| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹36.5 LAccepted-Finance | ₹36.5 L | L1 | Accepted-Finance Qualified |
| 2 | L2₹36.5 L+₹5,701.89 (0.16%)Rejected-Finance | ₹36.5 L+₹5,701.89 (0.16%) | L2 | Rejected-Finance Disqualified |
| 3 | L3₹36.6 L+₹11,311.30 (0.31%)Rejected-Finance | ₹36.6 L+₹11,311.30 (0.31%) | L3 | Rejected-Finance Disqualified |
| Sl No | Description | Qty | Unit | PAWAR CONSTRUCTION L2 | NEGI CONSTRUCTION L3 | BHUWAN CHANDRA JOSHI L1 |
|---|---|---|---|---|---|---|
| 1.00 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. All kinds of soil | 56.41 | cum | 284.56 ₹16,052.03 | 384 ₹21,661.44 | 284 ₹16,020.44 Lowest |
| 2.00 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) | 4.7 | cum | 9,889 ₹46,478.3 Lowest | 9,889 ₹46,478.3 Lowest | 9,889 ₹46,478.3 Lowest |
| 3.00 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) | 5.13 | cum | 11,864.66 ₹60,865.71 | 11,864.66 ₹60,865.71 | 11,564 ₹59,323.32 Lowest |
| 4.00 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | 10.99 | cum | 12,578.05 ₹1,38,232.77 | 12,578.05 ₹1,38,232.77 | 12,578 ₹1,38,232.22 Lowest |
| 5.00 | Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete. | 17.28 | sqm | 428.71 ₹7,408.11 | 428.71 ₹7,408.11 | 428 ₹7,395.84 Lowest |
| 6.00 | Centering and shuttering including strutting, propping etc. and removal of form for : Columns, Pillars, Piers, Abutments, Posts and Struts. | 60.84 | sqm | 1,050.91 ₹63,937.36 | 1,050.91 ₹63,937.36 | 1,050 ₹63,882 Lowest |
| 7.00 | Centering and shuttering including strutting, propping etc. and removal of form for : Lintels, beams, plinth beams, girders, bressumers and cantilevers. | 61.02 | sqm | 805.05 ₹49,124.15 | 805.05 ₹49,124.15 | 805 ₹49,121.1 Lowest |
| 8.00 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 2,345 | Kg | 117.05 ₹2,74,482.25 | 117.05 ₹2,74,482.25 | 117 ₹2,74,365 Lowest |
| 9.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 66.08 | cum | 7,447.02 ₹4,92,099.08 | 7,447.02 ₹4,92,099.08 | 7,447 ₹4,92,097.76 Lowest |
| 10.00 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth : Cement mortar 1:6 (1 cement : 6 coarse sand) | 17.41 | cum | 6,881.99 ₹1,19,815.45 | 6,881.99 ₹1,19,815.45 | 6,881 ₹1,19,798.21 Lowest |
Tender Value
₹36.5 L
EMD Value
₹74,000
Closing Date
11 Aug 2026, 11:30 amClosed
GM(C)
KMVN Ltd oak park house nainital
Beautification and site development work in sngrali mata mandir someshwar distt Almora
2026_KMVN_98252_1
KMVN/1244/dt07.07.2026
Open Tender
Civil Works
Item Rate
180 days
Someshwar
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,950
MD KMVN Ltd
₹74,000
18 Aug 2026
29 Jul 2026
11 Aug 2026
29 Jul 2026
11 Aug 2026
29 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. All kinds of soil | 56.41 | cum | 284.56 | ₹16,052.03 |
| 2 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) | 4.7 | cum | 9,889 | ₹46,478.3 |
| 3 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) | 5.13 | cum | 11,864.66 | ₹60,865.71 |
| 4 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | 10.99 | cum | 12,578.05 | ₹1,38,232.77 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete. | 17.28 | sqm | 428.71 | ₹7,408.11 |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for : Columns, Pillars, Piers, Abutments, Posts and Struts. | 60.84 | sqm | 1,050.91 | ₹63,937.36 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for : Lintels, beams, plinth beams, girders, bressumers and cantilevers. | 61.02 | sqm | 805.05 | ₹49,124.15 |
| 8 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 2,345 | Kg | 117.08 | ₹2,74,552.6 |
| 9 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 66.08 | cum | 7,447.02 | ₹4,92,099.08 |
| 10 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth : Cement mortar 1:6 (1 cement : 6 coarse sand) | 17.41 | cum | 6,881.99 | ₹1,19,815.45 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.15 MB
sangrali.pdf
Tender Documents • 4.28 MB
BOQ_115944.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .