Tender Value
₹27.7 L
EMD Value
₹27,700
Closing Date
26 Oct 2026, 5:00 pm
City Engineer, Vapi Municipal Corporation, Vapi
Construction of RCC Road At Internal Road of Salvav Dadri Faliya in Ward No.2, Vapi for Vapi Municipal Corporation.
353204
03/2026-27
Open
Civil Works - Roads
Works
Vapi
16 documents required · 14 mandatory · 2 optional
₹1,770
Municipal Corporation City of Vapi
₹27,700
7 Oct 2026
7 Oct 2026
7 Oct 2026
26 Oct 2026
7 Oct 2026
Name of Work : Construction of RCC Road At Internal Road of Salvav Dadri Faliya in Ward No.2, Vapi for Vapi Municipal Corporation.
Memorandum showing Items of Woks to be carried out
Item Quantities Item of Works Tendered Rates. Unit Total Amount According
Item Quantities Item of Works Tendered Rates. Unit Total Amount According
No. Estimated But In Figures In Words to estimated Quantity.
1 may be2 More 3 4 5 6
1 770.00 Box cutting the road surface to proper slope and camber for making a base for road ₹ 207.40 Rupees Two Hundred CuM ₹
work including removing the excavated stuff and depositing on the road side slope Seven Paise Fourty Only
as directed upto 50Mt.lead.
2 220.00 Construction of Granular Sub Base by Providing Coarse Graded Machine crushed ₹ 809.09 Rupees Eight Hundred CuM ₹
B.T. Material Satisfying MORTH Specification of Grading II ( B.T. Stone Agreegate Nine Paise Nine Only
53 mm to 2.36 mm Below - 20% ) Including spreading in unifrom layer with motor
grade on prepared surface, mixing by mix in place method with rotovator at OMC
an COmpacting with Vibratory Roller to Achieve the desired density etc. complete.
3 115.00 Providing and laying cement concrete 1:4:8 (1-Cement : 4- coarse sand : 8- hand ₹ 2,680.21 Rupees Two Thousand CuM ₹
broken stone aggregates 40 mm nominal size) and curing complete excluding cost Six Hundred Eighty Paise
of formwork in (A) Foundation and Plinth. TwentyOne Only
4 274.00 Providing formwork of ordinary timber planking so as to give a rough finish ₹ 171.80 Rupees One Hundred SqM ₹
including centering shuttering strutting and propping etc. Height of propping and SeventyOne Paise Eighty
centering below supporting floor to ceiling not exceeding 4 M. and removal of the Only
same for in situ reinforced concrete and plain concrete work in. (A) Foundations
Footings Bases of Columns etc. and Mass concrete.
5 230.00 Providing and laying in position Ready Mixed M-300 grade concrete for reinforced ₹ 5,080.15 Rupees Five Thousand CuM ₹
cement conctere work , using cement content as per approved Design Mix Eighty Paise Fifteen
manufactured in fully automatic batching plant and transported to site of work in Only
transit mixer for a lead up to 10 kms having continuous agitated mixer,
manufactured as per mix design of specified grade for reinforced cement concrete
work including pumping of R.M.C. from transit mixer to site of laying, excluding
the cost of centering shuttering finishing and reinforcement including cost of
admixtures in recommended proportions as per IS: 9103 to accelerate/ retard
setting of concrete, improve workability without impairing strength and durability
as per direction of the Engineer - in - charge. Without Fly Ash (Min cement level as
per latest IS 456 shall be maintained) (Cement level 475 kg )
6 6900.00 Providing TMT Bar FE 500D reinforcement for R.C.C. work including bending, ₹ 76.21 Rupees SeventySix Paise Kg ₹
binding and placing in position complete upto floor two level TwentyOne Only
7 490.00 Providing and Supplying of Premoulded Bituminous Joint Filler 25 mm Size in ₹ 65.50 Rupees SixtyFive Paise Rmt ₹
Grooves as Per Directed by EIC or Architect. Fifty Only
8 1150.00 Providing and Erection of Tri-Mix Treatment on Concrete Surface Using Concrete ₹ 163.01 Rupees One Hundred SqM ₹
Polishing Machine and Vaccum Dewatering Machine along with its instruments, SixtyThree Paise One
accessories, lead, transport, electricity, etc. all Only
9 172.50 Providing, laying, spreading and compacting graded stone aggregate to wet mix ₹ 828.67 Rupees Eight Hundred CuM ₹
macadam of 150 mm thickness specification including premixing the Material with TwentyEight Paise
water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, SixtySeven Only
laying in uniform layers with paver in sub- base / base course on well prepared
surface with Plant Mix Method and compacting with vibratory roller to achieve the
desired density.
10 50.00 Road marking with hot applied thermoplastic paints with reflectorising glass beads ₹ 367.72 Rupees Three Hundred SqM ₹
on bitumin surface providing and laying a hot applied thermoplastic compound 2.5 SixtySeven Paise
mm thick includingreflectorising glass beads @ 250gms per sqm area, thickness of SeventyTwo Only
2.5mm is excluding of surface applied glass beds as per IRC:35-2015. The finished
surface to be level, uniform and free from streaks and holes. zebra patta /bump
patta lane/center line/ edge line/cut patta. The white color marking should
provide liminance coefficinet on cemend road shalll be min 130 mcd/m2/lux and
Asphalt road shall be min 100 mcd/m2/lux during the service life during the day
time. The marking should meet the performance criteria for night time reflectivity,
wet reflectivity and skid resistance as mentioned in the section-15 of IRC 35-2015.
Warranty for the Retro reflectivity should be two years.
TOTAL Rs. (Round Off) ₹
Rupees TwentySeven Lakh SixtyEight Thousand One Hundred SixtySeven Only
I/ We am /are willing to carry out the work at ………….....………% above/below percent
above /below percent ( should be written in figures and words) of the estimated rates mentioned above.
Amount of tender works out as under.
*Estimate amount *Estimate amount
Put to tender Rs. Put to tender Rs. …
Deduct : % below / % Above Rs Add / Deduct :..: ……………..% above Rs………
Net. Total Rs………………..
In Words Rs. In Words………………………………………………
*( Please strike out whichever is not applicable)
Note-1:- All works shall be carried out as per Public Works Department, Hand Book & other specifications of Division or as directed.
Note-2:- All the columns in Schedule should be filled in digitally & the total of the entries in the last column should be struck by the contractor under his digitally
Note-3:- Rates quoted include clearance of the site (Prior commencement of work & at its close) in all respects & hold good for work under all conditions, site.
Note-4 The payment shall be made after availability fund. The contractor has no any claim in this regard.
Note-5 The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-Charge for which no extra payment shall be made.
Note-6 The labour cess will be deducted as per prevailing rules i.e.1% of the work done.
Note-7 GST and Income tax TDS will be deducted at a source while making payments of bills
Note-8 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt.G.R.:PRC-10/2017 Cement Consumption/16/ C Date : 11/05/2017 as stated in S.O.R.
therefore in R.C.C. items where there is a change as per actual mix design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate
mentioned in all the tender.
Note-9 The rates to be quoted by the contractor must be inclusive of all duties, taxes, and other levies Except GST payable by the contractor under the contract or for any other cause shall be
included in the rates, prices and total Bid Price submitted by the Bidder
Signature of Bidder. Vapi Municipal Corporation
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1.NIT.pdf
2.SBD.pdf
3.Annexue-1 BOQ.PDF
4.1 General Technical Specification.pdf
4.1 Specification-Road Works.pdf
5.GR_compressed.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .