| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAccepted-Finance | ₹1.0 Cr | L1 | Accepted-Finance Quoted L1 Rate |
| 2 | L2₹1.1 CrRejected-Finance | ₹1.1 Cr | L2 | Rejected-Finance Quoted L2 Rate |
| Sl No | Description | Qty | Unit | OM SAKTHI CONSTRUCTION L1 | P V K CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 1.00 | Strengthening to the road from Kumarappatti road KM 0/0- 1/830 (R-63)….Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc completeKm 0/0-1/830 | 2,196 | Sqm | 5.7 ₹12,517.20 | 7 ₹15,372 |
| 2.00 | Picking the existing mettaled surface and sectioning including all labour charges etc, complete.KM 0/0- 1/830 | 2,283.87 | Sqm | 21.85 ₹49,902.56 | 23 ₹52,529.01 |
| 3.00 | Earthwork excavation from borrow pits for filling in all classes of soils such as gravelly soil hard stiffcaly, stiff black cotton soil, hard red earth shales, murrams. Gravel stoney earth and earth mixed with 50% fair sized boulders and hard gravelly soil except sand and hard rock requiring blasting as per SS 20 A . | 657.76 | Sqm | 133 ₹87,482.08 | 140 ₹92,086.40 |
| 4.00 | Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction KM 0/0 -1/00 | 336.52 | Cum | 336.3 ₹1.1 L | 354 ₹1.2 L |
| 5.00 | KM 1/0 -1/830 | 280.13 | Cum | 336.3 ₹94,207.72 | 354 ₹99,166.02 |
| 6.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 1,027.75 | Cum | 2,519.4 ₹25.9 L | 2,652 ₹27.3 L |
| 7.00 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 6,851.62 | Sqm | 83.6 ₹5.7 L | 88 ₹6.0 L |
| 8.00 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 6,862.5 | Sqm | 19.95 ₹1.4 L | 21 ₹1.4 L |
| 9.00 | Providing and laying 50mm consolidated thick bituminous macadam using 0.20cum fo 26.50-13.20mm,0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRCmetal with 37Kgs of bitumen for pre mixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant20-30 ton capacity , conveying the mix by tipper trucks top a versite, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by8-10tonne Vibratory/ Pneumatic Roller to the required density etc.,including labour for attending to paver to site etc.,including hire charges and fuel charges for 20-30 to CMP with bitumen boiler, tipper trucks, Paver Finisher/ 9m paver finisher,Vibratory/Pneumatic roller and all other tools and plant required ,including fuel and all other incidental charges etc., complete as per specification | 342.59 | Cum | 8,714.35 ₹29.9 L | 9,173 ₹31.4 L |
| 10.00 | BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher, vibratory/ phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 | 171.56 | Cum | 11,178.65 ₹19.2 L | 11,767 ₹20.2 L |
Updated dates
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
27 Feb 2026, 3:00 pmClosed
Project Director
DRDA Tiruchirappalli
Strengthening the Road from Kumarappatti Road KM 0/0 -1/830 (R-63) (PUR) in Manapparai Block at Tiruchirappalli District under MGSMT - 2025-26 Additional Package.06
2026_RDTN_658204_6
DIPR/1099/TENDER/2026
Open Tender
Civil Works - Roads
180 days
Tiruchirappalli
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹1.1 L
DRDA Tiruchirappalli
8 Apr 2026
16 Feb 2026
27 Feb 2026
16 Feb 2026
27 Feb 2026
16 Feb 2026
19 Feb 2026
Strengthening to the road from Kumarappatti road KM 0/0- 1/830 (R-63)….Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc completeKm 0/0-1/830
Picking the existing mettaled surface and sectioning including all labour charges etc, complete.KM 0/0- 1/830
Earthwork excavation from borrow pits for filling in all classes of soils such as gravelly soil hard stiffcaly, stiff black cotton soil, hard red earth shales, murrams. Gravel stoney earth and earth mixed with 50% fair sized boulders and hard gravelly soil except sand and hard rock requiring blasting as per SS 20 A .
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction KM 0/0 -1/00
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying 50mm consolidated thick bituminous macadam using 0.20cum fo 26.50-13.20mm,0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRCmetal with 37Kgs of bitumen for pre mixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant20-30 ton capacity , conveying the mix by tipper trucks top a versite, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by8-10tonne Vibratory/ Pneumatic Roller to the required density etc.,including labour for attending to paver to site etc.,including hire charges and fuel charges for 20-30 to CMP with bitumen boiler, tipper trucks, Paver Finisher/ 9m paver finisher,Vibratory/Pneumatic roller and all other tools and plant required ,including fuel and all other incidental charges etc., complete as per specification
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher, vibratory/ phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
60 Cm Equilateral Triangle Cautionary Sign Board
60 Cm Circle Mandatory Sign
Chevron Sign 90 Cm Octogon (Curves)
HM Stone
KM Stone
Towards Provision for Road Stud
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
techsummary_790231.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.51 MB
TechBid6.pdf
Tender Documents • 1.36 MB
BOQ_790231.xls
BOQ • 0.24 MB
PriceBid6.pdf
Additional Documents • 0.86 MB
Download all tender documents and submit your bid