Loading…
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.4 LAccepted-AOC | L1 | Accepted-AOC l1 | |
| 2 | L2₹19.1 L+₹67,516 (3.67%)Rejected-Finance | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | RAGHULAN PILLAI R L1 | Arun Sahadevan L2 |
|---|---|---|---|---|---|
| 1.00Thengumpally Thumpassery Thodu | |||||
| 1.00 | OD124369/2025-2026:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:Dry Rubble Masonry | 9.5 | cum | 1,035.22 ₹9,834.59 | 918.51 ₹8,725.85 Lowest |
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 62.39 | cum | 332.22 ₹20,727.21 | 314 ₹19,590.46 Lowest |
| 1.00 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete | 12 | hour | 341.22 ₹4,094.64 | 301.65 ₹3,619.8 Lowest |
| 1.00 | OD124370/2025-2026:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good
quality blasted rubble including packing to compactness to lines and levels cost and conveyance
of all materials labour charges etc. complete as per direction of Departmental officers at site | 96.89 | cum | 3,150.22 ₹3,05,234.27 Lowest | 3,486.29 ₹3,37,797.1 |
| 1.00 | OD124371/2025-2026:DRY RUBBLE MASONRY using Departmental rubble _ Dry rubble without concrete levelling course masonry with good
quality blasted rubble including packing to compactness to lines and levels,
labour charges etc. complete as per direction of Departmental officers at site. | 6.65 | cum | 1,708.22 ₹11,359.66 | 1,497.96 ₹9,961.43 Lowest |
| 1.01 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 25.53 | sqm | 376.22 ₹9,604.9 | 337.11 ₹8,606.42 Lowest |
| 1.01 | 5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 7.2 | cum | 9,710.22 ₹69,894.16 | 8,698.51 ₹62,611.87 Lowest |
| 1.01 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 287.92 | kilogram | 109.44 ₹31,509.96 | 98.15 ₹28,259.35 Lowest |
| 2.00Kottoor Vallattu ela thodu | |||||
Tender Value
Refer Docs
EMD Value
₹50,000
Closing Date
19 Sept 2025, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
ASSISTANT ENGINEER, LSGD
DILEEP LEKSHMANAN ASSISTANT ENGINEER, LSGD KARAVALOOR GP
KARAVALOOR G.P 66/25-26-THODU PROTECTION IN VARIOUS PORTIONS
2025_LSGD_795862_5
03/AE/LID EW/KVR/25-26
Open Tender
Civil Works - Canal
Item Rate
120 days
KARAVALOOR
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,760
Yes
₹50,000
Yes
11 Nov 2025
11 Sept 2025
20 Sept 2025
11 Sept 2025
19 Sept 2025
11 Sept 2025
Amount
Thengumpally Thumpassery Thodu
OD124369/2025-2026:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:Dry Rubble Masonry
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD124370/2025-2026:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
OD124371/2025-2026:DRY RUBBLE MASONRY using Departmental rubble _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site.
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Kottoor Vallattu ela thodu
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD125998/2025-2026:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Plakkodu Chavarakonam Thodu
OD126132/2025-2026:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:Dry Rubble Masonry
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD126123/2025-2026:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
OD126138/2025-2026:DRY RUBBLE MASONRY using Departmental rubble _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site.
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Mathra Ela Thodu
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD132879/2025-2026:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Kanjiramukku Pulikkode Thodu
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD155065/2025-2026:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Thekkadath Bhagam Thodu
OD180626/2025-2026:Demolishing stone rubble masonry manually /by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in -charges : Dry Rubble Masonry
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD180654/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course levelling course masonry with good quality blasted rubble including packing to compactness to line and levels cost and conveyance of all materials labour charges etc . complete as per direction of Departmental officers at site .
OD180531/2025-2026:DRY RUBBLE MASONRY using Departmental rubble _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site.
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Pottukulam Thodu
OD182406/2025-2026:Demolishing stone rubble masonry manually /by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in -charges : Dry Rubble Masonry
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD182413/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course levelling course masonry with good quality blasted rubble including packing to compactness to line and levels cost and conveyance of all materials labour charges etc . complete as per direction of Departmental officers at site .
OD183219/2025-2026:DRY RUBBLE MASONRY using Departmental rubble _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site.
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Therikunnu choolattu bhagam Thodu
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
OD183001/2025-2026:DRY RUBBLE MASONRY - Dry rubble without concrete levelling course levelling course masonry with good quality blasted rubble including packing to compactness to line and levels cost and conveyance of all materials labour charges etc . complete as per direction of Departmental officers at site .
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Arun Sahadevan (BID ID -2346636)
Bidder Name
RAGHULAN PILLAI R
Arun Sahadevan
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .