| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.3 LAccepted-AOC | L1 | Accepted-AOC L1 |
Tender Value
₹8.5 L
EMD Value
₹21,180
Closing Date
19 Dec 2023, 6:00 pmClosed
Executive Engineer
O/o Executive Engineer,LSGD,Division Civi station
DRAIN
2023_LSGD_629329_43
JPDEC07/LIDEW/ALPY/23-24
Open Tender
Civil Works - Others
Item Rate
180 days
PLEASE SEE WORK ITEM DETAILS
Please refer Tender documents.
8 documents required · 8 mandatory
₹1,870
Yes
₹21,180
Yes
3 Apr 2024
11 Dec 2023
22 Dec 2023
11 Dec 2023
19 Dec 2023
11 Dec 2023
Amount
Side protection
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
Bidder Name
A S Anandan
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_952989.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .