Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹26.7 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹27.2 L+₹48,834.05 (1.83%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹24.3 L
EMD Value
₹50,000
Closing Date
5 Mar 2024, 4:00 pmClosed
Executive Engineer, NH Division Kollam
O/o Executive Engineer, NH Division Kollam
Traffic Safety Measures at NH Urban Links Kazhakkoottam-Traffic Safety Measures -Reconstruction of Drain and Retaining wall at Kazhakkoottam
2024_PWD_658914_2
PWD/NH/TR/22536/2023_5_1_1/1
Open Tender
Civil Works - Highways
Item Rate
180 days
Thiruvanathapuram
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹50,000
Yes
9 Jul 2024
27 Feb 2024
7 Mar 2024
27 Feb 2024
5 Mar 2024
27 Feb 2024
Amount
Urgent repair and maintenance
2.3.1.A:Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness In area of light jungle - By Manual Means
2.1.3:Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. <br> Girth from 900 mm to 1800 mm
12.1.B.1:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Ordinary Soil - Depth upto 3m - Mechanical Means
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer
12.8.2.C:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - With Batching Plant, Transit Mixer and Concrete Pump - ( Without formwork)
55.25:Lifting, conveying and fixing the newly casted RCC covering slabs of any thickness on top of drain in position including all labour charges and miscellaneous expenses etc complete
3.11:Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.
OD200314/2023-2024:Cutting the entire overhanging branches of dangerously standing trees by engaging skilled workers with necessary power tools with safety equipment including all hire charges for tools and plant and removing the all un serviceable materials from site with pick up vehicles etc complete as per the direction of the departmental officers
8.8:Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
8.16:Reinforced cement concrete M-15 grade boundary pillars of standard design as per IRC:25-19767, fixed in position including finishing and lettering but excluding painting .
8.22:Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer, all as specified
2.4.2.A:Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres Cement Concrete Grade M-15 & M-20 - By Mechanical Means
Retaining wall
4.2.3:Providing and laying cement concrete in retaining walls, return walls, walls ( any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor, etc. up to floor five level, excluding the cost of centering, shuttering and finishing:1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
OD200315/2023-2024:Providing and fixing PVC pipes for weep holes inside retaining wall as per direction of Engineer in Charge. 50 mm dia 6 Kgf/cm2
OD200316/2023-2024:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Baiju Thampi T
Bidder Name
J S Subhash Chandra Babu
Baiju Thampi T
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1030446.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .