| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1st₹7.8 LAccepted-AOC | 1st | Accepted-AOC FIRST LOWEST | |
| 2 | 2nd₹7.9 L+₹12,087.50 (1.56%)Rejected-Finance ORUMBIKKUNNEL HOUSE THURUTHIKKAD P O MALLAPPALLY PATHANAMTHITTA 689597 KERALA | MALLAPPALLY | PATHANAMTHITTA | KERALA | 689597 | 2nd | Rejected-Finance SECOND LOWEST |
Tender Value
₹7.2 L
EMD Value
₹17,895
Closing Date
1 Feb 2024, 2:00 pmClosed
EXECUTIVE ENGINEER
OFFICE OF THE EXECUTIVE ENGINEER,PROJECT DIVISION, kOLLAM
Jal Jeevan Mission (JJM)-PHASE 2 ADICHANALOOR -Construction of boundary wall at Kattachal OHSR -General Civil Work
2024_KWA_649787_1
Re- CE(SR)/TR/19042/2023_5_2_1/1
Open Tender
Civil Works - Water Works
Item Rate
270 days
ADHICHANALLOOR
5 documents required · 5 mandatory
₹1,580
₹17,895
25 Mar 2024
25 Jan 2024
2 Feb 2024
25 Jan 2024
1 Feb 2024
25 Jan 2024
25 Jan 2024 - 1 Feb 2024
Amount
Construction of boundary wall
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
5.33.1:Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately.All work upto plinth level
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.1.5:Solid block masonry using pre cast solid blocks ( Factory made) of size 30x20x20cm or nearest available size confirming to IS 2185 Part I of 1979 for super structure up to floor two level thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc complete
13.3.2:20 mm cement plaster of mix:1:6 ( 1 cement : 6 fine sand)
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
OD235231/2023-2024:Providing MS gates for compound wall using 40mm GI pipe for frame work and inside of this framemaking grills using 10mm square rod, 100mm C/C on both sides and the vertical rod extented from thetop frame upto required length as per drawing and painting epoxy paint two coats for approved colourafter painting zinc rich priming coat after rubbing with emery paper and cleaning the surface andarranging the locking system including cost of materials and labour and hire charges for fabricating etc.complete as per the direction of deptl. Officers.
LIBIN MATHEW
Bidder Name
SYAM SANKER
LIBIN MATHEW
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .