Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹24.8 LAccepted-AOC SHOP NO 1 154 1 G F BLDG KINARA WARD NO 2 SANGUEM GOA | 1 | Accepted-AOC Lowest Bidder | |
| 2 | 2₹24.9 L+₹9,122.21 (0.37%)Rejected-Finance | 2 | Rejected-Finance L2 Bidder | |
| 3 | Rejected-Technical | - | Rejected-Technical Wrong Documents |
Tender Value
₹23.8 L
EMD Value
₹47,530
Closing Date
13 Jun 2023, 4:00 pmClosed
EE II, WRD
Aquem Baixo Rawanfond
Flood protection measures and stabilization of banks of Nallah in Sy. No. 284-1 and 309-1 in Cuncolim Constituency.
2023_WRD_8934_1
WDII/TECH/F17/4e/2023-24/SN1
Open Tender
Miscellaneous Works
Item Rate
60 days
Rawanfond
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,000
₹47,530
25 Jan 2024
24 May 2023
14 Jun 2023
24 May 2023
13 Jun 2023
24 May 2023
Amount
Earthwork in excavation by mechanical/manual means in all types of strata comprising any of the materials such as soil, silt, sand, clay, gravel, moorum of all varieties shingles, pebbles, all types of conglomerates, laterite rocks, soft rock, disintergrated or weathered rock, fissured/shattered, decomposed rock and such materials either in full or in parts as the case may be adopting any approved method or methods as may be convenient or permitted including chiseling, wedging etc. but blasting prohibited all conditions such as dry, moist, saturated, submerged, foul conditions etc. incl. pumping or bailing out water/dewatering including setting out constructed shoring and bracing, removal of stump and other deleterious matter, dressing of sides and bottom, providing barricading, danger lighting, guarding etc. with all leads and lifts etc. as per specification and drawing and as directed by the Engineer in Charge etc. complete.
Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete.
Centering and shuttering including struttings, propping etc. and removal of formwork for : a) Foundations, footings, bases for columns and mass concrete.
Centering and shuttering including struttings, propping etc. and removal of formwork for : b) vertical surfaces such as retaining walls , return walls, walls (any thk) including attached pilasters, buttresses, plinth and string courses, fillets, etc.
Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggrt. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: a) All works upto plinth level
Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggrt. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: b) In retaining walls , return walls(any thk) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks, plain window sills, fillets etc, upto floor five level.
Laterite boulder masonry in cement concrete 1:3:6 (1 cement, 3 coarse sand : 6 graded granitic stone aggrt. 40mm nominal size) in foundation.
Providing and fixing weepholes with rigid PVC make laid in position with a required slope and level while layingpipes of approved the concrete of retaining wall, wing wall and earth retaining structure complete as directed by the Engineer in charge a. 110mm Dia
Kristly Enterprises
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .