Loading…
Loading…
Tender Value
₹79.4 L
EMD Value
₹80,000
Closing Date
15 Jun 2026, 6:00 pm
Executive Engineer, Rajkot Irrigation Division, Rajkot.
THIRD ATTEMPT AJI-III IRRIGATION SCHEME. Repairing And Restoration of Bucket, Endsill and Apron of Aji-3 irrigation scheme
311308
SBD-08 of 2026-27
Open
Civil - All
Rajkot
4 documents required · 4 mandatory
₹2,400
Executive Engineer, Rajkot Irrigation Division Rajkot
₹80,000
4 Jun 2026
4 Jun 2026
4 Jun 2026
15 Jun 2026
4 Jun 2026
NAME OF WORK :-
Repairing And Restoration of Bucket, Endsill and Apron of Aji-III Irrigation Scheme.
BILL OF QUANTITIES (SCHEDULE - B)
(A) Percentage Rate Tender (Upto Rs. 50 Crore)
Item Description of Item Quantity Unit Estimated Rate Amount
No. (with brief specification and reference to book of specifications) In Figure In words
1 Dewatering for earthen dam and allied works,foundation
Rupees: Twenty Seven
areas,pits,trenches etc incl cost of pumping machineries,pipe 42940 Hp-Hr
lines,labours diesel/electricity/DG set, etc complete.
2 Earth work in embankment from borrow pits in all sort of soil and soft
murrum or other suitable strata as directed incl breaking clods and Rupees: One Hundred
dressing to the design section with lead as under and all lift incl.site 3460 Cum. 165.20 Sixty Five & Ps Twenty
clearance etc comp. For all canal capacity & Without rolling and only
watering (TOTAL LEAD FOR 5 KM)
Desilting of dam bucket including depositing the same as directed with Rupees: Two Hundred
all lift and lead etc complete. Ninety Six Only
4 Preparing of spillway, piers and allied work incl. removal of loose
weathered material incl. hard rock by wedging, chiseling with all
Rupees Eight & Ps.
labours, tools and materials for cleaning the existing reinforcement or 54 sqmt
surfaces with sand blasting, compressed air and water jetting as
required etc complete.
5 Drilling 35 mm dia holes at distance as specified and depth upto 3.0mt
for check dam foundation & fixing anchor bars of specified diameter Rupees: Two Hundred
with cement grout incl cleaning holes as directed etc.(excluding cost Eighty Eight Only.
6 Providing,cutting,bending,binding and fixing in position as per
Rupees: Seventy Six
drawing.TMT BAR, reinforcement for R.C.C. works and anchor bars
2.35 MT 76574.00 Thousand Five Hundred
incl cost of black annealed 16 to 18 BWG M.S.. Wire etc.complete Seventy Four Only
with all lead and lift. (b) Fe-500
Item Description of Item Quantity Unit Estimated Rate Amount
No. (with brief specification and reference to book of specifications) In Figure In words
7 Epoxy bonding of new concrete Or mortar to old surface in structure
with proper application of coat of resin and hardener in proportion of Rupees: Two Hundred
2:1 by weight confirming to IS-9197 to give proper bond between old Fifty Nine Only
surface new concrete Or mortar etc complete
8 Providing & Laying in position controlled cement concrete using
cement, Steel Fibers (0.3 to 0.5 mm thick and 25 mm long), sand &
crushed metal aggregate by machine mix incl. necessary formworks
compaction by mechanical vibrator curing as directed with all lead nd 126 Cum.
Hundred Ninety Five
lift etc complete. Excluding the cost of reinforced steel. For bucket and Only
end sill etc.Concrete grade M-30 and MSA-20 mm Fiber Reinforced
Rupees: Seventy Five
Structural Steel & Plates etc. as per IS 2062 (SAIL ESSAR, J.S.W.,
0.76 MT 75993.00 Thousand Nine Hundred
Ambika, Tata, Monnet,Ispat, SKS Ispat) Ninety Three Only
10 Prov. and Laying in position Controlled cement concrete using
cement, sand and crushed aggregate by mass and machine mix for
Rupees: Five Thousand
R.C.C/CC work including necessary formworks centering scaffolding
35 Cum. 5267.00 Two Hundred Sixty
compaction by mechanical vibrator,curing as directed with all lead & Seven Only
lift etc complete Excluding the cost of reinforcement. A) Concrete
grade M-25 and MSA-20mm
Crack filling in RCC/PCC irrigation structure's components with epoxy
based putty incl racking the cracks cleaning curing etc
complete.Prime coat done with material of Resin+Hardner mixing of
BIS standerd quality material & quality that works in wetted condition. Rupees: One Hundred
Pointing done with water plugging BIS standerd quality material in first Fifty One Only
coat and after that second coat done with epoxy base putty of Resin+
Hardner mixing ( 1part Resin+1part Hardener ,+8part Silica ). The rate
includes cost of materials labours scaffolding equipments etc.
Dismantling C.C. foundation or flooring sorting & stacking useful and Rupees: Eight Hundred
unuseful material in lead upto 200mt as directed etc. complete. Twenty Eight only
Item Description of Item Quantity Unit Estimated Rate Amount
No. (with brief specification and reference to book of specifications) In Figure In words
Providing and fixing in position non return flap valve ofapproved
92 Nos 1201.00 Thousand Two Hundred
design and make. (a) 100 mm dia One Only
14 Providing & laying 150mm dia. G.I. ( B-Class medium duty ) outfall
Rupees: Eight Hundred
pipe at 5.0mt c/c or as specified for drainage purpose as directed etc 30 Rmt.
Forty Five only
15 Providing and fixing in position I.R.C. Fabrics of mesh 6"x6" & 10
Rupees: Two Hundred
gauge, reinforcement with necessary nailing in position, overlap etc as 54 sqmt
Eighty Three Only
directed with all lead and lift etc complete.
Excavation in all sort of strata and formations incl. depositing the
unuseful excavated stuff as and where directed incl.sorting and Rupees: Five Hundred
stacking useful materials in measurable conditions as directed upto Ninety only
200mt lead and all lift etc. complete incl. dewatering.(c) in hard rock
Rupees: Seventy Nine Lacs Thirty Six Thousand Five Hundred Thirty Four & Ps. Eighteen Only
I/We are willing to carry out the work at …………………………………………………………...% above/below percent (should be written in figure and words) of the estimated
rates mentioned above. The amount of my/our tender works out as under;
*Estimated amount put to tender Rs. ……………… *Estimated amount put to tender Rs. ………………
Deduct : ……… % below Rs. ………………. Add : ……… % above Rs. ……………….
Net : Rs. ……………… Total : Rs. ………………
In words : Rupees ………………………………………………………………………… In words : Rupees………………………………………………………
1 The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e.1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt.G.R.:PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated
in S.O.R.thereforeinR.C.C.items where there is a change as per actual mix design the cost of difference of cement consumption have been deducted from the rate of
original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of contractor. Rajkot Irrigation Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1 Tender P 1 to 17.pdf
2 SBD Rep. and Restoration Bucket Aji-III p -1 to 204.pdf
3 Sch B -Rep. Bucket Aji-III P -205 to 207.pdf
Download all tender documents and submit your bid