| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹25.7 LAccepted-AOC BUDOOBAGH NOWPORA 0 KHANYAR SRINAGAR JAMMU KASHMIR 190003 | SRINAGAR | JAMMU AND KASHMIR | 190003 | L1 | Accepted-AOC Due to L1 | |
| 2 | L2₹39.0 L+₹12.7 L (48.2%)Rejected-Finance SANAT NAGAR SRINAGAR PIN 190005 J K | SRINAGAR | JAMMU AND KASHMIR | 190005 | L2 | Rejected-Finance L2 | |
| 3 | Rejected-Technical | - | Rejected-Technical Due to not uploaded requisite documents as per NIT | |
| 4 | Rejected-Technical | - | Rejected-Technical Due to not uploaded requisite documents as per NIT | |
| 5 | Rejected-Technical | - | Rejected-Technical Due to not uploaded requisite documents as per NIT |
| Sl No | Description | Qty | Unit | Top Mind Industries Pvt Limited L1 | M/S BHAT ENGINEERING WORKS L2 |
|---|---|---|---|---|---|
| 1.00 | Material and labour for attending of complaint for day to day maintainence / daily complaints by checking the serviceability of fan coil unit of any capacity for having continuous sreviceability of FCU for any number of time as desired by Engr-in-Charge including replacement of minor spare part like Gasket, Teflon tape, flare nut, tightening of any loose glycol line connections, shifting FCU from one place to another place if required, heating up the freezed glycol line anywhere about the premices to have continuous flow of glycol fluid, stopping any kind of leakage from any size of pipe line, tightening the loose electrical connections as related with FCU / Heating system, cleaning the air filter including radiator of FCU to the entire satisfaction of Engineer-in- Charge all as directed at site
Note :-
(i) Attending any complaints of different nature in a single day in Plant Room inside / outside will be considered as one job.
ii) Any kind of replacement of major items shall be measured and paid for separately under respective item of schedule 'A' Part-II
iii) . Any nature of complaint related with FCUs, radiators, bursting/cracking/leakage of MS pipe lines, replacement of valves etc will be completed round the clock by suitable trademen (welder with suitable T & P,(including portable heating materials)-01,Skilled mechanic of CHS-01, Plumber/Fitter with helper-each 01, Supervisor-01 as per directions of Engineer-in- Charge. | 190 | Each Job | 100 ₹19,000 Lowest | 150 ₹28,500 |
| 2.00 | Supply and fixing in replacement of fan coil unit 1.5/2 Ton duel shaft electric motor 30 watt 930 RPM, 3 speed as per existing, complete all as specified and directed. Make- as per existing | 33 | Each | 3,500 ₹1,15,500 Lowest | 4,000 ₹1,32,000 |
| 3.00 | Supply and fixing in replacement of Old unsv radiator unit of FCU 1.5 Ton including connecting with the unit and making it leakproof of copper coils covered with aluminium finishing as per existing size of capacity 3000 K Cal / Hour complete all as specified and directed. | 30 | Each Job | 2,500 ₹75,000 Lowest | 4,000 ₹1,20,000 |
| 4.00 | Supply and fixing in replacement of Old unsv radiator unit of FCU 2 Ton including connecting with the unit and making it leakproof of copper coils covered with aluminium finishing as per existing size of capacity 6000 K Cal / Hour complete all as specified and directed. | 24 | Each Job | 2,500 ₹60,000 Lowest | 5,000 ₹1,20,000 |
| 5.00 | Fixing only fan coil unit 1.5 Ton as per existing connection complete all as specified and directed. | 7 | Each Job | 15,000 ₹1,05,000 Lowest | 18,000 ₹1,26,000 |
| 6.00 | Fixing only fan coil unit 2 Ton as per existing connection complete all as specified and directed. | 7 | Each Job | 15,000 ₹1,05,000 Lowest | 21,000 ₹1,47,000 |
| 7.00 | Material and labour for Dismantling of burner assembly at plant room CHS and removing of side cover and repairing the same by removing the old burnt fire refractory cement plastering, replastering the same as per existing fire refractory cement for boiler capacity 6 lakh Kcal/hr and complete servicing the boiler by removing the complete carbon/oil deposits with suitable coil shine chemical including repair to coil assembly by welding if there is any leakage found or any other repair required at site and reassembling/ testing the same, complete all as specified and directed. | 3 | Each Job | 15,000 ₹45,000 Lowest | 21,000 ₹63,000 |
| 8.00 | All as per srl item No. 7 here-in-before but for 4 Lakh Kcal/Hr complete all as specified and directed. | 1 | Each Job | 15,000 ₹15,000 Lowest | 22,000 ₹22,000 |
| 9.00 | M&L for dismantling Glycol based electrical operated central heating boiler of capacity 75 KW of capacity 75000 Kcal/hr by unscrewing and removal of heater side/end plates, with scalent de-carbonizing, scraping out carbon ,dirt acculated in heater, overhauling, servicing incl re- assembling all the dismantled component to its original position with testing and commissioning, Complete all as specified and directed by Engineer-in-Charge. | 4 | Each Job | 15,000 ₹60,000 Lowest | 21,000 ₹84,000 |
| 10.00 | M&L for dismantling Standalone air heater for space heating of capacity 50000 Kcal/hr by unscrewing and removal of heater side/end plates, with scalent de-carbonizing, scraping out carbon ,dirt acculated in heater, overhauling, servicing incl re- assembling all the dismantled component to its original position with testing and commissioning, Complete all as specified and directed by Engineer-in-Charge. | 23 | Each Job | 5,000 ₹1,15,000 Lowest | 10,000 ₹2,30,000 |
Tender Value
₹35.0 L
EMD Value
₹69,960
Closing Date
15 Oct 2025, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
CWE KHUMBATHANG
HQ CWE KHUMBATHANG PIN 900270 C.O 56 APO
REPAIR/MAINT OF CENTRAL HEATING PLANT, STAND ALONE CHS AND ELECT CHS AND OTHER CONNECTED WORKS AT NIMU/NURLA UNDER AGE (I) NIMU
2025_MES_731289_1
80051/39/2025-26
Open Tender
Civil Works
Item Rate
210 days
NURLA, NIMU
CLASS D and above and Cat c (i)
8 documents required · 8 mandatory
₹500
AGE (I) NIMU
₹69,960
Yes
10 Dec 2025
17 Sept 2025
16 Oct 2025
17 Sept 2025
15 Oct 2025
2 Oct 2025
17 Sept 2025 - 1 Oct 2025
Amount
Material and labour for attending of complaint for day to day maintainence / daily complaints by checking the serviceability of fan coil unit of any capacity for having continuous sreviceability of FCU for any number of time as desired by Engr-in-Charge including replacement of minor spare part like Gasket, Teflon tape, flare nut, tightening of any loose glycol line connections, shifting FCU from one place to another place if required, heating up the freezed glycol line anywhere about the premices to have continuous flow of glycol fluid, stopping any kind of leakage from any size of pipe line, tightening the loose electrical connections as related with FCU / Heating system, cleaning the air filter including radiator of FCU to the entire satisfaction of Engineer-in- Charge all as directed at site Note :- (i) Attending any complaints of different nature in a single day in Plant Room inside / outside will be considered as one job. ii) Any kind of replacement of major items shall be measured and paid for separately under respective item of schedule 'A' Part-II iii) . Any nature of complaint related with FCUs, radiators, bursting/cracking/leakage of MS pipe lines, replacement of valves etc will be completed round the clock by suitable trademen (welder with suitable T & P,(including portable heating materials)-01,Skilled mechanic of CHS-01, Plumber/Fitter with helper-each 01, Supervisor-01 as per directions of Engineer-in- Charge.
Supply and fixing in replacement of fan coil unit 1.5/2 Ton duel shaft electric motor 30 watt 930 RPM, 3 speed as per existing, complete all as specified and directed. Make- as per existing
Supply and fixing in replacement of Old unsv radiator unit of FCU 1.5 Ton including connecting with the unit and making it leakproof of copper coils covered with aluminium finishing as per existing size of capacity 3000 K Cal / Hour complete all as specified and directed.
Supply and fixing in replacement of Old unsv radiator unit of FCU 2 Ton including connecting with the unit and making it leakproof of copper coils covered with aluminium finishing as per existing size of capacity 6000 K Cal / Hour complete all as specified and directed.
Fixing only fan coil unit 1.5 Ton as per existing connection complete all as specified and directed.
Fixing only fan coil unit 2 Ton as per existing connection complete all as specified and directed.
Material and labour for Dismantling of burner assembly at plant room CHS and removing of side cover and repairing the same by removing the old burnt fire refractory cement plastering, replastering the same as per existing fire refractory cement for boiler capacity 6 lakh Kcal/hr and complete servicing the boiler by removing the complete carbon/oil deposits with suitable coil shine chemical including repair to coil assembly by welding if there is any leakage found or any other repair required at site and reassembling/ testing the same, complete all as specified and directed.
All as per srl item No. 7 here-in-before but for 4 Lakh Kcal/Hr complete all as specified and directed.
M&L for dismantling Glycol based electrical operated central heating boiler of capacity 75 KW of capacity 75000 Kcal/hr by unscrewing and removal of heater side/end plates, with scalent de-carbonizing, scraping out carbon ,dirt acculated in heater, overhauling, servicing incl re- assembling all the dismantled component to its original position with testing and commissioning, Complete all as specified and directed by Engineer-in-Charge.
M&L for dismantling Standalone air heater for space heating of capacity 50000 Kcal/hr by unscrewing and removal of heater side/end plates, with scalent de-carbonizing, scraping out carbon ,dirt acculated in heater, overhauling, servicing incl re- assembling all the dismantled component to its original position with testing and commissioning, Complete all as specified and directed by Engineer-in-Charge.
M&L for dismantling of the blower motor of Stand alone air heater for space heating of capacity 50000 K/Cal Hr incl rewinding of blower motor with suitable size/gauge of copper wire including replacement of suitable blower fan sweep and blower fan guard and refixing of the same after varnishing, Complete all as specified and directed by Engineer-in-Charge.
Material and labour including taking down and Re fixing for rewinding of electric motor 3 phase 415 volts of capacity 7.5/10 HP with superior quality super enameled copper winding wire of appropriate size and gauge as existing including varnishing , cotton tape, PVC sleeves etc, complete all as specified and directed.
M&L for servicing to the glycol pump and motor of capacity 7.5/10 HP, 2870 RPM including replacement of bearings, oil seals or any other spares / work required for smooth functioining of pump, complete all as specified and directed. Note - Major items replaced shall be measured and paid for separately under item No 14-17 of BoQ.
Supply and replace Ball Bearing of suitable size complete all as specified and directed
Supply and replace Oil seal /Gland complete all as specified and directed.
Supply and replace Air circulation Fan (Plastic) complete all as specified and directed.
Supply and replace Impellers complete all as specified and directed.
Material and labour incl taking down and Re fixing for rewinding of electric motor single phase 230 volts of capacity 01/ HP with superior quality super enameled copper winding wire of appropriate size and gauge as existing including varnishing , cotton tape, PVC sleeves etc, complete all as specified and directed.
M&L for servicing to the glycol make up pump and motor of capacity 01 HP, 2870 RPM including replacement of bearings, oil seals or any other spares / work required for smooth functioining of pump, complete all as specified and directed. Note - Major items replaced shall be measured and paid for separately under item No 20-23 of BoQ.
Supply and replace Ball Bearing of suitable size complete all as specified and directed.
Supply and replace Oil seal /Gland complete all as specified and directed.
Supply and replace Air circulation Fan (Plastic) complete all as specified and directed.
Supply and replace Impellers complete all as specified and directed.
S&F in sequence controller suitable for 6 lakh kilo/hr LAL 2.25 burner rod assembly, complete all as specified and directed.
S&F in sequence controller suitable for 4 lakh kilo/hr LAL 2.25 burner rod assembly, complete all as specified and directed .
S&F in replacement of ignition rod suitable for 06 lakh Kcal/hr burner rod assembly as per sample complete all as specified and directed.
S&F in replacement of ignition rod suitable for 04 lakh Kcal/hr burner rod assembly as per sample, complete all as specified and directed.
S&F in replacement of ignition Transformer electronic type suitable for 6 lakh Kcal/hr burner rod assembly as per sample complete all as specified and directed.
S&F in replacement of ignition Transformer electronic type suitable for 4 lakh Kcal/hr burner rod assembly as per sample complete all as specified and directed.
S&F temp controller digital type DTC 503 with sensor suitable for 6 lakh Kcal/hr LAL 2.25 burner rod assembly, complete all as specified and directed.
S&F temp controller digital type DTC 503 with sensor suitable for 4 lakh Kcal/hr LAL 2.25 burner rod assembly, complete all as specified and directed.
S&F in replacement of pressure gauage 4" dial 0 to 10 Kg/Sqcm as per existing, complete all as directed by Engineer-in-Charge.
S&F in replacement of digital type volt meter 0-500 volts, complete all as specified and directed.
S&F in replacement of photo cell as per existing suitable for 6 lakh Kcal/hr burner rod assembly, complete all as specified and directed.
S&F in replacement of photo cell as per existing suitable for 4 lakh Kcal/hr burner rod assembly, complete all as specified and directed.
S&F in replacement of digital type Amp meter complete with suitable CTs 0-300 Amps, complete all as specified and directed.
S&F in replacement of indicating lamps RYB as per existing complete all as specified and directed.
S&F in replacement of rotary type ON/OFF switches, 22mm dia as per existing, complete all as specified and directed.
S&F in replacement of DOL starter MK-1, 7.5/10 HP as per existing, complete all as specified and directed.
Supply and fix in replacement exhaust fan made of steel body complete with frame, voltage 230V, 50 Hz, RPM 1200, Copper winding of sweep 380/400mm complete as specified and directed.
Cleaning of MS diesel storage tanks of capacity 1000 Ltrs by removing of sludge from tanks and scrapping the side walls by means of wire brush or emery paper and wash the same with caustic soda and clear water and painting the internal wall with two coats of black rubber emulsion paint and painting the complete tank from out side with two coats of synthetic enamel paint, complete all as specified and directed.
S&F in replacement of PVC flexible copper multistrand wire 3 core of 2.5 sqmm as per existing, complete all as specified and directed.
S&F in replacement of burner nozzle suitable for 6 lakh K/Cal/Hr complete all as specified and directed.
S&F in replacement of burner nozzle suitable for 4 lakh K/Cal/Hr complete all as specified and directed.
S&F in replacement of Electrode suitable for burner of capacity 6 lakh K/Cal/Hr complete all as specified and directed.
S&F in replacement of Electrode suitable for burner of capacity 4 lakh K/Cal/Hr complete all as specified and directed.
S&F in replacement of High pressure fuel pipe 1.5 mtr length as per existing, complete all as specified and directed.
S&F in replacement of FCU connection flexible pipe 20/16 mm as per existing, complete all as specified and directed.
S&F in replacement insulation 13mm as per existing, complete all as specified and directed.
S&F in replacement of plug top 15/5 Amps as per existing, complete all as specified and directed.
S&F in replacement of gun metal butter fly control valves of 100 mm bore as per existing, complete all as specified and directed.
S&F in replacement of gun metal butter fly control valves of 80mm bore as per existing, complete all as specified and directed.
S&F in replacement of gun metal butter fly control valves of 40/50mm bore as per existing, complete all as specified and directed.
S&F in replacement of inlet outlet Ball valve 3/4" with stainer for FCU as per existing, including supply and fixing MS / GI nipple of size 3/4 inch includig welding work including cutting the existing rusty unserviceable MS/GI nipple complete all as specified and directed.
M&L for repair of exaust pipe of boiler/MS pipe by welding, complete all as specified and directed by Engr-in-Charge.
S&F for closed cell elastometric insulation 30 to 40 Kg/Cub mtr density 19 mm thick (nitrile insulation) complete all as specified and directed.
S&F in replacement of auto air pressure valve 3/8" as per existing, complete all as specified and directed.
Supply and filling of Mono Ethylene Glycol (MEG) of 99% purity and having freezing temperature less than -40° in Central heating plant all as specified and direced by Engineer-In- Charge.
Supplying and laying, connecting, fixing in repair/replacement including taking out the existing pipe and testing of MS ERW'C' class piping complete with fittings,duly insulated with 18mm/13 mm thick closed cell elastomeric insulation 30 to 40 KG/m3 density Hot Glycol fluid pipes 65mm bore with 13mm thick nitrile insulation. (The pipes shall be provided with 24 SWG aluminium cladding over the insulation for exposed piping only and underground pipe shall be laid down till 1.5m in depth)
All as per item Ser No 59 above but of size 50 mm bore
All as per item Ser No 59 above but of size 40 mm bore
All as per item Ser No 59 above but of size 32 mm bore
All as per item Ser No 59 above but of size 25 mm bore
All as per item Ser No 59 above but of size 20 mm bore
Material and Labour for laying MS Pipes heavy grade 80 mm bore in any length laid in trenches pressure testing, welding of pipe, washing out complete including dismantling, taking out old corroded pipe line including all fittings complete all as specified and directed.
All as per item Ser No 65 above but of size 100 mm bore
All as per item Ser No 65 above but of size 150 mm bore
Excavatoin in trenches not exceedng 1.5 mtr wide but exceeding 1.5 mtr in depth for laying of pipe and getting out all in hard and dence soil.
Returning filling in including spreading watering and well ramming in layer not exceeding 25mm thick in hard/ dence soil
Removing excavated material (soil) to a distance not exceeding 50 mtr and depositing where directed at a level not exceeding 1.5 mtr above starting point.
Cleaning and repairing of blockage choke in the hot water boiler of capacity 400000 kcal per hr as per approved specification and direction of Engineer-in-Charge.
Repairing of fan coil radiator and coil pipe leakage in certain areas/ barrack/hopitales etc and all as per approved specification and direction of Engineer-in-Charge.
Repairing of leakage in MS pipe of size 25mm to 50 mm dia with required type of welding including gas welding. as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of fuel pump as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of fuel filter assembly .as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of oil pump sensor as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of photo cell with wire as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of burner connector as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of Air flow sensor as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and repairing of glycol pump starter as per approved specification and direction of Engineer-in-Charge.
Supply & fixing in repairs with Providing and replacement of temperature meter of boiler as per approved specification and Engineer-in-Charge. charge
S&F in replacement of pressure gauage 4" dial 0 to 10 Kg/Sqcm as per existing, complete all as directed by Engineer-in-Charge.
S&F in replacement of digital type volt meter 0-500 volts, complete all as specified and directed.
Supply and fixing in replacement Fan coil unit of capacity 4500 K Cal/Hr with copper tubing and fins and having hot water inlet and outlet of 15 MM dia suitable for CHS including fitting and testing, Complete all as specified and directed by Engineer-in-Charge.
Note:-The accepted amount will be arrived after deducting the Sch of credit i.e. Rs 183994.00 and any other reduction if any from quoted amount.
M/S BHAT ENGINEERING WORKS (BID ID -3445778)
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .