| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹26.1 LAccepted-AOC | ₹26.1 L | L1 | Accepted-AOC AOC |
| 2 | Rejected-Technical | - | - | Rejected-Technical Second Lowest |
| 3 | Rejected-Technical | - | - | Rejected-Technical Third Lowest |
| 4 | Rejected-Technical | - | - | Rejected-Technical Fourth Lowest |
Tender Value
₹30 L
EMD Value
₹60,000
Closing Date
13 Nov 2017, 12:00 pmClosed
Executive Engineer
Office of the Executive Engineer Construction Division Uttarakhand Peyjal Nigam Karanprayag Chamoli
Construction of Talaur Water Supply Scheme of Block Dewal
2017_MDPEY_7533_1
LetterNo3692/Lekha4/137 Dated 07.10.2017
Open Tender
Civil Works
Item Rate
270 days
Talaur Block Dewal
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,360
Executive Engineer CD UKPJN
₹60,000
Karanprayag
16 Sept 2025
13 Oct 2017
18 Nov 2017
16 Oct 2017
13 Nov 2017
31 Oct 2017
30 Oct 2017
Amount
Supply, Carting, laying, jointing, fixing, testing & commissioning of following sizes of G.I. pipe as per latest IS : 1239 codes specification (Class medium) with specials & fittings in trenches underground including cutting, threading etc. complete in all respect or as per direction of Engineer in charge.
Excavation of earth for Pipe Line trenches of Supply Main in following strata requiring the use of special T&P such as Pick Axes, Sabbals etc. or by blasting or by crow bars with a lift up to 1.5 m and lead up to 30 m including refilling, watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth up to a distance of 60 m from the trenches including supply of all materials, labour, T&P etc. complete. Assuming that 90% Pipeline is laid in trenches & also it is estimated that 75% trenches will be in soil mixed with shingle, bazri, boulder and rest of 25% will be in medium rock.
Soil mixed with single boulder with bazri
Medium Rock
Supply, cartage & fixing of wheel valve of following dia. including supply of all necessary T&P like flanges, nut bolts, rubber gaskets, etc. complete as per latest IS speciation or as per satisfaction & approval of Engineer in Charge.
Supply, cartage & fixing of Air valve of following dia. including supply of all necessary T&P like flanges, nut bolts, rubber gaskets, etc. complete as per latest IS speciation or as per satisfaction & approval of Engineer in Charge.
Design, drawing & construction of wheel valve, complete in all respects, as per directions of Engineer in charge including supply of material, labour, T&P and fixing of required size M.H. Cover required for proper completion of work.(Size-.60x.60 M)
Design, drawing & construction of Air valve, complete in all respects, as per directions of Engineer in charge including supply of material, labour, T&P and fixing of required size M.H. Cover required for proper completion of work.(Size-.60x.60 M)
Supply,Cartage of all labour,material & T&P and construction of PTSP.
RCC CWR:-Design, testing bearing capacity of soil and construction of R.C.C. (1:1.5:3) semi sunk Clear Water Reservoir of following capacities in K.L. including supply of necessary scaffolding, shuttering and other accessories along with supply and fixing of inlet and outlet pipes of size equal to sizes of inlet and outlet pipe line, making bye pass arrangement, fixing of overflow pipe in outlet pipe/distribution system, fixing of lightening conductor & M.S. Manhole of size as per norms, supply and fixing of M.S. Steel Ladder outside and inside the tank, and colour washing of approved class snowcem and along with carting of all materials including supply of all materials, labour, T&P etc. complete as per latest IS specification or as per satisfaction & approval of Engineer in Charge.
PROTECTION WORK:-Construction of protection works including necessary Earth Work for Site Development, Service Reservoir etc. as per site conditions wherever necessary as follows :-
Random Rubble stone masonry in 1:6 cement and course sand mortar including supply of all materials, labour, T&P etc. complete.
Random Rubble stone masonry laid dry including supply of all materials, labour, T&P etc. complete.
Supply,cartage of all labour,material & T&P and construction of source including fixing of French Well and all other appurtenance works required for proper completion of work.
Supply,cartage of all labour,material & T&P and construction of RCC cross Wall.
Supply,cartage of all labour,material & T&P and construction/Fixing of Chlorinator Bucket over CWR.
M/S RAJENDRA SINGH CONT.
M/S CHAND KUNWAR SINGH CONTRACTOR
Manvendra Joshi
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_9892.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .