| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.3 LAccepted-AOC | L1 | Accepted-AOC First Lowest | |
| 2 | L2₹24.9 L+₹3.6 L (16.7%)Rejected-AOC SANTHOSH BHAVAN PADAMUGAL KOCHI PIN 682030 | KOCHI | ERNAKULAM | KERALA | 682030 | L2 | Rejected-AOC Second Lowest |
| Sl No | Description | Qty | Unit | Synergy Architects and Engineers L1 | AA AND S CONSTRUCTIONS L2 |
|---|---|---|---|---|---|
| 1.00Subsoil Investigation | |||||
| 1.00 | 56.17.1:Providing access to the site,clearing site and making good to erecting and conducting soil testing transfers within the site and for any other temporary arrangements to be erected within the area in connection with conducting soil testing. | 160 | sqm | 50 ₹8,000 | 27 ₹4,320 Lowest |
| 1.00 | 56.1.a:Mobilization including transportation of all necessary plant and equipment's and materials of boring, field testing and sampling and demobilization after completing the work - For machine boring | 4 | set | 80,000 ₹3,20,000 | 50,000 ₹2,00,000 Lowest |
| 1.00 | 56.2.a:Setting up boring at each bore hole locations including carrying all necessary plant, equipment and materials of boring and field tests and collection of samples at each bore hole location - For machine boring. | 18 | Bore Holes | 5,000 ₹90,000 Lowest | 5,000 ₹90,000 Lowest |
| 1.00 | 56.3.a.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata upto 10m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil. | 50 | metre | 1,300 ₹65,000 | 831 ₹41,550 Lowest |
| 1.00 | 56.3.b.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata next 10m and upto a depth of 20m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil. | 50 | metre | 1,300 ₹65,000 | 923 ₹46,150 Lowest |
| 1.01 | 56.3.c.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata next 10m and upto a depth of 30m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil. | 50 | metre | 500 ₹25,000 Lowest | 945 ₹47,250 |
| 1.01 | 56.3.d.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata above 30m depth including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil. | 200 | metre | 100 ₹20,000 Lowest | 600 ₹1,20,000 |
| 1.01 | 56.5.a:Boring through all classes of rock excluding hard rocks having N value greater than 50 using tungsten carbide drilling bit - In land | 15 | metre | 2,500 ₹37,500 | 2,161 ₹32,415 Lowest |
| 1.01 | 56.9.1:Erecting platform over 2 nos of 2nd Class Boat using Mango wood planks of not less than 30 mm thick, Mango wood joists of 100 mm x 70 mm at 60 cm intervals including labour and hire of all materials and dismantling the platform after completion of work etc complete. excluding hire of boats (A Platform of minimum size 6.00 m x 5.00 m will be required) | 180 | sqm | 250 ₹45,000 Lowest | 446 ₹80,280 |
Tender Value
₹28.4 L
EMD Value
₹50,000
Closing Date
12 Jan 2026, 11:00 amClosed
Executive Engineer
O/o The Executive Engineer RIQCL Tvm
KIIFB-Construction of Ashramam Link road in Kollam district -Phase IV-Investigation Work
2025_PWD_823814_2
PWD/DE/TR/20701/2025_3_1_1/1
Open Tender
Civil Works - Bridges
Item Rate
60 days
Asramam
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹50,000
Yes
19 Feb 2026
5 Jan 2026
14 Jan 2026
5 Jan 2026
12 Jan 2026
5 Jan 2026
Subsoil Investigation
56.17.1:Providing access to the site,clearing site and making good to erecting and conducting soil testing transfers within the site and for any other temporary arrangements to be erected within the area in connection with conducting soil testing.
56.1.a:Mobilization including transportation of all necessary plant and equipment's and materials of boring, field testing and sampling and demobilization after completing the work - For machine boring
56.2.a:Setting up boring at each bore hole locations including carrying all necessary plant, equipment and materials of boring and field tests and collection of samples at each bore hole location - For machine boring.
56.3.a.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata upto 10m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil.
56.3.b.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata next 10m and upto a depth of 20m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil.
56.3.c.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata next 10m and upto a depth of 30m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil.
56.3.d.1:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata above 30m depth including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil.
56.5.a:Boring through all classes of rock excluding hard rocks having N value greater than 50 using tungsten carbide drilling bit - In land
56.9.1:Erecting platform over 2 nos of 2nd Class Boat using Mango wood planks of not less than 30 mm thick, Mango wood joists of 100 mm x 70 mm at 60 cm intervals including labour and hire of all materials and dismantling the platform after completion of work etc complete. excluding hire of boats (A Platform of minimum size 6.00 m x 5.00 m will be required)
56.10:Hire charges for providing 2 nos of 2nd Class boat with boatman for erecting the platform over which the boring plant is to be erected, and 1 no of 2nd Class boat with 1 boatman for conveying the departmental staff and labour engaged from the banks to platform and back etc.
56.3.a.2:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata upto 10m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For under water.
56.3.b.2:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata next 10m and upto a depth of 20m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For under water.
56.3.c.2:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata next 10m and upto a depth of 30m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For under water.
56.3.d.2:Boring with rotary power drilling equipment's in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata above 30m depth including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For under water.
56.5.b:Boring through all classes of rock excluding hard rocks having N value greater than 50 using tungsten carbide drilling bit - In Water
56.4:Boring through all type of hard rock or similar refusal strata of N value greater than 50 using diamond core drilling bit for in land under water and banks of river.
56.7:Conducting standard penetration test in bore hole at any depth.
56.8:Recovering disturbed samples and preserving the same in air tight sample containers including waxing labelling packing storing including cost of containers as per IS Code.
56.6:Recovering undisturbed soil samples using thin tube sampler of 75mm.to 100mm length internal dia 500mm length conforming to relevant IS Code at any required depth including clearing the bore hole etc complete.
56.11.a:Compilation of all field data with recommendation for a suitable foundation after conducting necessary lab test (report in triplicate) - Machine boring for 5 bore holes.
56.11.c:Compilation of all field data with recommendation for a suitable foundation after conducting necessary lab test (report in triplicate) - Machine boring - Extra for additional set for bore holes exceeding 5 nos.
Traffic survey ,Inventory & Hydraulic particulars
OD208371/2025-2026:Conducting Origin Destination survey at one location for three days for peak hours at specified location (7am to 11 am and 3.30 pm to 7.30 pm) by recording the traffic count in the prescribed format, including provision for engaging technicians and setting up of station etc and compiling the data and submitting the details in hard and soft copy. (Roadside interview method)
OD208369/2025-2026:Data for inventorysurvey for upto 12 metre wide road, Survey work for collecting the detailsof road inventories and recording in prescribed format attachd based on the chainage marking including markingchainage at 50m intervals and taking details such as existing carriage way width, shoulder width type ofshoulder, width and location of approch road, details of existing drains,culverts and bridgs as given in theprescribed format attached pavement conditions ( Details of pot holes, raveling, fog seal, slurry seal edgedamage etc) road safety measures ( details of road sign, crash barriers, guard stones, delineator post, hazzardmarkers etc) and all other existing retaining structures in road, including documentation charges etc as per thedirection of the officers at site
OD208370/2025-2026:Collecting and preparing in usable form of Hydraulic Data of river/stream/paddy field such as High/Maximum Flood Level(HFL/MFL), Annual/Ordinary Flood Level (OFL), Noraml/Current Water Level(NWL), Low Water Level(LWL), High Tide Level (HTL), Low Tide Level(LTL), etc. with respect to bench mark of Topographic survey, from reliables sources such as Irrigation Department, Central Water Commission or such government agencies or Local people (in the absence of such data from such agencies) based on the proceedures of IRC: 5 for cross section at bridge proper and upto upstream and down stream sides as directed by department officers..
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
viewsbd.pdf
Tender Documents • 1.64 MB
BOQ_1384688.xls
BOQ • 0.32 MB
viewnit.pdf
Other Document • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .