| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.2 LAccepted-AOC | L1 | Accepted-AOC First lowest rate quoted bid | |
| 2 | L2₹63,642.50+₹5,053.56 (8.63%)Rejected-AOC KOTTATHARA SOCIETY | IDUKKI | KERALA | 685501 | L2 | Rejected-AOC Second lowest rate quoted bid |
Tender Value
Refer Docs
EMD Value
₹11,500
Closing Date
20 Mar 2025, 3:00 pmClosed
Asst Executive Engineer
KWA, PH SUB DIVISION KALPETTA
O_M DRW2025- Water Supply Schemes-AWSS to Kaniyambetta Desilting well and Infiltration gallery at RWPS Neeritad General Civil work
2025_KWA_746919_1
TR_3/WRD/KWA(CE)/4371/2025
Open Tender
Civil Works - Water Works
Percentage
5 days
Wayanad District
Please refer bid document
3 documents required · 3 mandatory
₹1,200
₹11,500
23 Apr 2025
6 Mar 2025
21 Mar 2025
6 Mar 2025
20 Mar 2025
6 Mar 2025
Amount
Desilting well
100.54.4.7:Desilting open wells of dia above 6.0m and up to 9.0m and depth up to 13.5m by earth work excavation in or under water, after closing the inlet valves and plugging any holes in the steining by engaging divers with breathing accessories, bailing out water using pump set of suitable capacity, lifting the excavated silt/mud/clay using ropes, pulleys and buckets and disposing the same within minimum lead of 50 m from the periphery of the well, including engaging coolies for scrapping the inner side of the well, without causing any damages to the existing structures and installations, including hire and conveyance of tools and plant and as per the directions of the department officers etc. complete.
100.54.4.8:Desilting open wells of dia above 6.0m and up to 9.0m and depth up to 15.0m by earth work excavation in or under water, after closing the inlet valves and plugging any holes in the steining by engaging divers with breathing accessories, bailing out water using pump set of suitable capacity, lifting the excavated silt/mud/clay using ropes, pulleys and buckets and disposing the same within minimum lead of 50 m from the periphery of the well, including engaging coolies for scrapping the inner side of the well, without causing any damages to the existing structures and installations, including hire and conveyance of tools and plant and as per the directions of the department officers etc. complete.
OD234019/2024-2025:Construction of temporary bund using earth filled cement bags including cutting of the earth, filling, conveying and placing in position, , Placing of polyethene sheets on the bund, placing bamboos poles at regular intervals, dismantling the sand/ earth filled cement bag from the foundation site of bund apron on both side, removing the sand/ earth from the bag and disposing the damaged cement bags properly as per the direction of the department officers including all cost and labour chargers and hire for tools and plants etc., complete.
Leading channel cleaning
OD233965/2024-2025:Cleaning leading channel including bailing out and all cost and conveyance of material, including labour charges, hire for tools etc.. complete
ABDUL MUNEER N K (BID ID -2165442)
Bidder Name
ISMAIL T
ABDUL MUNEER N K
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1206382.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .