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1 m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared. | 1,016 | Sqm | 5 | ₹5,080 |
| 7 | Extra for covering top of membrane with Geotextile, 120gsm non woven, 100% polyester of thickness 1 to 1.25mm bonded to the membrane with intermittent touch by heating the membrane by Butane Torch as per manufactures recommendation. | 80 | Sqm | 56 | ₹4,480 |
| 8 | Anti termite treatment of floor using Imidacloprid 30.5% EC non repellent, odorless, low dose, environmentally safe terniticide with rapid action non corrosive stain free, by drilling 12mm diameter holes 300mm apart injecting the emulsion as per specification and plugging with cement mortar 1:2 ( 1 cement : 2 coarse sand) in the whole floor area DPE 12mm dia termitube system with required number of junction boxes are to be installed. The termitube will run all along the perimeter wall both inside and outside. In the middle area the termitube to be installed at an interval of 1.00 Mtr. or less both ways as required with sufficient number of junction boxes to pump the emulsion. After successful testing of termitube, pesticide emulsion of imidacloprid 30.5% EC mixed with water in the ration of 1:474 will be pumped by a motorized spray pump from the junction box in specified manner. The plinth area of the area treated will be measured for payment. | 791 | Sqm | 216 | ₹1,70,856 |
| 9 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). | 260 | Cum | 3,302 | ₹8,58,520 |
| 10 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement.
M20 grade Nominal Mix / Design Mix Add extra for providing richer mixes respectively at all floor levels Providing M-25 grade concrete by using cement as per codal provision instead of M-20 grade design mix. | 222 | Cum | 5,003 | ₹11,10,666 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.17 MB
Bid_Document.pdf
Tender Documents • 11.39 MB
BOQ_964511.xls
BOQ • 0.57 MB
Bid_Document.pdf
PDF • 11.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .