Tender Value
₹6.1 Cr
EMD Value
₹6.1 L
Closing Date
3 Oct 2026, 6:00 pm6d left
Executive Engineer Sipu Project Division, Palanpur
Construction Of New Bituminous Road At Sipu Branch Canal Ta. Deesa Dist: B.K.
341171
Notice No.13 of 2026-27
Open
Civil Works - Roads
Works
Banaskantha
7 documents required · 7 mandatory
₹12,000
Executive Engineer Sipu Project Division Palanpur
₹6.1 L
2 Sept 2026
2 Sept 2026
2 Sept 2026
3 Oct 2026
2 Sept 2026
BILL OF QUANTITIES
Name of Work :- Construction Of New Bituminous Road At Sipu Branch Canal Ta.
Deesa Dist: B.K.
(A) Percentage Rate Tender (Up to INR 50 Cr. )
Item Description of Item (with brief specification Quantity Unit Rate In Amount
No and reference to book of specifications) figures
1 Clearing and grubbing road land including
uprooting rank vegetation grass
bushes,shrubs,sapling and trees girth up to
mm removal of stumps of trees cut earlier and
disposal of unserviceable materials (C) By
mechanical means in area of light jungle
2 Box cutting the road surface to proper slope and
camber for making a base for road work including
removing the excavated stuff and depositing on
the road side slope as directed upto 50Mt.lead.
3 Earthwork for embankment including breaking
clods, dressing with all lead and lift (excluding
watering and consolidation) (A) From Borrow
pits within 3.0 Km lead
4 Rolling & Watering of Earth work in layers with
vibratory roller including filling in depressions 10996.00 Cu.M. 22.960
which occur during the process.
5 Construction of granular sub-base by providing
well graded material, (Metal 25.60 mm to 53 mm
35%, B.T. Kapachi 25.60 mm to 4.75 mm 45% &
Coarse sand below 2.38 mm 20% }spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with smooth
wheel roller to achieve the desired density,
complete as per Technical Specification Clause
6 Providing and laying W.B.M. of M.C. metal of size
45 mm to 63 mm size including 0.12 Cu.M. Stone
screening & 0.08 Cu.M. stone dust as filler
including spreading, watering & consolidation by
vibratory roller 80KN to 100KN static weight.
75 mm thick compacted each.
7 Providing and laying, spreading and compacting
150 mm thick graded stone aggregate to Wet Mix
Macadam (W.M.M.) specification including
premixing the material with water at OMC in
mechanical mix plant carriage of mixed material
by tipper to site, laying in uniform layers with
mechanical means Paver Finisher in sub-base
/base course on well prepared surface and
compacting with vibratory roller to achieve the
desired density.
8 Providing and laying bituminous grout base
course 37.5 mm thick using asphalt Grade VG-30
for tack coat at the rate of 4.0 Kg. / 10 Sq.Mt. on 2838.00 M.T. 2535.870
WBM surface and 2.50 Kg. / 10 Sq.Mt. on BT
surface using B.T. stone aggregates as per
Item Description of Item (with brief specification Quantity Unit Rate In Amount
No and reference to book of specifications) figures
required gradation with the asphalt of VG-30
grade at the rate of 1.99 % i.e. 19.90 Kg. / M.T. by
weight by mix including heating and mixing in
drum mix plant, transporting the mix spreading
the same by paver finisher and consolidation by
vibratory roller including cost of all materials,
fuel labours, tools and plant etc. using contractors
own drum mix plant etc. complete.
9 Providing and laying 37.5 mm thick bituminous
macadam with B.T. Aggregates as per M.O.R.T.& H
gradation and Asphalt @ 2.50 Kg / 10 Sq mt for
tack coat on BT surfae, asphalt grade VG-30
{60/70} for mixing @ 35.00 Kg. / M.T. i.e. 3.5%
by total weight including heating the aggregates
and asphalt by continuous batching of drum mix
plant and spreading the same by paver finisher
and consolidation with vibratory roller 80 to
KN static weight including providing all
materials, equipments, tools and plant, oil,
kerosene, firewood, labour charges etc. comp.
using contractor's own machineries, drum mix
plant and paver finisher etc. complete.
10 Providing and laying 20mm thick Mixed seal
surfacing using stone chipping and aggregates as
per M.O.R.T.& H gradation and bitumen grade VG-
30 for mixing at the rate of 51 Kg. / M.T. i.e. 5.1 %
by total weight of mix, including heating & mixing
the asphalt and aggregates by continuous
batching of drum mix plant and spreading the
same by paver finisher and consolidation with
vibratory roller and flushing sand @ 0.30 Cu.M. /
100 Sq.Mt. including providing all materials
equipments, tools and plant, oil, kerosene,
firewood, labour charges etc. comp. using
contractor's own machineries, drum mix and
paver finisher etc. complete.
11 Providing and laying asphalt painting on BT
surface with Bitumen grade VG-30 at the rate of
kG/10 sqm. By mechanical sprayer and spreading
the stone dust on prepared surface at the rate of
0.03 Cum/ 10 Sqm. Etc. complete and rolling with
PTR roller and brushing etc.complete
12 Providing hard side shoulder of 100 mm thick for
embankment using quarry spall with all lead and
lift and including watering and rolling and
consolidation of sub grade in layers at OMC to
required dry density including filling depression
which occur during the process using vibratory
roller of 80 KN to 100 KN (selected quarry spall
having CBR value not less than 30.0)
13 Providing and fixing ordinary Kilometer stone of
approved hard stone as per I.R.C. type design in
Item Description of Item (with brief specification Quantity Unit Rate In Amount
No and reference to book of specifications) figures
C.C. 1:4:8 including painting and lettering etc.
complete (For O.D.Road,V.R.)
14 Providing and fixing 5th Kilometer stone of
precast C.C. 1:2:4 including necessary
reinforcement as per I.R.C. type design in C.C. 1.00 No. 1935.150
1:4:8 including painting,lettering etc. complete
(For N.H., S.H. and M.D.R.)
15 Providing and fixing hectometer stone as per
I.R.C. type design including painting, lettering etc. 39.00 No. 116.080
complete. (I) Fixing in earth
16 Road Marking with Hot applied thermoplastic
paints with Reflectorising glass beads on Bitumin
surface. Providing & Laying a hot applied
Thermoplastic compound 2.5 mm thick including
refflectorising glass beads @ 250 gms. Sqm. Area
thickness of 2.5 mm is excluding of Surface
applied glass beads as per IRC :35-2015. The
finished surface to be level , uniform and free
from streaks and holes Zebra patta / bump patta
lane / center line / edges/ Cut patta. The white 1940.00 Sq.Mt. 367.720
colour marking should provide leminance
coefficient on cermend road shallbe min.
mcd/m2/lux and Ashphalt road shall be
minimum 100 mcd/m2/lux during the service life
during the dry time. The marking should should
meet the performance criteria for night time /
reflectivity, wet reflectivitiy and skid reasistance
as mentioned in the section-15 of IRC 35 -
Warranty for Retro Reflectivity Two Year
17 Cat Eye / Road Stud / RPM: Providing & fixing
Raised Pavement Markers made of polycarbonate
and ABS moulded body and reflective panels with
Micro prismatic lens (No Glass bead lens) capable
of providing total internal reflection of the light
entering the lens face and shall support a load of
13635 kgs. tested in accordance to ASTM D
Type H and complying to Specifications of
Category A of MORTH Circular No
RW/NH/33023/10-97 Ð DO III Dt 11.06.
The height, width and length shall not exceed
mm, 130 mm and 130 mm and with minimum
reflective area of 13 Sqcm on each side and the
slope to the base shall be 35 +/- 5 degree. The
body of the marker should having finger grip for
easy and accurate placement and application with
epoxy / bituminous Adhesive as recommended by
the manufacturer of the marker. The color of the
marker should be as per the IRC 35-2015 and as
directed by Engineer-in- Carge.
Rupees Six Crore Eight Lakh Twenty Four Thousand Forty Five Paise Fifty Four Only
I/We am/are willing to carry out the work at… ...................... % above/below percent(Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our
tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
(B) For Item Rate Tender (For above INR 50 Cr.):
Item Description of Item Quantity Unit Rate Amount
No (with brief specification
and reference to book of In In
specifications) figures Words
(A) Total Tendered Amount
(B) Rebate on above tendered amount (if any) % (in figure) ………………………………
(C)Net Tendered Amount (A-B) (in figure) ………………………………
1. The Contractor shall exhibit a board with brief details of work as directed by the Engineer-In-Charge
for which no extra payment shall be made.
2. The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3. GST and Income tax TDS will be deducted at a source while making payments of bills
4. In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R. NO.:
MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore in R.C.C. items where there is a change
as per actual mix design the cost of difference of cement consumption have been deducted from the rate of
original item at the rate of input rate mentioned in all the tender.
Deputy Executive Engineer Sr. Divisional Accounts Officer Executive Engineer
Sipu Canal Sub Div. No 2 Sipu Project Division Sipu Project Division
Dantiwada Palanpur Palanpur
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Sipu Branch Canal Road.pdf
BOQ Sipu Branch Canal Road.pdf
Nivida 13.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .