| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹27.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹37.5 L+₹9.6 L (34.6%)Rejected-AOC TC 26 2325 1 CASTLE QUIN KUNNUKUZHY VANCHIYOOR P O THIRUVANANTHAPURAM | THIRUVANANTHAPURAM | KERALA | 695001 | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | V-Tech Enviro Solutions Private Limited L2 | RONIMON MATHEW L1 |
|---|---|---|---|---|---|
| 1.00Grey water management (DEWATS) | |||||
| 1.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 32.55 | cum | 324.61 ₹10,566.06 | 220 ₹7,161 Lowest |
| 1.02 | 2.7.1 Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock | 10.85 | cum | 652.51 ₹7,079.73 | 443 ₹4,806.55 Lowest |
| 1.03 | 4.1.5 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) | 5.73 | cum | 10,797.11 ₹61,867.44 | 7,336 ₹42,035.28 Lowest |
| 1.04 | 5.2.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 26.61 | cum | 16,092.95 ₹4,28,217.31 | 10,935 ₹2,90,969.42 Lowest |
| 1.05 | 5.22.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 2,660.9 | kilogram | 141.66 ₹3,76,943.09 | 95 ₹2,52,785.5 Lowest |
| 1.06 | 5.9.2 Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | 260.5 | sqm | 1,057.9 ₹2,75,582.95 | 718 ₹1,87,039 Lowest |
| 1.07 | 100.1.1 Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil. | 7.5 | cum | 854.52 ₹6,408.9 | 579 ₹4,342.5 Lowest |
| 1.08 | 100.1.5 Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50 m, in Ordinary Rock. | 30 | cum | 1,260.45 ₹37,813.5 | 855 ₹25,650 Lowest |
| 1.09 | 15.2.1 Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 1.5 | cum | 3,171.33 ₹4,756.99 | 2,155 ₹3,232.5 Lowest |
Tender Value
₹41 L
EMD Value
₹50,000
Closing Date
1 Sept 2025, 9:00 amClosed
Regional Project Director
2nd Floor, Bldg.No.3/253, Near AKG Hospital, Talap, Kannur
GREY WATER MANAGEMENT PROJECT NOWA WITH DEWATS AT PILATHARA FISH MARKET, CHERUTHAZHAM GP, KANNUR, KERALA
2025_KRWSA_786970_1
15/KRWSA/KNR/DW/SBM/CRTZ/24-25
Open Tender
Civil Works - Water Works
Item Rate
180 days
Pilathara, Cheruthazham Grama Panchayath Kannur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,500
₹50,000
Regional Project Management Unit, KRWSA, Kannur
10 Nov 2025
16 Aug 2025
2 Sept 2025
16 Aug 2025
1 Sept 2025
16 Aug 2025
16 Aug 2025 - 31 Aug 2025
19 Aug 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1294069.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .