| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.4 LAccepted-AOC | ₹9.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹10.3 L+₹91,675 (9.80%)Rejected-AOC | ₹10.3 L+₹91,675 (9.80%) | L2 | Rejected-AOC L2 |
| 3 | L3₹11.5 L+₹2.1 L (22.4%)Rejected-AOC | ₹11.5 L+₹2.1 L (22.4%) | L3 | Rejected-AOC L3 |
| 4 | L4₹12.8 L+₹3.4 L (36.5%)Rejected-AOC | ₹12.8 L+₹3.4 L (36.5%) | L4 | Rejected-AOC L4 |
| 5 | L5₹13.3 L+₹3.9 L (42.0%)Rejected-AOC | ₹13.3 L+₹3.9 L (42.0%) | L5 | Rejected-AOC L5 |
| Sl No | Description | Qty | Unit | G RAJESH L2 | P.R.SELVAN L6 | CS.JOHN L3 | V prakasan L5 | AIRESH L1 | Ratheesh L4 |
|---|---|---|---|---|---|---|---|---|---|
| 1.00Working charge | |||||||||
| 1.00 | 100.51.1: Disconnecting water connection from service mains along earthern road without causing any damage to the existing line including charges of earth work excavation in all kinds of soil for exposing connection point including tar cutting / conrete cutting if any, making the disconnection point water tight charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other existing utilities, including the charges of hire for tools and plant, conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of materials and as per the direction of departmental officers etc. complete. | 165 | Disconnection | 844 ₹1,39,260 | 1,000 ₹1,65,000 | 870 ₹1,43,550 | 1,009.54 ₹1,66,574.1 | 700 ₹1,15,500 Lowest | 970 ₹1,60,050 |
| 1.00 | 100.51.2:Disconnecting water connection from service mains along Concrete road without causing any damage to the existing line including charges of earth work excavation in all kinds of soil for exposing connection point including tar cutting / conrete cutting, making the disconnection point water tight charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other existing utilities, including the charges of hire for tools and plant, conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of materials and as per the direction of departmental officers etc. complete. | 800 | Disconnection | 844 ₹6,75,200 | 1,085 ₹8,68,000 | 890 ₹7,12,000 | 1,038.06 ₹8,30,448 | 700 ₹5,60,000 Lowest | 997.59 ₹7,98,072 |
| 1.00 | 100.51.3:Disconnecting water connection from service mains along Asphalt road without causing any damage to the existing line including charges of earth work excavation in all kinds of soil for exposing connection point including tar cutting / conrete cutting, making the disconnection point water tight charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other existing utilities, including the charges of hire for tools and plant, conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of materials and as per the direction of departmental officers etc. complete. | 200 | Disconnection | 844 ₹1,68,800 | 1,100 ₹2,20,000 | 888 ₹1,77,600 | 1,031.17 ₹2,06,234 | 700 ₹1,40,000 Lowest | 990.98 ₹1,98,196 |
| 1.00 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 16.1 | cum | 250 ₹4,025 Lowest | 800 ₹12,880 | 990 ₹15,939 | 1,148.41 ₹18,489.4 | 1,100 ₹17,710 | 1,103.65 ₹17,768.77 |
| 1.00 | 4.1.4:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded
stone aggregate 40 mm nominal size derived from natural sources) | 16 | cum | 2,500 ₹40,000 Lowest | 4,500 ₹72,000 | 6,000 ₹96,000 | 6,695.49 ₹1,07,127.84 | 6,400 ₹1,02,400 | 6,434.49 ₹1,02,951.84 |
Tender Value
₹18.0 L
EMD Value
₹44,967
Closing Date
17 Sept 2025, 11:00 amClosed
Executive Engineer
office of executive engineer,P.H.Division,KWA, Alappuzha.
DEPOSIT-AWSS- Alappuzha Municipality -Disconnection for Public Tap-Pipeline Work
2025_KWA_795157_1
WRD/KWA-CE(CR)/EST/15729/2024
Open Tender
Civil Works - Water Works
Item Rate
90 days
Alappuzha municipality
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,760
Yes
₹44,967
Yes
29 Oct 2025
9 Sept 2025
18 Sept 2025
9 Sept 2025
17 Sept 2025
9 Sept 2025
9 Sept 2025 - 17 Sept 2025
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1314726.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .