Loading…
Loading…
Tender Value
₹25.2 L
EMD Value
₹25,200
Closing Date
29 Sept 2026, 5:00 pm7d left
Superintending Engineer
Superintending Engineer, M.I. Division, Jeypore
Improvement to Dandabadi MIP in Bandhugaon Block of Koraput District under Critical Scheme 2026-27.
2026_CEMIB_140890_7
MIDJEY06/2026-27
Open Tender
Civil Works - Water Works
Percentage
90 days
Bandhugaon
Please refer tender documents
2 documents required · 2 mandatory
₹6,000
₹25,200
Yes
14 Sept 2026
14 Sept 2026
30 Sept 2026
14 Sept 2026
29 Sept 2026
14 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing shrub Jungles uprooting stumps and small bushes and trees below 1M girth on premeasurement etc. complete as directed by engineer-in-charge | 3,000 | One Sqm | 0.27 | ₹809.1 |
| 2 | Earth work in ordinary soil with all leads and lifts including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.30m in depth to proper profile etc, with supply of all labour and T&P required for the work including Royalty etc, complete in all respect as directed by the Engineer-in-Charge. | 236.25 | One Cum | 175.43 | ₹41,445.34 |
| 3 | Dismantling and removing lime or cement concrete flooring 7.5cm o 10cm thick including stacking the useful materials for reuse & removing the debries with all lead from work site with all labour T&P required for the work etc, complete as per directed by the Engineer-in-Charge. | 218.25 | One Cum | 877.16 | ₹1,91,440.17 |
| 4 | Excavation of foundation in hard soil or gravely soil with all leads and lifts and delifts including dressing and leveling the bed to proper slope and level & making it fit for laying concrete & removing the debris clear of work site with all leads and lifts and delifts including dewatering from foundation if necessary etc complete in all respect as directed by the Engineer-In-Charge. | 163.69 | One Cum | 282.89 | ₹46,306.26 |
| 5 | Filling in foundation and plinth with good quality sand in foundation bed with all leads and lifts including watering and ramming and compaction including cost, conveyance and royalty of the material etc complete as directed by the Engineer-in-charge. | 109.13 | One Cum | 725.56 | ₹79,176.74 |
| 6 | Cement concrete in M15 grade using 20 mm down graded size crusher broken granite chips of approved quality quarried and free from weathered skin and foreign materials including mixing the materials by use of concrete mixtures and laying concrete in layers not exceeding 0.15 m in depth to required level curing vibrating with vibrators, finishing etc with all leads lifts and delifts complete in all respect to proper profile and leveling including dewatering if necessary and cost, conveyance and royalty and other taxes etc of materials including hire & running charges of the machineries complete as directed by the Engineer - in - Charge. | 54.56 | One Cum | 5,344.67 | ₹2,91,615.88 |
| 7 | Reinforced Cement Concrete M20 grade with crushed granite 20mm down graded hard granite crusher broken chips of approved quality free from skin materials mixing by concrete mixer including hoisting lowering and laying the concrete in position to proper slope and level and compacting by vibrators in layers not exceeding 0.15m depth and finishing the exposed surface smooth including watering, curing for required period cost, conveyance, hire and running charges of all machineries, royalty and other taxes of all materials labour, T & P materials required for this item etc, complete as directed by the Engineer in charge. | 174.6 | One Cum | 5,794.7 | ₹10,11,754.62 |
| 8 | Providing and removing after casting rigid and smooth centering and shuttering for RCC and CC works with nominal reinforcement, cutting, bending, binding and dismantling them after casting including cost, conveyance, royalty and other taxes of all materials required for the work etc. complete as per direction of the Engineer-in-charge (For F & P) | 1,309.5 | One Sqm | 249.86 | ₹3,27,191.67 |
| 9 | Straightening, cutting, bending, binding, fitting and placing uncoated HYSD bar reinforcement and laying in position including cost of binding wire 18 to 20 gauge and fixing of reinforcement including lapping where necessary with all leads, lifts from bending yard to placement spot including cost ,conveyance & all taxes of reinforcement as directed by the Engineer-in-charge. | 50.85 | One Qntl | 9,465.25 | ₹4,81,326.89 |
| 10 | Earth work in Hard soil with all leads and lifts including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.30m in depth to proper profile etc, with supply of all labour and T&P required for the work including Royalty etc, complete in all respect as directed by the Engineer-in-Charge. (Measurement to be taken on finished level section) | 195.32 | One Cum | 235.73 | ₹46,042.78 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.59 MB
Dandabadi.pdf
Tender Documents • 5.07 MB
BOQ_609577.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .