ExecutiveEngineerKWAPalakkad
Executive engineer P H division KWA Palakkad
AMRUT AMRUT 2.0 Palakkad Muncipality Providing new House Connections and carrying out works in Pipelines to improve water supply levels in the connections Sekharipuram Part1 Pipeline Work
2023_KWA_580675_1
20/23-24/EE/PH/PKD
Open Tender
Civil Works - Water Works
Item Rate
180 days
Palakkad
Please refer Tender documents.
5 documents required · 5 mandatory
₹2,760
₹50,000
11 Aug 2023
8 Jun 2023
20 Jun 2023
8 Jun 2023
19 Jun 2023
8 Jun 2023
Amount
Cost of materials
100.98.216:Supply of PVC Pipe, 6kg/cm2, 160mm Dia.
100.98.213:Supply of PVC Pipe, 6kg/cm2, 90mm Dia.
OD60015/2023-2024:Supply of 150mm GI pipe
18.12.8:Providing and fixing G.I. pipes complete with G.I fittings including trenching and refilling etc. External work80 mm dia nominal bore
100.98.460:Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 150mm.
100.98.449:Supply of CI Air Valve with Flanges, Conforming to IS 14845 - 2000, Kinetic Air Valve Type DS1, Size 50mm.
18.17.4:Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) :50 mm nominal bore
OD60016/2023-2024:Cost of PVC Specials
OD60017/2023-2024:GI Specials
Wroking Charges
100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
100.59.1:Cutting the bituminous / concrete roads with cutting machine for a minimum depth of 200mm along the sides of proposed alignment of the pipe to be laid without causing any damage to other utilities, including the charges for hire and conveyance of tools and plant, cost of consumables and charges for lighting, watching, ribbon fencing, caution boards, traffic diversion, and as per the direction of departmental officers etc. complete, before carrying out the demolition of bituminous / concrete road by mechanical means and carrying out the excavation.
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
16.42:Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete
16.78.2:Construction of granular sub- base by Providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, Carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in- Charge.With material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBR Value-25
100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
100.9.11:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 160 mm nominal outside diameter pipes.
100.9.8:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 90 mm nominal outside diameter pipes.
100.12.11:Conveying and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc., but excluding cost of pipes and fittings for External work: 150mm diameter nominal bore.
100.31.2.4:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 150mm diameter, Class II.
100.32.3:Conveying and fixing C. I. Double Acting Air Valve of approved quality with bolts, nuts, rubber insertions etc., complete, but excluding the cost of air valve (tail pieces, if required, will be paid separately): 50mm Double Acting Air Valve.
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
100.60.14.1.1:Providing 15mm (1/2 inch) house connection with 15mm water meter from existing PVC / HDPE mains from 140mm to 200mm dia., up to a length of 5 m using 20mm ( 1/2 inch ) PE Pipe, PE80, PN16, Conforming to IS 4984: 2016 or later edition and PP PN 16 Compression / GM / Brass specials viz. brass ferrule, brass hexagonal nipple, GM full way wheel valve, bend, MTA, FTA, couplers, PVC Service Saddle of suitable size etc. and connecting with the mains, testing the joints etc. complete including trenching and refilling in all kinds of soil up to a depth of 1.50m for main line tracing and trench of average cross section 0.3m x 0.75m for laying connection pipe and service pipe, fixing water meter, lighting, watching, providing caution boards, traffic control etc. complete including cost of materials, hire for tools, cost of consumables and labour charges but excluding cost of water meter and meter box and excluding charges for cutting the concrete / tarred / bituminous roads etc, and as per the direction of the departmental officers.
OD60012/2023-2024:LINKING OF DI/CI OF VARIOUS SIZES
100.60.15.1.1:Providing additional length of house connection pipe using 20 mm (1/2 inch) PE Pipe, PE80, PN16, Conforming to IS 4984: 2016 or later edition and PN16 specials and testing the joints etc., by trenching and refilling in all kinds of soil with trench of average cross section 0.3m x 0.75m for laying of connection pipe and service pipe, lighting, watching, providing caution boards, traffic control etc., including cost of materials, hire for tools, cost of consumables and labour charges etc. complete, but excluding the cost of cutting of concrete / tarred / bituminous roads etc., and as per the directions of the department officers.
OD60013/2023-2024:providing and fixing 200mm dia or nearest size Protection tube/AC pipe bit or PVC bit for length of 1.5m long as protection for 150mm or below size valves and air valves in the pipe line
PWD Road Restoration
4.2.A.1:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-III -For lower sub-base - Mix in Place Method
4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.
5.2.b:Providing and applying tack coat with bitumen emulsion (RS) using emulsion pressure distributor at the rate of 0.25 - 0.30 kg per sqm on the prepared Granular Surface cleaned with mechanical broom.
5.3.2.a:Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with a bituminous binder (VG 30), transported to the site, laid over a previously prepared surface with paver finisher to the required grade, level, and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction For Grading II - (19 mm nominal size)
5.6.2.a:Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level, and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects For Grading - II (13.2 mm Nominal Size)
OD60011/2023-2024:Supply, stacking, spreading and consolidating of Quarry Muck in the trench of pipe line, including carriage, loading, unloading & stacking up to any lead.
LSGD Road Restoration
4.2.A.1:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-III -For lower sub-base - Mix in Place Method
4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.
5.9.1.a:Providing, laying and rolling of open-graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates using Viscosity Grade paving Bitumen( VG -30) to the required line, grade, and level to serve as wearing course on a previously prepared base, including mixing in a suitable HMP of appropriate capacity not less than 75 tonnes/hour, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to the required level and grades.
5.2.b:Providing and applying tack coat with bitumen emulsion (RS) using emulsion pressure distributor at the rate of 0.25 - 0.30 kg per sqm on the prepared Granular Surface cleaned with mechanical broom.
5.10.1.a:Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade, and cross fall using crushed stone chipping of 6.7 mm size and bitumen (VG-30) @ 9.8 kg per 10 sqm
OD60014/2023-2024:Supply, stacking, spreading and consolidating of Quarry Muck in the trench of pipe line, including carriage, loading, unloading & stacking up to any lead.
P T JOSHY
Bidder Name
P T JOSHY
Jayanandan
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.PDF
finance_857487.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .