Loading…
Loading…
Tender ID
Tender Value
₹35.0 L
EMD Value
₹25,000
Closing Date
4 Mar 2026, 9:00 amClosed
MANJEET DAHIYA
Municipal Committee Kundli
Providing and laying of PVC Pipeline in various streets of ward no. 5 in MC Kundli
2026_HRY_503968_1
2026D8F9A7C3 3E49 4764 B1B7 638FC5EE0F731676ULB
Open Tender
Civil Works
Works
120 days
Kundli(MC)
All skilled and unskilled works costing up to 1 crore will be reserved for Cooperative Labour and Construction Societies at the rates approved for similar works in the recent past, through tenders within the concerned PWD circle
2 documents required · 2 mandatory
₹5,000
₹25,000
Yes
25 Feb 2026
19 Feb 2026
4 Mar 2026
19 Feb 2026
4 Mar 2026
19 Feb 2026
Revised Providing and Laying 315 mm outer dia UPVC pipe Class 1 with Working Pressure 0.40 MPa (4kg/cm2) duly ISI marked IS 4985:2000 complete in all respect as per directions of Engineer-in-charge
Percentage BoQ
BoQ_Ver3.0
Name of the Bidder/ Bidding Firm / Company :
PRICE SCHEDULE (This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only )
NUMBER #
[13.28]Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. [Through Rate]
[21.95.5]Providing lowering cutting jointing and testing RCC pipe class NP3 as per IS-458-2003 with spigot and socketed joints manufactured with ISI marked sulphate resistance cement as per ISI 12330 with rubber rings ISI marked antiternmite as required at site in to trenches for all depths and laying out the same to correct alignment gradients and levels including dressing and trimming and cutting of concrete beds and side of trenches, if required jointing with rubber rings in trenches and jointing with 1:3/2 cement sand mortar and with end dowels filled with 1:3/2 cement sand mortar and finishing the joints at an angle of 45 degree with faces of spigot of socket joints cutting and finishing the cut surface to a uniform finish etc. as fully described in item No. 21.38, item 21.44, item 21.45, and item 21.46 including cartage loading and unloading complete in all respects. the internal diametric of the sewer being: 5. 600 mm [Through Rate]
[22.201.2.1]Providing and fixing in position pre-cast R.C.C. manhole cover and frame of required shape and approved quality 2.1. M D - 10 Square shape 450 mm internal dimension [Through Rate]
[5.23.1]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 1. Nominal concrete 1:1.5:3 or richer mix (i/c equivalent design mix) [Through Rate]
[6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate]
[6.33.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Labour Rate]
[6.33.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate]
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.14 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.69 MB
BOQ_582664.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .