Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance ROOM NO 3 1ST FLOOR SULTAN ANNEXE 168 LBS MARG KURLA WEST MUMBAI MAHARASHTRA 400070 | MUMBAI SUBURBAN | MAHARASHTRA | 400070 | Admitted-Finance |
| 2 | Admitted-Finance NO 2254 RAGHAVENDRA COLONY SHAKTINAGAR RAICHUR RAICHUR KARNATAKA 584170 | RAICHUR | KARNATAKA | 584170 | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
Tender Value
Refer Docs
Closing Date
6 Aug 2021, 10:00 amClosed
PARAU MURMU
MES DEPT ROOM NO 25 ADMIN BUILD RCF LTD CHEMBUR MUMBAI-400074
Biennial rate Contract of maintenance jobs during Annual IBR inspection and certification of Boilers at RCF Trombay.
2021_RCFL_638664_1
ET-MES/602/L/2122/009
Open Tender
Miscellaneous Services
Item Rate
730 days
MES DEPT ROOM NO 25 ADMIN
AS PER NIT
12 documents required · 12 mandatory
₹0
Exempted
22 Sept 2021
16 Jul 2021
6 Aug 2021
16 Jul 2021
6 Aug 2021
16 Jul 2021
Amount
Part A: Statutory Charges for Certification: AS PER NIT NOTE-The statutory charges (AS PER NIT) are to be paid by vendor at the time of booking of visit of IBR authority. These charges shall be reimbursed at actual after completion of work as per SOW.
Part B: Opening / Slip plating of Boilers, Cleaning, Hydrotesting and arrangement of conveyance during Certification:
Job #1: Ammonia I – WH Loop Boiler No. MR-12969.
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydrotest witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job #2: Ammonia I – RG/CG Boiler No. MR-11635
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydrotest witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job #3: Ammonia V – Syn. Loop Boiler No. MR-13916.
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydrotest witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job #4: Ammonia V – RG Boiler No. MR-10615
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydrotest witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Lumpsum charges for utilization of crane for removal & box up of RG boiler tube bundle including mobilization / de-mobilization as per scope of work
Job# 5: Urea - (Carbamate Condenser-E-604) Boiler No. MR-11871
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job# 6: Urea - (New Carbamate Condenser-E-604B)
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job # 7: HPNA Plant – WH Boiler No. MR-13648
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job # 8: MPNA Plant – WH Boiler No. MR-10236
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job# 9: SAP Plant – WH Boiler No. MR-11942
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job #10: SAP Plant – Economizer (MR 989)
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job # 11: Methanol Plant – LP Boiler (MR-14765)
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Job # 12: Methanol Plant – PG Boiler (MR-14800)
Lumpsum charges for opening, cleaning, slip plating, preliminary & final hydro-testing and final box up as per SOW along with arranging conveyance for visit of IBR Authority for all stage wise inspections, dry inspection hydro-test witnessing and any special visit during certification process.
Lump-sum charges for extension of certificate including arranging of conveyance for IBR Authority visit.
Part C: Opening & Boxing up of Valves, Servicing & Overhauling of Valves during Certification:
Opening and box-up/replacement of Gate / Globe / NRV valves (rating up to 600 #)
Size : Ø1" up to Ø3''
Size : Ø4" up to Ø6''
Size : Ø 8" up to Ø 10''
Opening and box-up/replacement of Gate / Globe / NRV valves (rating of 1500 # & 2500#)
Size : Ø1" up to Ø3''
Size : Ø 12" and above
Servicing /Overhauling of Gate / Globe / NRV valves (rating up to 600 #)
Size : Ø1" up to Ø3''
Size : Ø4" up to Ø6''
Size : Ø 8" up to Ø 10''
Servicing /Overhauling of Gate / Globe / NRV valves (rating of 1500 # & 2500#)
Size : Ø1" up to Ø3''
Size : Ø 12" and above
Super Steam Boiler Engg Pvt Ltd
P SUNNY ENGINEERING CONTRACTOR
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .