Tender Value
₹14.1 L
EMD Value
₹51,000
Closing Date
11 Jun 2026, 6:00 pm6d left
DEPUTY CONSERVATOR OF FOREST, NORMAL DIVISION, SURAT.
RETROFITTING WORK OF VAN BHAVAN OFFICE BUILDING AT ADAJAN IN SURAT (BUILDING GALLARY)
308912
DCFSUR/TENDER/04/2026-27
Open
Civil Works - Buildings
Surat
4 documents required · 4 mandatory
₹1,000
Deputy Conservator of Forest
₹51,000
28 May 2026
28 May 2026
28 May 2026
11 Jun 2026
28 May 2026
Bill of Quantities
Qty. May Tender Rate
Sr. No. Description of Item Unit Total Amount
Sr. No. Description of Item Unit Total Amount
More Or Less Rate In FIghure
Dismentaling tiled of stone floors laid in mortar including
stacking of serviceable materilas and disposal of
1 unserviceable materials with all lead and lift. Smt 18.84 50.11
Demolition of Brickwork and stone masonary including
stacking of serviceable materials and disposal of
unserviceable materials with all lead and lift. (ii)In cement
Excavation for foundation upto 1.5 m depth including
sorting out and stacking of useful materials and disposing
off the excavated stuff upto 50 Meter lead.(C) Hard
Murrum/or any surface
Filling in plinth and foundation with sand under floors
4 including watering ramming, consolidating and dressing Cmt 5.00 481.80
Filling in foundation and plinth with murrum or selected soil
in layers of 20cm. thickness including watering, ramming
and consolidating etc. complete. (more than 10 ton)
Filling available excavated earth (excluding rock) in
trenches. plinth, sides of foundations etc. in layers not
exceeding 20 cm. in depth consolidating each
disposited layer by ramming and watering.
Carring out plinth treatment to post construction / existing
structure by spraying chemical solution for termite control
treatment including labour and material consistent with I.S.I
specification. Using Chlordane and Chiorpurfiles 20 EC. As
7 Per 6131_paret-II Concentration Weight one percent is Smt. 32.00 87.03
recommended i.e one liter 20 EC chemical emulsion with
liter give 1 % concentration inclusive of one liter chemical
emulsion application at the rate of 5 Liter chemical/ Sqm of
surface is recommended as per I.S.
Providing and laying cement concrete 1:2:4 (1- Cement : 2-
Coarse sand : 4- graded stone aggregates 20 mm nominal
size) and curing complete excluding cost of formwork in (A)
Foundation and Plinth
Brick work using common burnt clay building bricks having
9 crushing strength not less than 35 Kg./Sq.,Cm. in Super Cmt 0.00 4,503.04
Structure in C.M. 1:6 (B) conventional
Qty. May Tender Rate
Sr. No. Description of Item Unit Total Amount
Sr. No. Description of Item Unit Total Amount
More Or Less Rate In FIghure
Providing and laying in position Ready Mixed M-300 grade
concrete for reinforced cement conctere work , using
cement content as per approved Design Mix manufactured
in fully automatic batching plant and transported to site of
work in transit mixer for a lead up to 10 kms having
continuous agitated mixer, manufactured as per mix design
of specified grade for reinforced cement concrete work
including pumping of R.M.C. from transit mixer to site of
laying, including the cost of centering shuttering finishing
and excluding reinforcement including cost of admixtures in
recommended proportions as per IS: 9103 to accelerate/
retard setting of concrete, improve workability without
impairing strength and durability as per direction of the
Engineer - in - charge. Without Fly Ash (Min cement level as
per latest IS 456 shall be maintained) (Cement level 475 kg )
Providing and fixing temporary steel props/support system
to take the load of the surrounding structure during the
repair process, including necessary staging and removal
11 after completion. complete with all the required tools, Sqm 131.00 404.00
tackles, labourers as required and as directed by the
engineer in charge. Unit will be in sqm and For
measurement, column Height and Length will be measured.
Chipping of existing concrete surface using mechanical
tools to remove loose/damaged concrete and expose coarse
aggregates, including cleaning the surface with wire brush,
removal of dust, debris and laitance. P/A ANTI CORROSIVE
RUST REMOVER ON REIN Providing and applying anti
corrosive rust remover "Rusticide" of M/S Sunanda
speciality coating pvt Ltd or equivalent approved including Smt. 110.00 585.80
cleaning the reinforcement bars with wire brush or air
blowing including removing of all loose particle with
applying rust remover thoroughly on reinforcement bars by
using cotton waste swab etc. complete with all the required
tools, tackles, labourers as required and as directed by the
engineer in charge.
Drilling holes in existing column using rotary hammer drill
and fixing 12 mm dia L-shaped TMT bars as shear
connectors in zig-zag pattern at 600 mm c/c on all faces,
13 including cleaning of holes, filling with approved Nos 260.00 196.95
epoxy/chemical grout and proper anchorage. complete with
all the required tools, tackles, labourers as required and as
directed by the engineer in charge.
Providing and applying polymer modified mortar treatment
in proportion (Cement : White Sand : SBR = 1 : 1 : 0.14) in
layers up to 22 mm thickness each by hand pressing method
over prepared concrete surface, including surface cleaning
14 and roughening, application of bonding coat, placing and Smt. 110.00 858.50
compacting mortar, finishing to a rough texture to ensure
proper bond with subsequent RCC jacketing, including
curing, all materials, labour, tools and equipment complete
as per specification and directed by EIC.
Qty. May Tender Rate
Sr. No. Description of Item Unit Total Amount
Sr. No. Description of Item Unit Total Amount
More Or Less Rate In FIghure
Providing formwork of ordinary timber planking so as to
give a rough finish including centering shuttering strutting
and propping etc. Height of propping and centering below
15 supporting floor to ceiling not exceeding 4M. and removal Smt. 131.00 320.70
of the same for insitu reinforced concrete and plain concrete
work in. (G) Columns Pillars Posts and struts
Providing and laying minimum 100 mm thick RCC jacketing
around existing column using design mix M30 micro
concrete, including addition of approved admixtures
(superplasticizer) and fiber reinforcement 3s 12mm fibers
(Recron or equivalent),
16 including: Cmt 16.00 46,460.00
-Pouring/pumping of micro concrete
-Compaction using vibrator
-Finishing to line and level
The work shall be carried out from foundation level up to
required height
Providing TMT Bar FE 500D reinforcement for R.C.C. work
17 including bending, binding and placing in position complete Kg 2246.00 77.29
upto floor two level
Providing 15mm thick Water proof Cement Plaster in single
coat on brick/concrete wall for interior/exterior plastering at
18 all floor Lvl. & finished even and smooth in(i) Cement mortar Smt 145.00 199.02
1:4 (1-cement :4-sand) For all floor, etc. Complete, as per
detailed and directed by EIC
20mm thick sand faced cement plaster on walls upto height
10 metres above ground level consisting of 12mm thick
19 backing coat of C.M. 1:3 (1-cement : 3-sand) and 8mm Smt 0.00 347.42
thick finishing coat of C.M. 1:1 (1-cement : 1-sand) etc.
Providing and laying Vitrified tiles 8 to 10 mm thick , 24'' x
24'' in flooring treads of steps and landing laid on a bed of
20 12mm thick cement mortar 1:3 (1-cement : 3-coarse sand ) Smt 16.90 1,092.37
finishing with flush pointing in white cement.
Applying two coats of Birla or Asian acrylic lappy ( putty) &
two coats of primer at Wall painting (two coats) with plastic
emulsion paint of approved brand & manufacture on
21 undecorated wall surfaces to give an even shade including Smt 145.00 123.95
thoroughly brushing the surface free from mortar droppings
& other foreign matter & sand papered smooth, as per
detailed & directed by EIC.
I/We am/are willing to carry out the work @............ % above/below percent ( should be
written in figures & Words) of the estimated rates mentoined above . Amount of my/our
tender work out as under .
Estimated amount put to tender Estimated amount put to tender
Qty. May Tender Rate
Sr. No. Description of Item Unit Total Amount
Sr. No. Description of Item Unit Total Amount
More Or Less Rate In FIghure
Deduct:……………………...….% below Add……………………..……..% above
IN words IN words
(Please strike out whichever is not applicable.)
The Contractor shall exhibit a board with detailed specification and details of work as
1 directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.:
PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in S.O.R. therefore in R.C.C.
items where there is a change as per actual mix design the cost of difference of cement consumption
have been deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Signature of Contractor with Seal Signature of Contracting Authority with Seal
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1.0 SBD.pdf
2.0 BOQ.pdf
3.0 SPECIFICATION INDEX.pdf
3.2 RETROFITTING SPECIFICATION and METHODOLOGY.pdf
TSN.pdf
Building Specification Book.pdf