| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹1.5 CrAccepted-AOC | ₹1.5 Cr | L-1 | Accepted-AOC Accepted |
| 2 | L-2₹1.6 Cr+₹13.0 L (8.64%)Rejected-AOC | ₹1.6 Cr+₹13.0 L (8.64%) | L-2 | Rejected-AOC Rejected |
| 3 | L-3₹1.7 Cr+₹23.1 L (15.4%)Rejected-AOC | ₹1.7 Cr+₹23.1 L (15.4%) | L-3 | Rejected-AOC Rejected |
| 4 | Rejected-Technical | - | - | Rejected-Technical Rejected |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Others-Cost of tender document not submitted |
Tender Value
₹1.9 Cr
EMD Value
₹3.9 L
Closing Date
5 Oct 2023, 4:00 pmClosed
Managing Director
Assam Industrial Development Corporation Ltd., R.G.Baruah Road, Guwahati-781024
Construction of Boundary Wall at Industrial Growth Centre (IGC) Balipara from Main Gate to the Boundary wall of M/s Patanjali Ayurved Ltd. via Nepali Basti including construction of exposed walls in Phase-I area.
2023_ICD_32540_1
ECF No 344199
Open Tender
Civil Works
Item Rate
180 days
IGC Balipara
Please refer Tender documents.
4 documents required · 4 mandatory
₹3,860
₹3.9 L
Yes
5 Feb 2025
15 Sept 2023
6 Oct 2023
15 Sept 2023
5 Oct 2023
18 Sept 2023
Amount
Civil Works
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared.
Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge: All kinds of soil
Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources)
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand)
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size de rived from natural sources)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level: Cement mortar 1:4 (1 cement :4 coarse sand)
Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns, etc. for mass concrete
Centering and shuttering including strutting, propping etc. and removal of form for: Lintels, beams, plinth beams, girders, bressumers and cantilevers
Centering and shuttering including strutting, propping etc. and removal of form for: Columns, Pillars, Piers, Abutments, Posts and Struts
15 mm cement plaster on the rough side of single or half brick wall of mix : 1:4 (1 cement: 4 fine sand)
12 mm cement plaster of mix : 1:4 (1 cement: 4 fine sand)
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level: Mild steel and Medium Tensile steel bars
Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used: With G.I. barbed wire
Maa Corporation
PANKAJ KHANIKAR
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .