| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹25.0 LAccepted-AOC | L1 | Accepted-AOC L1 BIDDER | |
| 2 | L3₹27.6 L+₹2.5 L (10.2%)Rejected-AOC | L3 | Rejected-AOC L3 BIDDER | |
| 3 | L4₹27.1 L+₹2.1 L (8.29%)Rejected-AOC | L4 | Rejected-AOC L4 BIDDER | |
| 4 | L4₹28.4 L+₹3.4 L (13.5%)Rejected-AOC | L4 | Rejected-AOC L4 bidder | |
| 5 | L5₹28.5 L+₹3.5 L (13.8%)Rejected-AOC | L5 | Rejected-AOC L5 BIDDER |
Tender Value
₹33.8 L
EMD Value
₹50,000
Closing Date
5 Apr 2025, 6:00 pmClosed
Executive engineer Irrigation division kozhikode
O/O Executive engineer Irrigation division kozhikode
GENERAL-Iruvanhipuzha side protection- Protecting the left bank of Iruvanjipuzha downstream of Mukkam kadavu Bridge near Anayamkunnu road in Karassery Panchayath in Kozhikode district-General Civil Work
2025_Irrig_755621_1
EEIK/ET-28/2024-25
Open Tender
Civil Works - Others
Item Rate
Anayamkunnu
Please refer Tender documents.
11 documents required · 11 mandatory
₹2,760
Yes
₹50,000
Yes
3 Jun 2025
27 Mar 2025
8 Apr 2025
27 Mar 2025
5 Apr 2025
27 Mar 2025
Amount
Side Protection Works
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
60.7.6:Supplying and stacking granite stone 20 to 45 dm3 for dumping works- Supplying at site of work granite stone 20 to 45 dm3 in size (60% 45m3,30%30 to 40dm3 and 10% 20 to 30dm3 stones) for measurement ( deducting not less than 15% for voids as fixed by the departmental officer at site) including all cost, conveyance, loading and unloading charges all other incidental charges all leads and lifts etc. complete as per the direction of the departmental officers at site.
60.7.7:Conveyance and dumping of departmental granite stones-Conveyance of departmental granite stone 20 to 45 dm3 in size from stack at site and dumping in position (60% 45m3,30%30 to 40dm3 and 10% 20 to 30dm3 stones) to lines and levels to from the core of the sea wall as per approved design including all leads and lifts etc. complete as per the direction of the departmental officers at site.
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
Abdul Hameed NK (BID ID -2188180)
Kodiyathur Labour Contract Co_Operative Socity Ltd D 2888 (BID ID -2188306)
Nellikkaparamba Labour Contract Co-operative Society Ltd No D 3188 (BID ID -2182146)
SHIMIL SHOUKATH U P (BID ID -2188246)
ANSILMUHAMMEDHASSAN CHALAKANDI (BID ID -2185274)
Bidder Name
Abdul Hameed NK
Kodiyathur Labour Contract Co_Operative Socity Ltd D 2888
Nellikkaparamba Labour Contract Co-operative Society Ltd No D 3188
ANSILMUHAMMEDHASSAN CHALAKANDI
MUHAMMED NAUJAN MALIYAKKAL
SHIMIL SHOUKATH U P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .