| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹45.6 LAccepted-AOC | ₹45.6 L | L1 | Accepted-AOC Willingly agreed to reduce rate have been accepted from competent authority |
| 2 | L2₹49.2 LRejected-AOC SANTIR BAZAR SOUTH TRIPURA PIN 799114 | SANTIR BAZAR | SOUTH TRIPURA | TRIPURA | 799114 | ₹49.2 L | L2 | Rejected-AOC Comparatively high percentage rate |
Tender Value
₹44.5 L
EMD Value
₹89,040
Closing Date
10 Jun 2026, 3:00 pmClosed
Executive Engineer,PWD(R and B),Santirbazar Div.
O/o the Executive Engineer,PWD (R and B),Santirbazar Division, South Tripura
SH- RCC Retaining Wall and its allied works
2026_CEPWD_73503_1
07/NIT/SE-III/B/PWD R and B/2026-27
Open Tender
Civil Works - Building
Percentage
270 days
Santirbazar
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
₹89,040
29 Jul 2026
4 Jun 2026
10 Jun 2026
4 Jun 2026
10 Jun 2026
4 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation for Structures. A. With out dewatering. Earthwork in excavation for structures as per drawing and MoRD technical specifications Clause 305.1 including setting out, construction of shoring & bracing, removal of stumps & other deleterious material and disposal upto a lead of 50 m, dressing of sides & bottom and backfilling in trenches with excavated suitable material. I. Ordinary Soil (i) Upto 3 m depth | 1 | Cum | 458.2 | ₹457.74 |
| 2 | Filling in foundation trenches as per drawing & MoRD technical specification Clause 305.3.9, 1200 I. Sand filling | - | Cum | 1,299.5 | - |
| 3 | Providing concrete for plain/reinforced concrete in open foundations complete including formwork as per drawings & MoRD technical specifications Clauses 802, 803, 900, 1202 and 1203. (including centering, shuttering, staging etc. but excluding reinforcement). I P.C.C grade M 10 (i)Nominal mix (1:3:6) | - | Cum | 9,983.7 | - |
| 4 | Providing concrete for plain/reinforced concrete in open foundations complete including formwork as per drawings & MoRD technical specifications Clauses 802, 803, 900, 1202 and 1203. (including centering, shuttering, staging etc. but excluding reinforcement). V R.C.C grade M 25 | 1 | Cum | 13,090.1 | ₹13,077.01 |
| 5 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar reinforcement in foundation complete as per drawings & MoRD technical specifications Clauses 1000 & 1202. | 0.4 | Ton | 91,627.18 | ₹36,650.87 |
| 6 | Plain/reinforced cement concrete in substructure complete including formwork as per drawings & MoRD technical specification Clauses 802, 804, 805, 806, 807, 900, 1202 & 1204. (including centering, shuttering, staging etc. but excluding reinforcement). V. R.C.C grade M-25 | - | Cum | 13,761 | - |
| 7 | Supplying, fitting & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar reinforcement in substructure complete as per drawings & MoRD technical specifications Clauses 1000 & 1202. | 0.4 | Ton | 91,869.48 | ₹36,738.61 |
| 8 | Providing & laying filter media with jhama brick aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil & bigger size towards the wall & providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and MoRD technical specification clause 1204.3.8. | - | Cum | 4,882.3 | - |
| 9 | Providing weep holes in brick masonry/ stone masonry, plain/ reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe or uPVC pipe (110 mm OD of 6.0 Kg/cm2 pressure) extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and MoRT&H technical specification clauses 2706, 2200 | 1 | Mtr | 392.2 | ₹391.81 |
| 10 | Construction of Embankment with Material Obtained from Borrow Pits. Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per MoRD Technical Specification Clause 301.5. | - | Cum | 245.4 | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.66 MB
dnit.pdf
Tender Documents • 3.24 MB
BOQ_74803.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].