| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.1 LAccepted-Finance | L1 | Accepted-Finance L1 | |
| 2 | L2₹5.1 L+₹2,546.32 (0.50%)Rejected-Finance | L2 | Rejected-Finance L2 | |
| 3 | L3₹5.1 L+₹7,638.97 (1.51%)Rejected-Finance 659 MAHARAJ NAGAR LAKHIMPUR KHERI KHERI LAKHIMPUR KHERI UTTAR PRADESH 262701 | KHERI | UTTAR PRADESH | 262701 | L3 | Rejected-Finance L3 |
Tender Value
₹5.1 L
EMD Value
₹43,158
Closing Date
18 May 2026, 11:00 amClosed
EXECUTIVE OFFICER
NAGAR PANCHAYAT KHERI
Pump no. 02 par tin shed ka nirman karya
2026_DOLBU_1141848_2
179/NPKHERI/2026-27 DATE 23.04.2026
Open Tender
Civil Works
Percentage
90 days
KHERI TOWN
Please refer Tender documents.
2 documents required · 2 mandatory
₹885
EXECUTIVE OFFICER
₹43,158
8 Jun 2026
27 Apr 2026
18 May 2026
27 Apr 2026
18 May 2026
27 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation soil (Loam clay or sand ) including lift upto 1.5 metre (5fts) and lead upto 30 Mtr ( 100fts) & including filling watering and ramming of excavated earth into the tremches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of suplus earth as directed Engineer in charge up to distance of 30m (100fts) from the foundation trenches. as per .DAR 2.8.1 | - | Cum | 155 | - |
| 2 | Providing & Laying cement concreet 1:6:12 40mm gauge brick ballast etc. As per SI No 273 | 2.2 | Cum | 4,520 | ₹9,944 |
| 3 | Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (up to any pitch in horizontal/ vertical or curved surfaces), excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required.0.63 mm thick with zinc coating not less than 275 gm/m² as per DAR No 12.1.3 | 90 | sqm | 791 | ₹71,190 |
| 4 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding andbolted with special shaped washers etc. complete. As per DAR 10.25.2 | 0.88 | Kg | 105 | ₹92.4 |
| 5 | 12mm thick plaster with cement approved C-sand in 1:4 including supply of all materials labour and T&P etc. required for proper completion of the work. (As per SI No 02 DsR 13.4.1 | - | Sqm | 192 | - |
| 6 | P/A Cement based wall putty. As per DSR 13.80 | - | sqm | 80 | - |
| 7 | Painting or vanishing on iron works in small areas or new wood work with one coat of ready mixed priming paints & one coat of approved superior quality ready mixed paint of clear synthetic vamish including supply of all materials, labour and T&P etc.As per S I No 641+642 | 0.47 | Sqm | 93 | ₹43.9 |
| 8 | Distempering (Two coat with oil bound distemper of approved brand and manufacture and of required shade on undecorated wall surface to give an even shade over & including a priming coat with cement primer of approved brand and manufacture such as Berger, J & N Shalimar. Asian paints after thoroughly brushing the surface free from mortar droppings and other foreign matter and also including preparing the surface even with plaster of paris or approved synthetic material and sand papered smooth including cost of all materials. (upto floor two level S I No 649+650 | - | sqm | 125 | - |
| 9 | Reinforced cement concrete work excluding the cost of centering, shuttering, finishing and reinforcement, with l:1.5:3 (l cement : 1.5 coarse sand(zone-Ill) : 3 graded stone aggegate 20 mm nominal size as per DAR (5.2.2) | 0.8 | Cum | 8,825 | ₹7,060 |
| 10 | Miled steel or iron in plain work such as reinforced concrete or reinforced brick work (When not wrougt to include in over all rates) wrought to required shape as mecessary including bending for proper completion of the work and including supply of steel its wastage bend hooks and authorised overlapping shall be measured upto floor two level. | 0.48 | Kg | 64.5 | ₹30.96 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.42 MB
BOQ_2132507.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .