| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.8 LAccepted-AOC | L1 | Accepted-AOC AGMNT EXECUTED | |
| 2 | L2₹7.8 L+₹187.13 (0.02%)Rejected-Finance | L2 | Rejected-Finance L2 |
Tender Value
₹7.1 L
EMD Value
₹17,657
Closing Date
18 Mar 2025, 12:00 pmClosed
SUPERINTENDING ENGINEER
O/o SE, Kozhikode Corporation, [email protected]
Please refer Tender document
2025_LSGD_748950_1
PP/EG7/2024-25/SE/536
Open Tender
Civil Works - Others
Item Rate
300 days
Kozhikode Corporation
Please refer Tender documents.
11 documents required · 11 mandatory
₹1,560
Yes
₹17,657
Yes
28 May 2025
11 Mar 2025
18 Mar 2025
11 Mar 2025
18 Mar 2025
11 Mar 2025
Amount
compound wall
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
2.7.1:Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
50.6.7.1:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc.
10.26.1:Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.M.S. tube
4.1.4:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 )1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size)
OD202248/2024-2025:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work
BALAKRISHNAN K P (BID ID -2161031)
Bidder Name
ADHARSH K
BALAKRISHNAN K P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1211525.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .