| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹20.5 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹19.3 L−₹1.1 L (5.40%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹20.7 L+₹22,335.23 (1.09%)Rejected-AOC | L3 | Rejected-AOC L3 | |
| 4 | L4₹22.1 L+₹1.6 L (8.05%)Rejected-AOC | L4 | Rejected-AOC L4 | |
| 5 | L5₹22.1 L+₹1.7 L (8.19%)Rejected-AOC | L5 | Rejected-AOC L5 |
Tender Value
₹24.4 L
EMD Value
₹50,000
Closing Date
17 May 2023, 3:30 pmClosed
Executive Engineer
KWA PH DIVISION SOUTH TVPM
DEPOSIT URBAN AGGLOMERATION TVM CORPORATION 2022 23 PHASE 2 PERUNTHANNI WARD PIPE LAYING AT VARIOUS PLACES UNDER WW SECTION KURIATHY
2023_KWA_575835_1
TR/14910/2022_26_2_1/1
Open Tender
Civil Works - Water Works
Item Rate
240 days
KWA PH DIVISION SOUTH TVPM
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,760
₹50,000
Yes
10 Jul 2023
10 May 2023
19 May 2023
10 May 2023
17 May 2023
10 May 2023
Amount
PIPE LAYING WORKS
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
100.9.11:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 160 mm nominal outside diameter pipes.
100.9.9:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 110 mm nominal outside diameter pipes.
100.37.6.1:In situ fabrication of M.S. pipes of size 150mm (I.D.) using 8mm thick M.S. plate including cost and conveyance charges of M.S. plate, all fabrication charges, charges of painting the steel work with two or more coat deluxe multi surface paint to give an even shade over an under-coat of primer etc., complete.
100.37.6.2:Fabricating M.S. flanges of diameter 150mm using 12mm thick M.S. plate including cost and conveyance charges of M.S. plate, all fabrication charges, charges of painting the steel work with two or more coat deluxe multi surface paint to give an even shade over an under-coat of primer etc., complete: For pipes fabricated with 8mm thick M.S. plates.
OD155427/2022-2023:Fabricating MS bends of size 150mm (ID) using 8mm thick MS plate including cost and conveyance charges of MS plate, all fabrication charges, charges of painting the steel work with two or more coat deluxe multi surface paint to give an even shade over an under coat of primer etc.complete.For pipes fabricated with 8mm thick MS plates
100.98.1008:Engaging Coolie.
100.98.1009:Engaging Fitter ( grade 1).
100.7.1:Bailing out water with 5HP engine and pump set including conveyance to the site, erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc., complete.
OD155428/2022-2023:Providing alteration of house connection from the existing main including earth work excavation, supplying and fitting suitable saddle piece, supplying and fitting 20mm brass ferrule 1no, 20mm GM full way wheel valve 1no, bend 1no. union 1no etc. and connecting the newly laid main, testing the joints etc. complete but excluding cost of pipe
OD155429/2022-2023:Interconnection to the existing PVC/AC/CI pipe to the newly laid PVC /AC/CI using convinient specials like PVC/AC/CI Tee,Reducer etc ,including earth work excavation, and all labour charges excluding the cost pipe and specials etc
OD155430/2022-2023:Taking connection from the existing main(Double boring), up to 200 mm PVC/AC/CI Pipe , boring the main, supplying and fitting suitable specials etc. and connecting the newly laid main, testing the joints etc. complete
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
CONSTRUCTION OF VALVE CHAMBER
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
OD155431/2022-2023:Reinforced cement concrete 1:2:4 using 20mm metal including watering,curing,hire charges of form work, centering and shuttering for valve chamber and including the cost of cement 320 kg/m3 and excluding cost of reinforcement
5.22.4:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelHot rolled deformed bars
13.7.2:12 mm cement plaster finished with a floating coat of neat cement of mix:1:4 ( 1 cement : 4 fine sand)
OD155432/2022-2023:Conveying CI MH cover with frame from the deptl store to site and placing in position etc. complete
100.31.1.4:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 150mm diameter, Class I.
100.31.1.2:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 100mm diameter, Class I.
SUPPLYING MATERIALS
100.98.226:Supply of PVC Pipe, 8kg/cm2, 160mm Dia.
100.98.224:Supply of PVC Pipe, 8kg/cm2, 110mm Dia.
100.98.460:Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 150mm.
100.98.458:Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 100mm.
OD155423/2022-2023: Suppling CI MH Frame with cover
OD155424/2022-2023:Supply and laying of 20mm ASTM pipe
OD155425/2022-2023:10% for specials
PANANVILA LABOUR CONTRACT CO OPERATIVE SOCIETY LTD NO T 2002
A SADANANDAN
M ASHOK KUMAR
M/s. Green construction
Bidder Name
A SADANANDAN
M ASHOK KUMAR
ARUNDAS Y R
PANANVILA LABOUR CONTRACT CO OPERATIVE SOCIETY LTD NO T 2002
M/s. Green construction
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .