| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹55.7 LAccepted-Finance | L1 | Accepted-Finance Lowest Rate Quoted among the others | |
| 2 | L2₹55.8 L+₹5,012 (0.09%)Accepted-Finance | L2 | Accepted-Finance Higher Rate Quoted among the others |
Tender Value
₹55.5 L
EMD Value
₹1.1 L
Closing Date
25 Mar 2025, 2:30 pmClosed
Director PNRD BTC Kokrajhar
Director PNRD BTC Kokrajhar
DPRD/BTC/(15th FC)UT/V/Udl-16/2024/10
2025_BoTC_43457_1
DPRD/BTC/(15th FC)UT/V/Udl-16/2024/10
Open Tender
Civil Works
Item Rate
90 days
Mazbat Udalguri
Refer to Bid Document
4 documents required · 4 mandatory
₹1,110
₹1.1 L
Yes
24 Apr 2025
13 Mar 2025
26 Mar 2025
13 Mar 2025
25 Mar 2025
13 Mar 2025
13 Mar 2025 - 25 Mar 2025
Amount
Construction of 7 Nos of 100 mm NP-3 HP Culvert :
Construction of embankment with approved material obtained from borrow pits with all lift upto 1.5m, transporting to site, spreading , grading to required slope and compacting to meet requirement to Table 300.1 and 300.2 with a lead upto 1000m as per Technical Specification Clause 301.5 (i) Private Land
Collection of sand gravel containing 60% and 40% gravel at quarry free from disintegrated and flaky pieces vegetation and other deleterious matter and adherent coating etc., (Rate including FR & ST loading, unloading stacking in working site from nearest quarry as directed)
Labour for spreading metal gravel / granular material on the road surface as directed including dressing and cambering the formation and utilizing the loose earth in filling the depression as directed including carriage of gravel within 30 m
CONSTRUCTION OF 7 NOS OF 1000 MM NP-3 HP CULVERT (SINGLE OPENING) Excavation of Structures Earthwork in excavation for structure as per drawing and technical specifications Clause 305.1 incl. setting out, constr of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. 1. Ordinary soil, upto 3m depth.
Proving conc. For plain/reinforced conc. In open foundations complete as per drawings and technical specifications Clause 802, 803, 1202,& 1203 B. With Natural Gravel 1. PCC Grade M 10, Nominal mix 1;3:6
Bedding for pipe, Type-B (1st class) Bedding laying (1st class) Bedding on well compacted Granular materials.
Construction of 7 Nos of 100 mm NP-3 HP Culvert :
Proving conc. For plain/reinforced conc. In sub-structure complete as per drawings and technical specifications Clause 802, 804, 805, 806, 807, 1202, & 1204 B. With Natural Gravel 1. PCC Grade M 15, Nominal mix 1:2.5:5.
Providing and Laying RCC NP3 in Single Row Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, conc and masonry works in head walls and parapets Clause 1106 (B) 1000 mm dia.
Providing Signboard
GABRIEL DAIMARI (BID ID -262931)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .