Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.4 CrAccepted-AOC | ₹1.4 Cr | 1 | Accepted-AOC Less than estimate |
| 2 | 2₹1.4 CrRejected-AOC THIRUCHIRAPPALLI THIRUCHIRAPPALLI TAMIL NADU | ARIYALUR | TAMIL NADU | 608901 | ₹1.4 Cr | 2 | Rejected-AOC Above estimate |
| Sl No | Description | Qty | Unit | M RAMESH L2 | ARUN AVINASH MARIYASOOSAI L1 |
|---|---|---|---|---|---|
| 1.00 | Providing and Laying, Spreading and compacting graded stone aggregates to Wet Mix Macadam specification including premixing the materials with waterat OMC in mechnanical mix plant carriage of mixed material by tipper to site laying inuniform layers with paver sin Sub Base/Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5 | 188 | m3 | 2,700 ₹5.1 L | 2,665 ₹5.0 L |
| 2.00 | Providing and laying Prime Coat over WBM/ WMM Surface using 7Kg of Emulsion Bitumen (SSI) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5 | 1,873 | m2 | 90 ₹1.7 L | 84.5 ₹1.6 L |
| 3.00 | Providing and laying Tack Coat over WBM/ WMM Surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 | 1,873 | m2 | 25 ₹46,825 | 19 ₹35,587 |
| 4.00 | Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 | 10,118 | m2 | 35 ₹3.5 L | 28 ₹2.8 L |
| 5.00 | Providing and laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5 | 600 | m3 | 10,700 ₹64.2 L | 10,630 ₹63.8 L |
| 6.00 | Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 9.50-2.36mm and 0.26cum of 2.36 and below with 45.27 kgs of VG30( 60/70) bitumen and 50.30 Kg for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30t on capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory/Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher/9mpaver finisher, Vibratory/Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 360 | m3 | 11,500 ₹41.4 L | 11,197 ₹40.3 L |
| 7.00 | Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniformand free from streaks and holes etc., complete as per MoRT&H specification No.803 | 625 | m2 | 1,000 ₹6.3 L | 890 ₹5.6 L |
| 8.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum | 217 | m3 | 150 ₹4,350 | 131 ₹3,799 |
| 9.00 | Plain Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers. -Mixing by manual means | 217 | m3 | 5,700 ₹1.7 L | 5,560 ₹1.6 L |
| 10.00 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid). | 96 | m2 | 800 ₹76,800 | 710 ₹68,160 |
Tender Value
Refer Docs
EMD Value
₹1.7 L
Closing Date
23 Jan 2026, 3:00 pmClosed
Executive Officer
Ambalakara street, S.Kannanur, Samayapuram Post, Mannachanallur Tk, Trichy Dt.
Relaying of BT and CC Road
2026_DTP_641717_1
TURIP 25/2026 A1
Open Tender
Civil Works - Roads
60 days
S.Kannanur Town Panchayat
Please refer Tender documents.
3 documents required · 3 mandatory
₹17,700
₹1.7 L
S.Kannanur Town Panchayat
24 Feb 2026
10 Jan 2026
23 Jan 2026
10 Jan 2026
23 Jan 2026
10 Jan 2026
14 Jan 2026
Providing and Laying, Spreading and compacting graded stone aggregates to Wet Mix Macadam specification including premixing the materials with waterat OMC in mechnanical mix plant carriage of mixed material by tipper to site laying inuniform layers with paver sin Sub Base/Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5
Providing and laying Prime Coat over WBM/ WMM Surface using 7Kg of Emulsion Bitumen (SSI) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack Coat over WBM/ WMM Surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5
Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 9.50-2.36mm and 0.26cum of 2.36 and below with 45.27 kgs of VG30( 60/70) bitumen and 50.30 Kg for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30t on capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory/Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher/9mpaver finisher, Vibratory/Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniformand free from streaks and holes etc., complete as per MoRT&H specification No.803
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum
Plain Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers. -Mixing by manual means
Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid).
Plain Cement Concrete 1:1.5:3 (One part of Cement, one and half part of Crushed Sand (M- Sand), three coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification
Supplying and laying of Bitumen Pad of 12mm thick for expansion joints at an equal intervels, including cost and conveyance of all materials and labour charges etc, complete
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.08 MB
TURIPNotice.pdf
Additional Documents • 0.07 MB
BOQ_768600.xls
BOQ • 0.30 MB
BIDTURIP.pdf
Tender Documents • 0.27 MB
Download all tender documents and submit your bid