Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.4 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹11.8 L+₹46,743.04 (4.11%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | Rejected-Technical | - | Rejected-Technical L3 |
Tender Value
₹13.4 L
EMD Value
₹20,070
Closing Date
18 Nov 2021, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Executive Engineer LSGD Division Kannur
Executive Engineer LSGD Division Kannur
Kannur DP Proj No.204/21-22 Muzhakunnu mudakozhi road muzhakunnu grama panchayath in between ch 0/900 to 1/418 km
2021_LSGD_452508_10
DB/TN/5(2)/21-22
Open Tender
Civil Works - Roads
Item Rate
270 days
kannur
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,800
Yes
₹20,070
Yes
13 Jan 2022
10 Nov 2021
22 Nov 2021
10 Nov 2021
18 Nov 2021
10 Nov 2021
60 days
Amount
ROAD DRAIN AND RETARRING WORKS
3.5.2 : Excavation in Soil with Dozer with lead upto 100 m <br> Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections.
3.5.1 : Excavation in Cutting in Soil by manual means with lead upto 50 m Excavation for roadway in soil using manual means for carrying of cut earth to embankment site with a lift upto 1.5 m and lead upto 50 m as per Technical Specification Clause 302.3
2.2.2.A : Clearing and Grubbing Road Land<br> Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. <br> (II) By Mechanical Means <br> (A) In area of non-thorny jungle
od1374994/2021_2022 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br><br>I.P.C.C grade M 10<br><br>(i)Nominal mix 1:3:6(Modified 11.4.1.1)
11.4.2.1 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 II.P.C.C grade M 15 (i)Nominal mix (1:2.5:5)
11.4.3.1 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203III.P.C.C. grade M 20 (i)Nominal mix (1:2:4)
3.2 : Preparation of Foundation for Embankment Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
3.3 : Construction of Embankment with Material Obtained from Roadway Cutting <br> Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5
4.11.2 : Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. <br>(ii) Using Gravel mix soil.
od1196400/2021_2022 : Granular sub-base/base/surface course with local materials (Table 400.13) by mix in<br>place method normal. Construction of granular sub-base by providing local material spreading in uniform<br>layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and<br>compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per<br>Technical Specification Clause 408.<br>(ii)Using Gravel mix soil.deptl material
4.9 : Wet Mix Macadam <br> Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. <br> By Mechanical Means with 1 km lead
75.5.1.1pb : Prime Coat - Low porosity - With Packed Bitumen Rates <br> Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
75.5.2.1pb : Tack Coat - With Packed Bitumen Rates <br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
75.5.2.3pb : Tack Coat - With Packed Bitumen Rates <br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503.
75.5.5.B.2pb : Modified Penetration Macadam 75 mm thick using Bitumen S-65 - Packed Bitumen Rates <br> Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506.
75.5.5.A.1pb : Modified Penetration Macadam 50 mm thick using Bitumen S-65 - Packed Bitumen Rates <br> Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506.
75.9.3.pb.pa : Plastic roads- Packed Bitumen Rate <br> 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder -<br> Bitumen S-65 - Packed Bitumen and Shredded Plastic<br> <br> Providing, laying and rolling of opengraded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, using HM Plant attached with open pugmilll.Heating of aggregate at 150 degree Celsius to 170 degree Celsius, then transferring the hot aggregate to pugmill and add shredded plastic @10.22 kg/100m2 mixing well to form a uniform thin layer of plastic over - hot aggregate and adding hot bitumen (150 to 165 degree Celsius) @ 13.578 Kg/10m2 and mix well, laying and rolling with a. three wheel 80-100 kN static roller capacity, finished to required level and grades to be- followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508 <br> Case - I By Manual Means <br> <br> (II) Bitumen (S-65)
75.5.12.A.3.2pb : Seal Coat - Manual Means - Type C - Bitumen S-65 - Packed Bitumen Rates <br> Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 <br> A. By Manual Means <br> Case III : Type C <br> (II) Bitumen (S-65)
11.4.4 : Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203IV.R.C.C grade M 20
od1488908/2021_2022 : derived 11.4.3.1-Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203<br>III.P.C.C. grade M 10 <br>(i)Nominal mix (1:3:6)
11.8 : Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202
od1196401/2021_2022 : :Providing and fixing of project sign board size 800x600mm with<br>MS Plates of 1.6 mm thick riveted with MS angle iron frame of 25x25x5mm on back on edges with 50mm GI<br>pipe 1.20m above GI posts duly embedded in cement concrete M-15 grade blocks of 300mm x 300mm x<br>300mm. Lettering and printing , border etc. will be painted with ready mixed synthetic enamel paint of<br>superior quality in required shade and colour. All sections of framed posts and steel tube will be painted<br>with primer and two coats of epoxy paint
MATHAI VD
VIPINLAL M
Bidder Name
PAULKANNANTHANAM
MATHAI VD
VIPINLAL M
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_646852.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .