| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹47.9 LAccepted-AOC | L1 | Accepted-AOC Agreement Executed | |
| 2 | L2₹49.6 L+₹1.7 L (3.58%)Rejected-Finance KIZHUKKARAKKATTU HOUSE KOORACHUNDU KOZHIKODE 673527 | KOZHIKODE | KERALA | 673527 | L2 | Rejected-Finance Higher rate quoted | |
| 3 | L3₹59.9 L+₹12.0 L (25.2%)Rejected-Finance | L3 | Rejected-Finance Higher rate quoted | |
| 4 | L4₹61.7 L+₹13.9 L (29.0%)Rejected-Finance CHITHAN VIL ATHYAPI P O MALAPPURAM 676517 | MALAPPURAM | MALAPPURAM | KERALA | 676517 | L4 | Rejected-Finance Higher rate quoted | |
| 5 | L5₹64.3 L+₹16.4 L (34.3%)Rejected-Finance | L5 | Rejected-Finance Higher rate quoted |
Tender Value
₹71.4 L
EMD Value
₹50,000
Closing Date
8 Oct 2021, 4:00 pmClosed
Executive Engineer
Office of the Executive Engineer, PWD Roads Division, Kozhikode
EKD-Reconstruction of damaged side protection wall at km 29/500 of Ekarool Kakkayam Damsite road
2021_PWD_442609_1
DB2/TN/24/2021-22
Open Tender
Civil Works - Roads
Item Rate
180 days
Kakkayam
Please refer Tender documents.
8 documents required · 8 mandatory
₹2,760
Yes
₹50,000
Yes
3 Jan 2022
30 Sept 2021
11 Oct 2021
30 Sept 2021
8 Oct 2021
30 Sept 2021
Amount
CONSTRUCTION OF RETAINING WALL
3.13.1.B:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. Ordinary soil - Mechanical Means - (Depth upto 3 m)
2.3.1.B:Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness In area of thorny jungle -By Manual Means
3.13.4.A:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work Hard Rock ( blasting prohibited ) - Mechanical Means
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
13.5.E.P.1:Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications RCC Grade M20 - Using concrete Mixer - Height upto 5m
OD38653/2021-2022:Providing and fixing Dowel Bars with 16mm HYSD bars 2.00m length, 1.00m below ground and 1.00m above ground level on rock surface by drilling with air compressor 250cfk with 2 jack hammers, fixing the dowel bar in the borehole with cement slurry etc complete
12.8.1.C:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer - (Without formwork)
12.8.A.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15
13.8:Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V : 20H towards drawing foce.Complete as per drawing and Technical Specifications
13.9.A:Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification Granular material
12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
8.8:Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
15.5:Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification
REJIJOSEPH K
APA Transporters and Builders
ASHRAF CHEERANGAN
Abdul Ashik B.A
Bidder Name
REJIJOSEPH K
Abdul Ashik B.A
APA Transporters and Builders
ASHRAF CHEERANGAN
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_629937.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .