| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.7 LAccepted-AOC | L1 | Accepted-AOC As per panchayat Board Resolution | |
| 2 | L2₹7.4 L+₹78,001.39 (11.7%)Rejected-AOC | L2 | Rejected-AOC As per panchayat Board Resolution | |
| 3 | L3₹7.5 L+₹89,143.02 (13.4%)Rejected-AOC | L3 | Rejected-AOC As per panchayat Board Resolution |
Tender Value
₹7.5 L
EMD Value
₹11,230
Closing Date
18 Jan 2022, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Assistant Engineer
LSGD section Chelannur, ChelannurGramaPanchayat, Kannankara (P.O), Kozhikode - 673616
Drinking water project works
2022_LSGD_466592_1
11/ET/2021-22
Open Tender
Civil Works - Water Works
Item Rate
180 days
Chelannur GP
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,497
₹11,230
Yes
26 May 2022
10 Jan 2022
22 Jan 2022
10 Jan 2022
18 Jan 2022
10 Jan 2022
90 days
Amount
Construction of Well
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
od1311090/2021_2022 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.<br>All kinds of soil
od1311091/2021_2022 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.<br>All kinds of soil
od1311092/2021_2022 : Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.<br>All kinds of soil
50.5.7 : Reinforced cement concrete work in well-staining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1. 5:3 ( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.9.12 : Centering and shuttering including strutting, etc. and removal of form for:Well steining
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.2.3.1 : Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
9.48.1 : Providing and fixing M.S. Grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. including priming coat with approved steel primer all complete.Fixed to steel windows by welding
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
od1311094/2021_2022 : Supplying and filling around well steining, stone chips for filtering purpose. Stone screening 11.2mm nominal size (Type B)
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
od1589676/2021_2022 : Filling with contractor own earth (excluding rock) in open areas in layer not exceeding 20 cm in depth,consolidatingeach deposited layer by ramming and watering, lead upto 50m and lift up to 1.5m as per direction of site Engineer-in-charge.
od1548150/2021_2022 : :Excavating trenches of required width for pipes, cables, etc including excavation forsockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavatedsoil, and then returning the soil as required, inlayers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, withina lead of 50 m :
od1548151/2021_2022 : :Providing and fixing PVC pipes includes jointing of pipes with one step PVC solventcement, trenching, refilling & testing of joints complete as per direction of Engineer in Charge. 25 mm dia10KGF/cm2(<br>MODIFIED 50.18.9.3.2 WITHOUT TRENCHING AND REFILLING )
od1588886/2021_2022 : Providing street fountains with vertical posts by 75 mm PVC pipe 1.20m long fixed in concrete filled with cc 1:3:6 , 20 mm metal and erected on a cc platform for in 1:3:6 20mm metal , and connecting the taps in position including all cost conveyance etc. complete (cost of tap and connecting pipe should be paid separately)
ABDUL HAKKEEM V P
shahinshad
Bidder Name
V. ASHRAF
shahinshad
ABDUL HAKKEEM V P
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_668224.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .