Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹10.1 L+₹1.3 L (15.2%)Rejected-Finance | L2 | Rejected-Finance Second Lowest |
Tender Value
₹11.3 L
EMD Value
₹28,141
Closing Date
22 Apr 2025, 3:00 pmClosed
Assistant Executive Engineer
P H Sub division, Kerala Water Authority, Nattika
Oand-MWater Supply Schemes-Mace of CWSS to Nattika Firka-Demolishing Damaged OH Tank and Construction of Compound Wall at Kottamkulam in Perinjanam Grama Panchayath-General Civil Work
2025_KWA_759946_1
01/AEE/PHSD/NTK/2024_25
Open Tender
Civil Works - Water Works
Item Rate
90 days
Perinjanam
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,760
₹28,141
24 May 2025
15 Apr 2025
23 Apr 2025
15 Apr 2025
22 Apr 2025
15 Apr 2025
15 Apr 2025 - 22 Apr 2025
Amount
Demolition of OH tank
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
OD108571/2022-2023:Providing shade net covering around the periphery of OH tank from bottom to top of the tank for protecting people, vehicle from the dust while demolishing by fixing vertical full bamboos fixed at 1.50m intervals and struts provided horizontally 1.50m intervals with 1/4 split of full bamboos tied with coir yarn on vertical bamboos and covering with nylon shade net and dismantling the same after the completion of the work as per the direction of daptl. officers
15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
15.6:Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B work.
15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
15.12.1:Dismantling doors, windows and clerestory windows (steel or wood ) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead:Of area 3 sq. metres and below
15.60:Disposal of building rubbish/ malba/ similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved
14.72:Providing and fixing double scaffolding system (cup lock type) on the exterior side, upto seven story hight made with 40 mm dia. M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staricase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The elevational area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. Note:- This item to be used for maintenance work judicially, necessary deduction for scaffolding in the existing item to be done .
OD108211/2022-2023::Dismantling C.I pipes for taking out the pipes, manually / by mechanical means breaking lead caulked joints, melting of lead and making into blocks including stacking of pipes & lead at site within 50 metre lead as per direction of Engineer - in- Charge: Up to 150 mm diameter
100.98.1008:Engaging Coolie.
OD108212/2022-2023::Collecting debris of the demolished cement concrete from roof cover slab, column, braces etc. in bucket/ trolly and lowering to ground manually using pully and iron rope as per direction including hire for tools and plants
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
Construction of Compound wall
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
50.6.1.2:Solid block masonry using pre cast solid blocks (Factory made) of size 40x20x20cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level thickness 20cm and above in: CM 1:6 ( 1 cement: 6 coarse sand) etc complete.
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.40:Distempering with dry distemper of approved brand and manufacture (two or more coats) of required shade on new work, over and including water thinnable priming coat to give an even shade:
10.25.2:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
13.52.1:Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work
MOHAMMED RAFEEQUE K P (BID ID -2200245)
Bidder Name
AIRESH
MOHAMMED RAFEEQUE K P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .