Tender Value
₹27.7 Cr
EMD Value
₹15.3 L
Closing Date
27 Dec 2025, 2:00 pmClosed
Yes (up to 3 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
Above/Below/Par
WORKS
14 conditions · 2 needing a document upload
Financial Eligibility Criteria: The tenderer must have minimum average annual contractual turnover of V/N or V whichever is less crores; where V = Advertised value of the tender in crores of Rupees, N = Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderer(s) shall submit requisite information as per Annexure-VIII, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheets.
(a) The tenderer must have successfully completed/substantially completed any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of the tender. (b) (i) In case of composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed/substantially completed any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or Two similar works , each costing not less than the amount equal to 40% of advertised value of each component of tender, or a One similar work, each costing not less than the amount equal to 60% of advertised value of each component of tender. Note: Separate completed works of minimum required values for each component can also be considered for fulfillment of technical eligibility criteria. (b) (ii) In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity. Any work or set of works shall be considered to be a separate component, only when cost of the component is more than Rs. 2 crore each. The tenderer shall submit the completion certificate as per proforma given in Annexure-IV-A or IV-B or IV-C as applicable or in the format containing all information as required as per the Annexure-IV-A or IV-B or IV-C. Note :- Criteria for the completed work/substantially completed has been given in the General Instructions in the Standard Tender Document.
Defination of Similar Work :- Civil / Composite work involving construction of formation (cutting / filling / blanketing) and / or construction of bridges.
65 conditions · 7 needing a document upload
In case the tenderer is (iii) Labour Cooperative Societies - shall deposit only 50% of the Earnest Money Deposit and shall submit certified copy of the registration/ Valid document issued by the relevant Ministry/ Labour commission (mandatory if applicable).
In case the tenderer is (i)Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' - shall be exempted from payment of Bid security deposit and shall submit certified copy of the registration/ Valid document issued by DIPP (mandatory if applicable)
"Mandatory in case Bid security amount is prescribed in STD Para 5.1.2 - The Bid Security shall be deposited in cash through e-payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure- XXXII and shall be valid for a period of 90days beyond the bid validity period. "
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
The initial e-Reverse Auction ( e-RA) period as mentioed in the Clause no. 26.1 (b), Annexure C, Para 2 of the "GENERAL INSTRUCTIONS" of Tender Document will be as per railway board guidelines or as approved by Tender accepting authority . (Applicable to the works and service tenders of value more than Rs. 50 crore.)
The auto extension period as mentioed in the Clause no. 26..1(b), Annexure C, Para 2 of the "GENERAL INSTRUCTIONS" of Tender Document will be as per railway board guidelines or as approved by Tender accepting authority .(Applicable to the works and service tenders of value more than Rs. 50 crore.)
The Minimum Increment as mentioed in the Clause no. 26.1 (b), Annexure C, Para 2 of the "GENERAL INSTRUCTIONS" of Tender Document will be as per railway board guidelines or as approved by Tender accepting authority . (Applicable to the works and service tenders of value more than Rs.50 crore.)
I/We have read the various conditions to tender attached here to and agree to abide by the said conditions. I/We also agree to keep this tender open for acceptance for a period as mentioned in NIT header from the date fixed for opening the same and in default thereof, I/We will be liable for forfeiture of my/our "Bid security". I/We offer to do the work for North Western Railway, at the rates quoted in the attached schedule and hereby bind myself/ourselves to complete the work in all respects within time period as mentioned in the NIT Header from the date of issue of letter of acceptance of the tender.
I/We also hereby agree to abide by the General Conditions of Contract-2022 corrected up- to- date and to carry out the work according to the Special Conditions of Contract and Indian Railways Unified Standard Specifications (Materials and Works) 2021 as corrected up-to-date, Unified Standard Schedule of Rates of North-Western Railway - 2021 as corrected up-to-date & C P W D DSR-2021 and Specification 2019 (for the present contract)
T.No.JU/Const.III/T-01-2025-26-MJ-BYPASS - Construction of major and minor bridges, earthwork, including and filling, blanketing, construction of new station building, other service buildings, platforms, PF shelters, circulating area. Road Under Bridges, Supply of track ballast laying and linking of new BG track including turnouts, SEJs, etc. Transportation of P way material and carrying out all other ancillary civil works and track works in connection with Marwar Bypass New Line Project (3.9 Km.) of North Western Railway.
T-01-2025-26-MJ-BYPASS~NWR
T-01-2025-26-MJ-BYPASS
Open
Works - General
18 Months
Jodhpur, Rajasthan
₹0
₹15.3 L
27 Dec 2025
28 Nov 2025
13 Dec 2025
265 items across 6 schedules · ₹36,17,03,739.82 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Preparation of foundation for Embankment by clearing, grubbing, stripping top soil (average 150 mm) and stacking beyond foundation area, thereafter ploughing and pulverizing 150 - 200 mm of top of soil with tractor trolley, mixing water to achieve OMC with water sprinkler or left for natural drying, as required, and compaction with vibratory roller of suitable capacity to achieve 98% MDD for laying first layer of soil for embankment construction. | 100 Sqm | 560.00 | 488.56 | 2,735.94 |
| Earthwork in filling in embankment, guide bunds, around buried type abutments, bridge gaps, trolley refuges, platforms etc. with contractor's own earth conforming to Soil Quality Class SQ1/SQ2/SQ3, after preparation of foundations as applicable, benching in existing banks wherever required, spreading in layers with motor grader, bringing the moisture content to OMC, mechanical compaction to specified density a n d dressing of bank to final profile as per RDSO Specifications: RDSO/2020/GE: IRS-0004 with latest correction slips. Note: 1) Foundation preparation, Benching including additional earthwork on account of this, wherever required, shall be paid extra under relevant schedule item for benching. 2) Payment for Earthwork under this item shall be made based on the cross section measurements calculated (i) with original ground profile of existing bank based on initial ground levels before doing benching and (ii) final profile of the bank worked out with final levels as per prevailing guidelines. | — | — | — | — | |
| 2 | Using Soil Class SQ2 | cum | 317361.00 | 227.72 | 7,22,69,446.92 |
| 3 | Mechanical manufacturing of blanketing material by using only hard and durable stone crushed in mechanical crusher to different gradations, wet mixing of the same in designed proportion in Pug mill or wet mix plant to have uniform gradation including all incidental transportation, laying over finished formation in uniform layer(s) with motor grader, compaction with suitable vibratory roller to specified density and finishing to correct profile, complete as per RDSO Specification No. RDSO/2020/GE: IRS-0004 with latest correction slips. Note: This item shall be used only when entire constituent of blanketing material is mechanically manufactured by crushing of hard and durable stone into desired gradation of designed proportion. | cum | 17992.00 | 1,728.03 | 3,10,90,715.76 |
| Turfing / planting, including all lead & lift and watering as required until properly rooted with. Note: Initially payment of only 40% will be made. Balance 60% will be paid after 3 months of maintenance period, only if the turfing is properly rooted on entire turfed area. | — | — | — | — | |
| 4 | Turfing with sods, 10cm thick and 20cm square closely laid. | 100 Sqm | 25.00 | 6,513.75 | 1,628.44 |
| P r o v i d i n g portable fencing along running track where work is to be done in close vicinity of track, maintaining during execution of work and removing after completion of the work as per direction of the Engineer. Fencing shall consist of self supporting steel angles of size 50mm x 50mm x 6mm, 1.5m long provided with hooks etc. and embedded in CC 1:2:4 block of size 0.23m x 0.23m x 0.23m placed at c/c distance of 2m along track. 12mm dia rods in three horizontal layers shall be tack welded with angle posts. Note : Released material will be property of the contractor after completion of work. Cost of cement required for CC blocks shall be paid separately. | — | — | — | — | |
| 5 | With provision of painting verticals & horizontals with red luminous paints / strips of 30cm each with a gap of 30 cm. | Metre | 100.00 | 136.03 | 13,603 |
| Earthwork in excavation by mechanical means (Hydraulic Excavator)/Manual Means for foundations and floors of the bridges, retaining walls etc. including setting out, dressing of sides, ramming of bottom, getting out the excavated material, back filling in layers with approved material and consolidation of the layers by ramming and watering etc. including all lift, disposal of surplus soil up to a lead of 300m, all types of shoring and strutting with all labour and material complete as per drawing and technical specification as directed by Engineer in charge. Note: This item will be used for excavation work in connection with other miscellaneous works also like side drains, foundation for OHE masts and other miscellaneous structures in connection with Gauge Conversion, Doubling, New lines. | — | — | — | — | |
| 6 | All kinds of soils | cum | 5636.00 | 210.9 | 11,88,632.4 |
| Providing and laying in position Plain cement concrete of specified Nominal M i x f o r miscellaneous works like side drains, foundation for OHE masts and other miscellaneous structures excluding the cost of Cement, centering and shuttering - All work up to plinth level : | — | — | — | — | |
| 7 | 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) | cum | 70.00 | 2,845.47 | 1,99,182.9 |
| 8 | 1:2:4 (1 cement : 2 coarse sand (zone- III) : 4 graded stone aggregate 20 mm nominal size) | cum | 372.00 | 2,936.59 | 10,92,411.48 |
| 9 | P r o v i d i n g and laying in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality in RCC raft foundation & Pile cap including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability complete as per specifications and direction of the Engineer in charge. Note: 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum | 1803.00 | 2,919.59 | 52,64,020.77 |
| P r o v i d i n g and laying in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality for the following Reinforced cement concrete structural elements up to height of 9.0 m from foundation top level, including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability complete as per specifications and direction of the Engineer in charge. Note: 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons for not using plasticiser at the stage of Mix Design and in that case deduction shall be made as per relevant item. | — | — | — | — | |
| 10 | Abutment & Pier | cum | 693.00 | 2,999.09 | 20,78,369.37 |
| 11 | Wing wall and Return wall | cum | 1083.00 | 2,999.09 | 32,48,014.47 |
| 12 | Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. | cum | 97.00 | 3,038.85 | 2,94,768.45 |
| 13 | Approach slab at formation level, Dirt wall/ ballast wall at formation level | cum | 60.00 | 2,959.34 | 1,77,560.4 |
| 14 | Providing and laying Plain Cement Concrete 1:3:6 with graded stone aggregate of 40mm nominal size, in foundation and floors, retaining walls of bridges including mechanical mixing, vibrating, pumping and bailing out water where ever required with all materials and labour complete but excluding the cost of cement and shuttering as per drawings and technical specifications as directed by Engineer. | cum | 191.00 | 2,988.17 | 5,70,740.47 |
| 15 | Providing and fixing Weep Holes in Abutments, Wing walls and Return walls etc., of new bridges with 110mm dia UPVC pipe Type A ISI marked with all contractor's men, material, transportation, all taxes as per specifications and as directed by Engineer-in-Charge. | Metre | 260.00 | 262.24 | 68,182.4 |
| 16 | Providing and casting machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix, mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants, (Cast in-Situ/Pre-cast) in bottom/top slab, side walls, toe wall and sumps haunch filling head walls, thrust bed or any other component using 20mm graded crushed stone aggregate and coarse sand of approved quality of RCC box of any size including finishing, Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability, complete as per drawings and technical specifications as directed by Engineer in charge. Note: 1. Payment for cement, reinforcement and shuttering shall be made extra under relevant item. 2. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum | 1394.00 | 3,211.55 | 44,76,900.7 |
| 17 | Providing and laying in position machine batched, machine mixed and machine vibrated Design Mix Cement Concrete, mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants, of specified grade (cast in-situ) using 20mm graded crushed stone aggregate and coarse sand of approved quality in Drop and curtain wall and alike structures below bed level, complete in all respect as per drawings and technical specifications to the satisfaction of Engineer-in-Charge. Note: Payment for cement, reinforcement and shuttering shall be made extra. | cum | 101.00 | 2,919.59 | 2,94,878.59 |
| 18 | Providing and applying two coats of coal tar or bitumen confirming to IS:3117- latest version on the top and sides of RCC box/slabs @ 1.70 kg/sqm after cleaning the surface with all labour and materials complete job as directed by the Engineer. | Sqm | 1655.00 | 178.84 | 2,95,980.2 |
| Centering and shuttering including strutting, propping etc. and removal of form for : | — | — | — | — | |
| 19 | All types of bridge sub-structures, e.g. pier, abutment, wing wall, retaining wall, RCC box type foundations, Abutment cap, Pier Cap, Inspection Platform & Pedestal over Pier cap, Fender wall, Diaphragm wall etc. up to 5m above ground level | Sqm | 5733.00 | 715.17 | 41,00,069.61 |
| 20 | All types of bridge super-structures, e.g. slabs, I-girders, T-girders, Box girders etc. up to 5m above ground level. | Sqm | 1528.00 | 927.65 | 14,17,449.2 |
| Supply and using Cement at Worksite | — | — | — | — | |
| 21 | Ordinary Portland Cement 43 grade approved brands/makes | MT | 2257.00 | 7,801.51 | 1,76,08,008.07 |
| 22 | Ordinary Portland Cement 53 grade of approved brands/makes | MT | 201.00 | 7,968.76 | 16,01,720.76 |
| 23 | Pozzolana Portland Cement approved brands/makes | MT | 177.00 | 7,294.44 | 12,91,115.88 |
| Supply of steel reinforcement of approved brands/makes for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. | — | — | — | — | |
| 24 | Thermo-Mechanically Treated bars of grade Fe-500D or more of approved brands/makes. | Kg | 641049.00 | 107.01 | 6,85,98,653.49 |
| 25 | Providing and launching in position machine batched, machine mixed and machine vibrated Cement Concrete of specified grade as per approved Design Mix (mixed in Mobile Concrete Batching/Mixing Plant at site or RMC from approved plants) using 20mm graded crushed stone aggregate and coarse sand of approved quality for the Precast Prestressed (Post-tensioned) Concrete Girder/Box Girders/Slabs in contactor's casting yard in the vicinity of worksite, including finishing, using Plasticiser in approved proportions (as per IS:9103), to modify workability without impairing strength and durability, complete as per drawings, specifications and direction of the E n g i n e e r. Note: 1. Payment for Shuttering, Cement, Reinforcement, HTS cables, Sheathing, Anchorage Cones, stressing of cables, grouting of the ducts and launching of girder/slab in position shall be made extra under relevant items. However, deduction shall be made in case of slab as per relevant item. 2. For pre-cast item, loading in transport vehicle in casting yard is included and shall not be paid extra. 3. Plasticiser shall invariably be used in approved proportion to increase workability with minimum possible quantity of cement for all grade of Design Mix Concrete unless it is specifically approved citing reasons at the stage of Mix Design and in that case deduction shall be made as per relevant item. | cum | 309.00 | 2,919.59 | 9,02,153.31 |
| 26 | Providing, fabricating & fixing in position to exact design profiles, H.T.S. cables of all classification made from Low Relaxation strands conforming to IS:14268- latest version in Prestressed (Post-tensioned) Concrete girders/slabs etc. including supplying, cutting, making into cables with necessary spacers, colour coding, protecting with water soluble oil at all time, anchoring of cables, supplying and placing spiral corrugated type galvanized metal steel ducts sheathing made up of Cold Rolled Cold Annealed (CRCA) mild steel conforming to IS:513 of required diameter/ thickness, vent pipe, placing, bending, routing, fixing, stressing & grouting of cable ducts with cement grout, Anchorage sets in required number with provision for future prestressing if any including all lead and lift with contractor's own materials, labour, equipments etc. complete as per drawings & specifications. Rate also includes covering anchorage pads with epoxy mortar of approved quality to avoid corrosion. Cement for grouting to be paid separately. Payment shall be made in terms of weight of HTS cables as per drawing. | MT | 15.00 | 2,01,861.72 | 30,27,925.8 |
| 27 | Extra for using HDPE sheathing in place of CRCA sheathing | Metre | 1286.00 | 179.28 | 2,30,554.08 |
| Launching in position, by any approved method, pre-fabricated Steel Girders, precast PSC girders/slabs, casted at casting bed developed at site, to correct alignment and level over the bed block / pedestal with all required arrangements, complete in all respect. | — | — | — | — | |
| 28 | PSC girders / slabs | MT | 1085.00 | 1,661.73 | 18,02,977.05 |
| 29 | Supplying fabricating and erecting welded and/or bolted and/or riveted steel work in built up sections, trusses and framed work, staging, racks, Height Gauge etc. for Steel Structures other than bridge girders, using RSJ, tees, angles and channels/flats, plates, gussets, round or square bars, cleats, bolts etc., with contractors own steel including cutting, bending, straightening, drilling, riveting, hoisting, fixing, erecting, welding, bolting etc., with Providing stiffeners wherever required as per approved drawing including applying a priming coat of a approved steel primer with all contractor's materials, labour, tools & plants, lead & lift including crossing of tracks if required etc., complete as per s p e c ifi c a t io n and as directed by Engineer-in-charge. Note: The payment shall be made on the theoretical weight of main components and gusset plates only. | MT | 30.00 | 1,29,631.69 | 38,88,950.7 |
| 30 | Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 35 kg each with voids filled with spalls complete as per drawing and Technical Specification. | cum | 40.00 | 1,975.73 | 79,029.2 |
| 31 | Providing and laying of filter media consisting of granular materials of GW, GP, SW groups as per IS:1498 (latest) in required profile behind boulder filling of abutments, wing walls / return walls etc. above bed level with all labour and material complete job as per drawing and technical specification of RDSO Guidelines. | cum | 510.00 | 2,577 | 13,14,270 |
| 32 | Painting the HFL mark and Danger level mark, year of HFL on bridge abutments and piers with ready mixed paint as per standard in two coats over one coat of primer with all materials, labour, tools, scaffolding, all lead and lift etc. including writing complete. | Each | 59.00 | 303.85 | 17,927.15 |
| 33 | Providing cast in situ bridge number plaques as per Railway drawing in cement concrete 1:2:4 mix using 20mm hard stone aggregate embedded in 30mm notch in Bridge parapet coping duly engraving the letter and figures and an arrow indicating the direction of flow and finishing the top exposed surface with cement mortar 1:3, painting letters and figures with two coats of black enamel paint on two coats of white background with all labour, tools, cement, paint etc. with all leads and lifts. | Each | 16.00 | 869.26 | 13,908.16 |
| 34 | Providing cast in-situ plaques for bridge foundations details of size 45cmx45cmx5cm in cement concrete 1:2:4 mix using 20mm hard stone aggregate embedded in 30mm deep notch over abutment & piers, engraving the letters & figures with CM 1:3 and finished smooth including painting letters and figures with 2 coats of black enamel and plaque with white enamel with all labour, tools, cement, paint, curing etc. as a complete job. | Each | 51.00 | 1,308.64 | 66,740.64 |
| 35 | Providing Boulder Backing behind wing wall, return wall, retaining wall with hand packed boulders & cobbles with smaller size boulders toward the back including all lead, lift, labour & other incidental charges as complete work in all respect. Payment for boulder/cobbles will be done extra. | cum | 505.00 | 411.68 | 2,07,898.4 |
| 36 | Dewatering of natural or accumulated water from any location. Payment to be done for Horse power of pump multiplied by pumping hours. | HP Hour | 170.00 | 44.73 | 7,604.1 |
| Dismantling and removing rail of all section & length from track, laid on any type & density of sleeper by removing fish plates, fastenings & fish bolts and other materials including stacking all released materials within an average distance of 500 metres as directed by Engineer in-charge. Note: 1.Cutting of rails shall be paid separately. 2.Work to be done under traffic block. | — | — | — | — | |
| 37 | For Casual/Scattered Rail Renewal work | RM | 100.00 | 38 | 3,800 |
| Through Sleeper Renewal (TSR) with PSC sleepers involving removal existing sleepers of any type along with fittings from track, insertion of PSC sleepers lying along the cess / formation / slope / toe within 5 metres height with all fittings to specified spacing, gauge and squareness, one round of through packing to make track fit for 20 kmph speed, dressing of ballast to standard profile, all in accordance with the latest provisions of IRPWM and stacking of all released material neatly at specified places within an average lead of 100 m as directed by Engineer in-charge. | — | — | — | — | |
| 38 | For PSC wider base sleepers - For location of work not involving deep screening | Each | 100.00 | 383.31 | 38,331 |
| 39 | Removing seized ERC from SGCI inserts of existing track by using suitable approved chemicals and re-fixing after greasing of insert eye and ERC with Contractor's grease of specified quality as per provisions of IRPWM, as directed by Engineer in-charge. Note: 1.List of Seized ERC along with location shall be prepared after inspection of SSE/P.Way and marked prior to execution of this item. 2. Due care shall be taken to avoid any damage to the sleeper 3.A penalty of 50% of the basic cost of new sleeper in nearest sleeper factory shall be levied on each, if SGCI insert is broken or sleeper gets cracked in the process. | ERC | 100.00 | 53.1 | 5,310 |
| 40 | Lubrication of gauge face of rail on curves, cross overs, points & crossings, turn-in curves and at locations as required with contractor's grease graphite grade "O" IS 408 and as directed. | RM | 1500.00 | 4.65 | 6,975 |
| Drilling of hole of different diameter and chamfering, in rail of any section and any UTS manually only in emergencies with contractor's labours, tools & plants, consumables etc. | — | — | — | — | |
| 41 | Hole of dia. 26.5mm and above | Each | 1350.00 | 255.59 | 3,45,046.5 |
| 42 | Hole of dia. below 26.5mm | Each | 420.00 | 167.38 | 70,299.6 |
| Gas cutting of rail of various sections with contractor's tools & plants, as directed by engineer in-charge : | — | — | — | — | |
| 43 | Rail section of 52Kg and above | Each | 100.00 | 127.67 | 12,767 |
| Assembling and Laying of Improved Switch Expansion Joint (SEJ) on PSC sleepers of any rail section as per RDSO drawing including leading of SEJ rails, sleepers, fittings for a free lead of 250 metres, cutting of rails, drilling of holes as required and lubrication of SEJ, gauging, aligning rails, providing temporary connection with adequate welding gap with adjoining rails, providing reference posts at SEJ, first through packing of SEJ portion to make track geometry fit for 30 kmph speed and making ballast profile as per IRPWM. Note: (1) Rail cutting and hole drilling shall be paid separately.(2) One set comprise complete SEJ on both rails at SEJ. | — | — | — | — | |
| 44 | Under Conditions not requiring Traffic Block | Set | 2.00 | 7,182.05 | 14,364.1 |
| 45 | Under Traffic Block Conditions | Set | 2.00 | 7,900.25 | 15,800.5 |
| 46 | Dismantling & removing existing SEJ (Switch Expansion Joint) assembly during line block and its replacement with plain track as of adjoining section with all fittings including rail cutting and drilling of holes and renewal of special sleepers with PSC Sleepers as directed and aligning rails, providing fishplates and bolts/ temporary connection with adequate welding gap with adjoining rail and ensuring proper track geometry for 30 kmph speed. The release material shall be stacked as directed by Engineer in charge. | Set | 2.00 | 9,336.66 | 18,673.32 |
| Assembling complete BG Turnout on s t a g i n g , clear of infringements, to correct gauge and alignment as per standard drawings with all types of rail sections over PSC sleepers at specified locations, duly leading rails, special sleepers, switches, crossings with a maximum lead of 500m, all lift & crossing of track as required and testing points with S&T staff for throw of switch etc. at station yard after levelling surface complete including lubrication of all fastenings, complete in all respect. Note: 1.Rail cutting and Drilling shall be paid separately 2. Required P.Way fittings/fastenings shall be supplied at the SSE/P.Way stores. | — | — | — | — | |
| 47 | 1 in 12 Turnout | Set | 2.00 | 46,110.68 | 92,221.36 |
| Laying and linking of turnouts of all t y p e s including diamond crossings & Derailing switches with 52Kg / 60Kg rail section on PSC sleepers on prepared ballast bed for New lines or during total closure of section at indicated location as per standard drawing, duly leading sleepers, rails, switches, crossings, fastenings including rail cutting, drilling, fixing of all components, fittings with housing of tongue rails as per requirement of signaling, preparing ballast bed, filling and spreading of ballast as required, linking of turnout with track, attending track parameters including lifting, providing one round of packing to make track fit for 20 kmph speed including lubrication of fittings/fastenings, complete as directed by Engineer in-charge. | — | — | — | — | |
| 48 | 1 in 12 Turnouts | Set | 2.00 | 52,614.73 | 1,05,229.46 |
| Laying and linking all types of turnouts, diamond crossings and Derailing switches with 52Kg / 60Kg rail section on PSC sleepers on ballast bed, prepared after dismantling & removal of existing turnout/normal line during TTR/yard remodeling under traffic block, as per standard drawing, duly leading sleepers, rails, switches, crossings, fastenings including rail cutting, drilling, fixing of all components, fittings with housing of tongue rails as per requirement of signaling, preparing ballast bed, filling and spreading of ballast as required, linking of turnout with track, attending track parameters including lifting, providing one round of packing to make track fit for 20 kmph speed including lubrication of fittings/fastening, complete as directed by Engineer in- charge. Note: Payment for dismantling & removal of existing turnout/normal line, transportation/stacking of released material and preparing of ballast bed is not included in this item and shall be paid under relevant item. | — | — | — | — | |
| 49 | 1 in 12 Turnouts | Set | 2.00 | 57,876.21 | 1,15,752.42 |
| 50 | Lifting and packing for regrading the existing PSC sleeper track to required height / level in stages not exceeding 75mm or part thereof at a time, providing permissible ramp for the track, insertion of moorum / sand / stone ballast uniformly under the existing track and placing the same to safe approved gradient, gauge, cushion including levelling and one round of through packing to allow train movement at restricted speed of 30 kmph for a specified length with all leads & lifts and fixing, marking, painting rail level pegs at every 30m interval. Note: Lifting of track shall be done in stages as per procedure prescribed in latest edition of IRPWM to get the proposed final level as per approved working profile, as directed by Engineer in-charge. | TRM | 100.00 | 191.51 | 19,151 |
| 51 | Extra for additional lift over 75mm for every 50mm lift or part thereof up to 275mm for item nos. 083010 for each TRM. | TRM | 100.00 | 29.7 | 2,970 |
| 52 | Boxing and profiling of ballast as per procedure prescribed in latest edition of IRPWM including cess dressing on both sides of track. The work will include removing excess ballast from track and putting the same in crib and shoulder by leading to a maximum of 50m including crossing of track, deweeding on ballast section etc and as directed by Engineer-In charge. | TRM | 200.00 | 28.14 | 5,628 |
| Manufacturing, supply and stacking of machine crushed Track Ballast conforming to RDSO Specification (IRS- GE-1) with latest correction slips at Railway depot or nominated location. Note: Distance of nearest quarry mentioned in each sub-item is only for the purpose of selecting the items for preparation of estimates/tender schedule, based on the minimum distance between nearest quarry and centre of supply points and will not affect the selection of quarry during physical supply in any way till prescribed specification is met fully. | — | — | — | — | |
| 53 | When distance of nearest quarry is more than 20 km and up to 30 km | cum | 13000.00 | 1,073.76 | 1,39,58,880 |
| 25mm gap 'in-situ' welding during traffic block and finishing of weld to m e e t the prescribed tolerances and pass all stipulated tests with all required labour, materials, consumables, tools, equipments etc. to complete the work in all respect as per IR's "Manual for Fusion Welding of Rails by Alumino - Thermic Process" with latest correction slips, including marking of welded joint, painting weld collar with anticorrosive paint, restoration of track near weld joint to original position and fixing of joggled fish plate at new weld, to be removed after passing of weld in USFD test as directed by Engineer in charge. Note: 1. Welding shall be carried out only by trained welder having valid competency certificate using RDSO approved Alumino Thermit Welding Portions, 3 piece prefabricated mould (ZIRCON WASHED) manually pressed, Single shot crucible fitted with auto tapping thimble a n d Compressed Air Petrol/LPG preheating technique as per RDSO Specification No IRST/19-2020 with latest amendment. 2. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing. 3. Only required nos. of Joggled fish plates shall be supplied by Railway at nearest P. Way Stores and the same shall be returned at nearest P. Way Store or at other location as per direction of Engineer-in-Charge after release from track. All other items required shall be supplied by the Contractor. | — | — | — | — | |
| 54 | For 60 Kg/60EI - R260 grade Rail | Each | 90.00 | 7,444.59 | 6,70,013.1 |
| 55 | For 52 Kg - 90/72 UTS Rail | Each | 10.00 | 7,297.42 | 72,974.2 |
| 56 | Dismantling of existing LWR/SWR track of any structure, removing rails, sleepers, fish plates, cutting of rails, segregation and stacking of released Rails, Sleepers and fitting at nominated location in countable manner within a free lead of 500m, levelling of ballast to correct profile for laying new track over it, all as per direction of Engineer-in- Charge. | TRM | 100.00 | 189.77 | 18,977 |
| Shifting & pairing of rails / panels unloaded alongside existing running track to adjoining formation of a new line including crossing of one track, duly lifting & pushing rail / panel without damaging it and taking all necessary precautions, so as not to infringe the running track, as directed by Engineer in-charge. Note: The rail barricading, if disturbed during working, should be restored to its original condition by the agency including re-fixing & concreting as required. | — | — | — | — | |
| 57 | Rail length up to 13m - Under Conditions not requiring Traffic Block | RM | 8000.00 | 17.37 | 1,38,960 |
| Providing Centre Line / Rail Level, reference Pegs on formation at an interval of 30 metres on one side or at centre of proposed / existing track, as directed by engineer in-charge for linking of new track / CTR / Deep Screening / Lifting / Lowering works, duly embedding in formation including marking with contractor's paint. Note: (1) Rails/tie bar of suitable size bar shall be supplied by the Railways from nearest Stores Depot. In case of hard wood peg, the hard wood will be supplied by the contractor. (2) Excavation and concrete work, if required, will be paid separately. | — | — | — | — | |
| 58 | With contractor's hard wood pegs of 50 mm dia and 60 cm long | Each | 80.00 | 133.12 | 10,649.6 |
| Linking of BG track (except at LC, Bridges and SEJs) with any type of rail section and sleeper of specified density, o n ballast bed spread and compacted with suitable roller, over prepared f o r m a t i o n i n c l u d i n g leading free rails/welded panels available along the alignment on to formation, leading and spreading all fittings and fastenings, spreading of sleepers at specified spacing, squaring, placing of rails over sleepers and fixing rails to sleepers with all types of fittings and fastenings to correct gauge & alignment, lubrication of fittings and fastenings with contractor's grease as per IRPWM standards with contractors labour, tools, consumables, with all lead, lifts etc. complete and raising, levelling and initial packing of track to make it fit for 30 kmph and meet other prerequisites prescribed in Indian Railway Track Machine Manual for deployment of Tamping Machine. Note: 1.Rail cutting and Hole drilling shall be paid separately. 2.Spreading of ballast and compaction shall be paid separately under relevant item. | — | — | — | — | |
| 59 | For sleeper density of 1660 sleepers per km | TRM | 4000.00 | 299.09 | 11,96,360 |
| 60 | For sleeper density of 1540 sleepers per km | TRM | 500.00 | 277.89 | 1,38,945 |
| 61 | Carrying out cut & connection to the existing PSC sleeper track under line block of any rail section and sleeper density to connect the same to newly linked track which is laid by the side, duly carrying out cutting of rails, insertion of additional PSC sleepers, if required, providing fish plated joints including drilling of holes, slewing required length of both tracks to prescribed alignment, adjusting sleeper spacing, providing continuity to track, spreading of ballast to provide cushion, shoulder ballast to the track stretch, giving one round of initial packing to make track fit for 20 kmph speed and boxing of ballast to profile as directed by Engineer in charge. | Each | 2.00 | 67,711.42 | 1,35,422.84 |
| Shifting / Slewing the existing or newly assembled track of any rail section with any type of sleepers and any density under line block to correct locations & alignment and attending to one round kutcha packing to run safely at 20KMPH speed with all contractors tools and consumables complete and as directed by Engineer in-charge. | — | — | — | — | |
| 62 | Maximum Shifting / Slewing up to 1 metre | TRM | 100.00 | 221.24 | 22,124 |
| 63 | Maximum Shifting / Slewing for more than 1 metre & up to 2 metres | TRM | 100.00 | 265.83 | 26,583 |
| Working of the Railway Push Trolley by arranging one Head trollyman along with 3 trollymen as per Railway's rules and stipulations for conducting inspections by Railway officials and as directed by Engineer in-charge. Note: 1) Labourers supplied should be of skilled in case of head trollyman and semiskilled in case of trollymen and capable of pushing trolley in all gradients, and levels duly observing all safety precautions as per the manual. 2) The labour engaged should be physically fit for strenuous work, literate and meeting prescribed medical category. | — | — | — | — | |
| 64 | For Full day (8 hrs ) | Each | 150.00 | 3,550.89 | 5,32,633.5 |
| Providing Caution Watchman at a location where caution order is imposed and ensuring to be on continuous vigil and exhibit necessary hand signals to the trains for their passage over caution s p o t . Note: 1) Prescribed protection equipment shall be supplied by Railways and the same shall be returned after work is over. 2) If Contractor fails to post watchman at any time during one day, penalty at double the accepted rates will be levied and 3) The watchman nominated by the contractor will be screened for suitability as per Railway norms. | — | — | — | — | |
| 65 | For one shift ( 12 Hrs) | Each | 10.00 | 1,281.08 | 12,810.8 |
| 66 | For Half Shift (4 hours) | Each | 20.00 | 431.48 | 8,629.6 |
| De-stressing of LWR/CWR track of any density under traffic line block with contractor's labours, tools, equipments and consumables inclusive of all lead & lift. Activities include cutting of LWR/CWR into convenient panels of specified length, removal of ERCs, liners, greasing of ERCs and liner contact area, lifting rails and keeping them on rollers provided at every 15 sleepers, working out elongation of rail ends depending on prevailing site conditions, pulling rails with the help of Hydraulic Tensor to achieve the desired elongation, cutting rails, as required, removing rollers and placing rail in position, re-fixing ERCs & liners and adjustment of gap at SEJs : Note: (1) Welding of rail joints will be paid separately. (2) Rail cutting and Hole drilling shall be paid separately. (3) Opening and closing of LC if required will be paid separately. (4) As per procedure prescribed in latest edition of IRPWM & CE's Circulars for destressing of LWR/CWR, if any. | — | — | — | — | |
| 67 | With Contractor's Hydraulic Rail tensor | TRM | 1000.00 | 47.38 | 47,380 |
| 68 | Without Rail tensor | TRM | 3000.00 | 42.59 | 1,27,770 |
| Fixing Joggled Fish Plates with bolt / clamp (supplied by Railway from nearest SSE Store) in running track conditions at welds on rail, as directed by engineer in-charge (drilling of holes in rail, if required, shall be paid separately). | — | — | — | — | |
| 69 | With 2 bolts | Set | 10.00 | 117.37 | 1,173.7 |
| 70 | With Clamps | Set | 24.00 | 166.97 | 4,007.28 |
| 71 | Replacing existing glued joint rail with cut rails or with glued joint rail or insertion of glued joint by cutting existing track under traffic condition by cutting rails, refixing with all rail sleeper fastenings and providing required gaps for carrying out welding as an alternative to drilling holes or joining rails with fish plates duly drilling holes as required including stacking of released material and as directed by engineer in-charge. N o t e : (1) Drilling holes & rail cutting will be paid separately. (2) Transportation of materials to the site of work from supply points, if more than 250m, shall be paid separately. | Each | 10.00 | 1,929.81 | 19,298.1 |
| Fixing of Wooden Distance Block of size 1.0m x 0.3m x 0.15m between track and platform wall. | — | — | — | — | |
| 72 | With Contractor's hard wood block. | Each | 50.00 | 1,426.71 | 71,335.5 |
| Anti-corrosive painting of rail outside track on rail bottom, web, foot and fishing plane with two coats of thickness of 100 microns each by bituminous black paint confirms to IS- 9862 of reputed make including surface preparation, as a complete job as per procedure prescribed in latest edition of IRPWM. | — | — | — | — | |
| 73 | For 60 Kg Rails | RM | 3000.00 | 57.49 | 1,72,470 |
| 74 | Carrying out various miscellaneous works, for proper upkeep of crew rest van / rest room as directed by machine i n - c h a r g e of Track Machines by providing a team of 2 labours for 12 hours shift, broadly mentioned hereunder: (1) Bringing water from nearby source and cleaning machine with water jet or any suitable means; (2) Fuelling machine duly bringing diesel / hydraulic oil from the stacked drums; (3) Bringing water to staff rest van or staff rest room, cleaning rest van / rest room, cooking food for Track Machine staff or bringing food from outside (cost of food shall be borne by the staff concerned).; (4) Guarding & watching machines, spare parts, oils, grease etc. during day and night time at all locations, wherever necessary, as instructed by the machine in-charge; (5) In case, contractor provides less no. of Labour/Mate, payment will be deducted for each such person @ 75% of the accepted item rate. | Shift | 8.00 | 1,493.14 | 11,945.12 |
| Quick cutting with abrasive rail cutter of all types of rail sections including wear resistant, head hardened rails up to 110 UTS, with contractors tools & plants, equipment, consumable with all lead & lift etc. complete as directed by Engineer in-charge. Abrasive Rail Cutter will be as per RDSO Specification No. TM/SM/1 (Rev. 01 of 2012) with latest status of RDSO; Rail Cutting Wheel Abrasive Disc will be as per RDSO Specification No.TM/SM/2 (Rev. 01 of 2020) | — | — | — | — | |
| 75 | 60 Kg - 110/90 UTS - Outside Track | Each | 60.00 | 219.76 | 13,185.6 |
| 76 | 52 Kg - 90 UTS - Outside Track | Each | 1400.00 | 197.11 | 2,75,954 |
| 77 | 60 Kg - 110/90 UTS - On Running Line | Each | 20.00 | 280.99 | 5,619.8 |
| 78 | 52 Kg - 90 UTS- On Running Line | Each | 20.00 | 228.94 | 4,578.8 |
| Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine including chamfering with appropriate chamfering tools in all types of rail section with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in-charge. Rail Drilling Machine will be as per RDSO Specification No. TM/SM/3, dated 24.04.1991. | — | — | — | — | |
| 79 | Outside Track | Each | 40.00 | 50.01 | 2,000.4 |
| 80 | On Running Line | Each | 1000.00 | 67.23 | 67,230 |
| Loading of rails of any section and length up to 1 3 metres in Wagons / Truck / trailer including lead up to 50 metres and lift up to 5 metres. | — | — | — | — | |
| 81 | In Wagon where mechanical handling is possible and traffic block is not required or in Truck/trailer. | MT | 850.00 | 124.5 | 1,05,825 |
| Loading of tongue rail, stock rail, switch assembly and crossings of any section and length, SEJ, Glued joint etc. with / without P.Way fittings and fastenings, in Wagon / Truck / trailer including lead up to 250 metre and lift up to 5 metre. | — | — | — | — | |
| 82 | In Wagon where mechanical handling is possible and traffic block is not required or in Truck/trailer. | MT | 40.00 | 123.98 | 4,959.2 |
| Unloading of rails of any section and length up to 13 metre, in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/trailer including lead up to 50 metre, lift up to 5 metre and stacking in prescribed manner. | — | — | — | — | |
| 83 | From Wagon where mechanical handling is possible and traffic block is not required or in Truck / trailer. | MT | 850.00 | 92.69 | 78,786.5 |
| Unloading of all type of rails of length 130 metre and beyond from end unloading rake and keep the panels in head-up position at specified distance from centre of track clear from any infringement.. Note: Contractor has to keep Oxygen and Acetylene gas with cutter as standby during the period of work. | — | — | — | — | |
| 84 | During period of traffic block | MT | 50.00 | 31.32 | 1,566 |
| 85 | Not involving traffic block | MT | 500.00 | 26.2 | 13,100 |
| Loading, leading and unloading of all types of P.Way fittings and all other miscellaneous material except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. | — | — | — | — | |
| 86 | Lead up to 5 Km | MT | 60.00 | 182.79 | 10,967.4 |
| 87 | Lead beyond 5 Km and up to 10 km | MT | 60.00 | 226.82 | 13,609.2 |
| 88 | Lead beyond 10 Km and up to 20 km | MT | 60.00 | 286.21 | 17,172.6 |
| 89 | Lead beyond 20 Km and up to 30 km | MT | 60.00 | 357.88 | 21,472.8 |
| 90 | Lead beyond 30 Km and up to 50 km | MT | 60.00 | 456.55 | 27,393 |
| 91 | Lead beyond 50 Km and up to 100 Km | MT | 60.00 | 669.61 | 40,176.6 |
| 92 | Lead beyond 100 Km and up to 150 Km | MT | 60.00 | 990.6 | 59,436 |
| 93 | Extra for every Km per MT beyond 150 Km over item no. 172047 | MT-Km | 3000.00 | 3.29 | 9,870 |
| Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. | — | — | — | — | |
| 94 | Lead up to 5 Km | MT | 100.00 | 59.47 | 5,947 |
| 95 | Lead beyond 5 Km and up to 10 km | MT | 100.00 | 103.5 | 10,350 |
| 96 | Lead beyond 10 Km and up to 20 km | MT | 100.00 | 162.89 | 16,289 |
| 97 | Lead beyond 20 Km and up to 30 km | MT | 100.00 | 234.56 | 23,456 |
| 98 | Lead beyond 30 Km and up to 50 km | MT | 200.00 | 333.24 | 66,648 |
| 99 | Lead beyond 50 Km and up to 100 Km | MT | 700.00 | 546.3 | 3,82,410 |
| 100 | Lead beyond 100 Km and up to 150 Km | MT | 1600.00 | 867.28 | 13,87,648 |
| 101 | Extra for every Km per MT beyond 150 Km over item no. 172057 | MT-Km | 240000.00 | 3.29 | 7,89,600 |
| Unloading of 52kg / 60kg PSC line and special sleepers up to 2.75 metre length in Depot / Station / Mid-section between stations in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane or any other means including crossing of one track and lead up to 250 metre & lift up to 5 metre with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 102 | From Truck / Trailer | MT | 2400.00 | 91.41 | 2,19,384 |
| Unloading of 52kg / 60kg PSC special sleepers beyond 2.75 metre length in Depot / Station / Mid-section between stations in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane or any other means including crossing of one track and lead up to 50 metre & lift up to 5 metre with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 103 | From Truck / Trailer | MT | 275.00 | 94.08 | 25,872 |
| Collection, segregation and stacking of various scattered P.Way materials at nominated stacking location with serviceable and un-serviceable ones separately within a lead up to 500 metre and lift up to 5 metre including crossing of track(s) wherever necessary as directed by Engineer-in-Charge. | — | — | — | — | |
| 104 | Rails, switches, crossings, SEJ, Glued Joints, Check Rails etc. | MT | 20.00 | 392.28 | 7,845.6 |
| 105 | P.Way fittings of all types and other similar loose items | MT | 25.00 | 414.33 | 10,358.25 |
| Manufacturing, fabricating and supplying retro-reflective Engineering Indicator boards, made of 2mm thick aluminium sheet or 3mm thick aluminium composite sheet, face to be fully covered with high intensity encapsulated type heat activated retro- reflective sheeting conforming to type- IV of ASTM-D4956-01 in yellow & black or other colour combination including subject matter, message, symbols, borders etc. as approved by Engineer In-charge or as per IRPWM guidelines, pasted on substrate by an adhesive backing which shall be activated by applying heat and pressure conforming to class-2 of ASTM-D-4956-01 and fixing the same with suitable sized aluminium alloy rivets @ 20 cm c/c to back-support frame of M.S. angle iron of size 25mm x25mm x 3mmprovided all along the edges of board with theft resistant measures back side of board shall be with non-peelable weatherproof paint, consisting of one coat of zinc chromate primer and two coats of epoxy paint. Vertical post shall have black & white anti-corrosive paint or powder coating complete, as directed. | — | — | — | — | |
| 106 | Caution Indicator Board of size 1400mmx400mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each | 8.00 | 6,988.14 | 55,905.12 |
| 107 | Speed Indicator Board of equilateral triangular shape having each side of 1000mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each | 8.00 | 6,008.27 | 48,066.16 |
| 108 | Termination Indicator Board of Circular shape having diameter of 1000mm with back support frame welded to vertical post of MS angle of size 50mmx50mmx6mm of 3950 mm long | Each | 8.00 | 8,543.06 | 68,344.48 |
| 109 | Manufacturing, supplying and fixing Curve Indicator / Point Indicator / SEJ Boards to be provided at various locations on formation, made out of MS sheet 2mm thick of size 450mm x 300mm duly fixed with MS frame of 25mm x 25mm x 3mm angle welded to 50mm x 50mm x 3mm MS angle, 1000mm long post split and bent 100mm at bottom end with all lead & lift as per specification and including painting of details with enamel paint, as directed by Engineer in-charge (Earthwork & concreting will be paid separately) | Each | 20.00 | 1,137.1 | 22,742 |
| Schedule total | ₹25,09,90,158.37 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .