| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.5 CrAccepted-AOC | ₹3.5 Cr | L1 | Accepted-AOC Agreement executed |
| 2 | L2₹3.9 Cr+₹39.6 L (11.3%)Rejected-AOC | ₹3.9 Cr+₹39.6 L (11.3%) | L2 | Rejected-AOC L2 |
| 3 | L3₹4.2 Cr+₹66.2 L (18.9%)Rejected-AOC | ₹4.2 Cr+₹66.2 L (18.9%) | L3 | Rejected-AOC L3 |
Tender Value
₹4.3 Cr
EMD Value
₹1 L
Closing Date
4 Mar 2022, 5:00 pmClosed
Superintending Engineer, MICC, EKM
Office of the Superintending Engineer, MICC,3rd Floor, Civil Station, Kakkanad, Ernakulam
Rejuvenation of Kachithod Dam
2022_Irrig_477737_1
04/ET/SEMICC/2021-22/S
Open Tender
Civil Works - Others
Item Rate
365 days
Madakkathara Panchayath
Please refer Tender documents.
7 documents required · 7 mandatory
₹9,760
Yes
₹1 L
Yes
13 Oct 2022
24 Feb 2022
8 Mar 2022
24 Feb 2022
4 Mar 2022
24 Feb 2022
24 Feb 2022 - 4 Mar 2022
Amount
APPENDIX A - Desilting of Reservoir - 2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared as per the direction of departmental officers at site.
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per the direction of departmental officers at site.
od42165/2021_2022/IA : Protecting and dressing up of surface and sides of the outer bund constructed using excavated mud and base for planting ramacham etc with reinforced GCL (Geoclay 310) including material cost, transportation and labour charges for placing etc.complete as per the directions of departmental officers at site.
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil , as per the direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc, as per the direction of departmental officers at site.
4.1.3 : Providing and laying in position cement concrete 1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), of specified grade excluding the cost of centering and shuttering - All work up to plinth level: as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more , as per the direction of departmental officers at site.
Appendix-B strengthening and Preventing Leakage of existing check dam- 15.3 : Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
60.1.1 : RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete as per the direction of departmental officers at site.
60.2.3 : Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete, as per the direction of departmental officers at site.
2.8.1 : Earth work in excavation in all classes of soil by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms,with all lead and lift, including getting out the excavated soil and disposal of surplus excavated soil as per the direction of departmental officers at site.
4.1.8 : Providing and laying in position cement concrete 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size), of specified grade excluding the cost of centering and shuttering - All work up to plinth level: as per the direction of departmental officers at site.
50.2.33.8 : Cutting branches of trees overhanging above any structures of girth beyond 120cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete as per the direction of departmental officers at site.
4.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc as per the direction of departmental officers at site.
4.1.3 : Providing and laying in position cement concrete 1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), of specified grade excluding the cost of centering and shuttering - All work up to plinth level :as per the direction of departmental officers at site.
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc, :as per the direction of departmental officers at site.
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete 1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size,, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level: :as per the direction of departmental officers at site.
60.6 : PVC WEEP HOLES- Providing weep holes using 75mm dia. PVC pipes working pressure 4kg /sq.cm including cost of materials, conveyance, labour charges etc. complete , as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
50.13.1 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete , as per the direction of departmental officers at site.
od40930/2021_2022/IA : Name board - Supplying and fixing granite of any coloue , 18mm thick (area 1sqaure meter approx.) in a concrete slab using cement concrete mix of 1:2:4 with finishing and engraving letters in granite, as per the direction of departmental officers at site.
APPENDIX :C- Renovation works for Dam area - 60.7.4 : DR PACKING FOR APRONS - Rough stone dry packing for apron with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
50.2.33.5 : Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete, as per the direction of departmental officers at site.
2.1.1 : Earth work in surface excavation in all classes of soil not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth with all lead and lift, disposed soil to be levelled and neatly dressed: as per the direction of departmental officers at site.
60.1.1 : RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete, as per the direction of departmental officers at site.
15.9.1 : Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In Lime Mortor, as per the direction of departmental officers at site.
od39610/2020_2021/IA : DR PACKING FOR APRONS BY USING DEPARTMENTAL RUBBLE - Rough stone dry packing for apron with good quality departmental blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.2.4 : BAILING OUT WATER USING PUMP ABOVE 10HP AND UP TO 20HP - Bailing out water with engine and pump set above 10HP and up to 20HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete, as per the direction of departmental officers at site.
2.6.1 : Earth work in excavation in all classes of soil by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth,with all lead and lift, disposed earth to be levelled and neatly dressed. as per the direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand), as per the direction of departmental officers at site.
16.68 : Providing and laying 60 mm thick factory made cement concrete interlocking paver block of M - 30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge.
4.1.8 : Providing and laying in position cement concrete 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size), of specified grade excluding the cost of centering and shuttering - All work up to plinth level: as per the direction of departmental officers at site.
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns, as per the direction of departmental officers at site.
4.1.3 : Providing and laying in position cement concrete 1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), of specified grade excluding the cost of centering and shuttering - All work up to plinth level: as per the direction of departmental officers at site.
5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform, as per the direction of departmental officers at site.
5.2.2 : Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size), as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
50.6.2.2 : Solid masonry using pre cast solid blocks (factory made) of size 30x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in : CM 1:6 ( 1 cement : 6 coarse sand) etc complete, as per the direction of departmental officers at site.
13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand), as per the direction of departmental officers at site.
16.69 : Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature jointed with cement mortar 1:3 ( 1 cement : 3 coarse sand) , including making joints with or without grooves ( thickness of joints except at sharp curve shall not to more than 5 mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge ( length of finished kerb edging shall be measured for payment ). ( Precast C.C. kerb stone shall be approved by Engineer-in-Charge)
10.26.3 : Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.G.I. pipes, as per the direction of departmental officers at site.
13.43.1 : Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer, as per the direction of departmental officers at site.
13.60.1 : Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work, as per the direction of departmental officers at site.
13.52.1 : Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work, as per the direction of departmental officers at site.
13.71 : Lettering with black Japan pint of approved brand and manufacture, as per the direction of departmental officers at site.
8.2.2.1 : Providing and fixing 18 mm thick gang saw cut, mirror, polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations, of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 ( 1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels.Granite of any colour and shadeArea of slab upto 0.50 sqm, as per the direction of departmental officers at site.
od42136/2021_2022/IA : Supplying and laying interlocking CC paver block with minimum thickness of 80 mm or nearest size ,minimum strength M30 including providing a layer of 6 mm aggregate for 5 cm thickness above levelling course of 13 cm thickness using stone aggregate below 40mm nominal size ,then laying interlock cobbles in lines and levels as per the directions of the departmental officers at site inclusive of all cost and conveyance charges etc.complete.
Appendix-D view point and fishing area - 2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared, as per the direction of departmental officers at site.
60.2.3 : Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete ,as per the direction of departmental officers at site.
60.1.2 : RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete.,as per the direction of departmental officers at site.
od44688/2021_2022/IA : Making precast reinforced cement concrete piles of 300mm X 300mm size sqaure pile with a design mix of M25 grade concrete with cast iron shoe to carry safe working load ncluding cost of all materials, labour charges, centering and shuttering, curing and placing inposition for driving as per the direction of departmental officers at site.
od50710/2021_2022/IA : driving precast reinforced cement concrete piles of 30cm square pile, as per the direction of departmental officers at site.
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size,as per the direction of departmental officers at site.
5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform,as per the direction of departmental officers at site.
5.9.5 : Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers,as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
11.19.3 : Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand):Dark shade pigment using ordinary cement, as per the direction of departmental officers at site.
10.26.3 : Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.G.I. pipes, as per the direction of departmental officers at site.
13.52.1 : Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work, as per the direction of departmental officers at site.
Appendix E-Cafeteria and Toilet in Park - 2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared, as per the direction of departmental officers at site.
2.8.1 : Earth work in excavation in all classes of soil by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms,with all lead and lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m., as per the direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
50.6.2.2 : Solid masonry using pre cast solid blocks (factory made) of size 30x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in : CM 1:6 ( 1 cement : 6 coarse sand) etc complete, as per the direction of departmental officers at site.
50.6.3.1 : Solid block masonry using pre cast solid blocks ( Factory made) of size 40x20x10cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth for 10 cm thick wall in CM 1:6 ( 1 cement : 6 coarse sand) including cost of scaffolding etc complete, as per the direction of departmental officers at site.
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand), as per the direction of departmental officers at site.
5.9.5 : Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers, as per the direction of departmental officers at site.
5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform, as per the direction of departmental officers at site.
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size, as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
10.6.2 : Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.20 mm M.S. laths with 1.20 mm thick top cover, as per the direction of departmental officers at site.
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size), as per the direction of departmental officers at site.
13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand), as per the direction of departmental officers at site.
50.13.1 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete, as per the direction of departmental officers at site.
8.31 : Providing and fixing Ist quality ceramic glazed wall tiles conforming to IS: 15622 (thickness to be specified by the manufacturer), of approved make, in all colours, shades except burgundy, bottle green, black of any size as approved by Engineerin-Charge, in skirting, risers of steps and dados, over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm, including pointing in white cement mixed with pigment of matching shade complet,as per the direction of departmental officers at site.
11.46.2 : Providing and laying Vitrified tiles indifferent sizes (thickness to be specified by manufacturer), with water absorption less than 0.08 % and conforming to I.S. 15622, of approved make, in all colours & shade, in skirting, riser of steps, over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand), including grouting the joint with white cement & matching pigments etc. complete.Size of Tile 600x600 mm,as per the direction of departmental officers at site.
13.43.1 : Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer,as per the direction of departmental officers at site.
9.117.1 : Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1 mm), with wall thickness 2.0mm (±0.2 mm), corners of the door frame to be jointed with galvanized brackets and stainless steel screws, joints mitred and plastic welded. The hinge side vertical of the frames reinforced by galvanized M.S. tube of size 19 x 19 mm and 1 mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per manufacturer's specification and direction of Engineer-in-charge Extruded section profile size 48x40 mm
9.118.1 : Providing and fixing to existing door frames24 mm thick factory made PVC door shutters made of styles and rails of a uPVC hollow section of size 59x24 mm and wall thickness 2 mm (± 0.2 mm) with inbuilt edging on both sides. The styles and rails mitred and joint at the corners by means of M.S. galvanised/plastic brackets of size 75x220 mm having wall thickness 1.0 mm and stainless steel screws. The styles of the shutter reinforced by inserting galvanised M.S. tube of size 20x20 mm and 1 mm (± 0.1 mm) wall thickness. The lock rail made up of 'H' section, a uPVC hollow section of size 100x24 mm and 2 mm (± 0.2 mm) wall thickness,fixed to the shutter styles by means of plastic/galvanised M.S. 'U' cleats. The shutter frame filled with a uPVC multi-chambered single panel of size not less than 620 mm, having over all thickness of 20 mm and 1 mm (± 0.1 mm) wall thickness. The panels filled vertically and tie bar at two places by inserting horizontally 6 mm galvanised M.S. rod and fastened with nuts and washers, complete as per manufacturer's specification and direction of Engineer-in-charge( For W.C. and bathroom door shutter).
50.9.1.2 : Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia & length ( hold fast lugs or dash fastener shall be paid for separately) using good quality Pincoda wood, as per the direction of departmental officers at site.
50.9.4.1 : Providing and fixing paneling or paneling and glazing in paneled or paneled and glazed shutters for doors, windows and clerestory windows (Area of opening for panel inserts excluding portion inside grooves or rebates to be measured) paneling for paneled or paneled and glazed shutters 25 mm to 40 mm thick using good quality Anjili/ Jack wood, as per the direction of departmental officers at site.
50.9.5.1 : Providing and fixing glazed shutters for doors, windows and clerestory windows using 4 mm thick float glass panes including ISI marked M.S pressed butt hinges bright finished of required size with necessary screws. Using Anjili wood/ jack wood 35 mm thick shutters as per the direction of departmental officers at site.
50.9.15.5 : Providing and fixing iron hooks and eyes: 100 mm, as per the direction of departmental officers at site.
50.18.9.13.2 : Providing and fixing PVC pipes, fittings including fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 25 mm dia 10 Kgf/cm2- External work - Exposed on wall, as per the direction of departmental officers at site.
50.18.9.17.1 : Providing and fixing PVC pipes including fixing the pipe with clamps/ clip at 1.00 m spacing . This includes jointing of pipes with one step PVC solvent cement and testing of joints complete as per direction of Engineer-in-Charge 63 mm dia 6 Kgf/cm2 - External work - Exposed on wall, as per the direction of departmental officers at site.
51.19.ST4 : Supplying and installing ready made PVC Septic tank including the cost of carriage, trenching, placing at the level below ground level as specified as per the direction of engineer in charge (Provision for CC/RCC/Sand/06mm aggregate for the preparation of bed shall be paid separately) 4. 35 to 50 flush capaci, as per the direction of departmental officers at site.
19.32.1 : Making soak pit 2.5 m diameter 3.0 metre deep with 45 x 45 cm dry brick honey comb shaft with bricks and S.W. drain pipe 100 mm diameter, 1.8 m long complete as per standard design.With common burnt clay F.P.S. (non modular) bricks of class designation 7.5, as per the direction of departmental officers at site.
17.2.1 : Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan) with seat and lid, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever), conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required:W.C. pan with ISI marked white solid plastic seat and lid, as per the direction of departmental officers at site.
17.23 : Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm or 340x410x265 mm sizes respectively, as per the direction of departmental officers at site.
17.25.2 : Providing and fixing white vitreous china wash basin including making all connections but excluding the cost of fittings:Flat back wash basin of size 550x400 mm, as per the direction of departmental officers at site.
17.26.1 : Providing and fixing kitchen sink including making all connections excluding cost of fittings.White glazed fire clay sink of size 600x450x250 mm, as per the direction of departmental officers at site.
17.28.1.2 : Providing and fixing P.V.C. waste pipe for sink or wash basin including PVC. waste fittings complete.Semi rigid pipe40 mm dia, as per the direction of departmental officers at site.
18.48 : Providing and placing on terrace (at all floor levels) polyethylene water storage tank :ISI 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank, as per the direction of departmental officers at site.
8.2.2.1 : Providing and fixing 18 mm thick gang saw cut, mirror, polished, premoulded and prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and similar locations, of required size, approved shade, colour and texture laid over 20 mm thick base cement mortar 1:4 ( 1 cement : 4 coarse sand), joints treated with white cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing, moulding and polishing to edges to give high gloss finish etc. complete at all levels.Granite of any colour and shadeArea of slab upto 0.50 sqm, as per the direction of departmental officers at site.
Appendix F- Step, Ramp & Protection wall near to varikulamPump house. - 2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared,as per the direction of departmental officers at site.
60.2.3 : Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete, as per the direction of departmental officers at site.
60.1.2 : RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete, as per the direction of departmental officers at site.
2.8.1 : Earth work in excavation in all classes of soil by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, with all lead and lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. as per the direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site,
16.11 : Dry stone pitching 22.5 cm thick including supply of stones and preparing surface complete, as per the direction of departmental officers at site.
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand), as per the direction of departmental officers at site.
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) ,as per the direction of departmental officers at site.
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns, as per the direction of departmental officers at site.
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc, as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
11.19.3 : Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in floors, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing and polishing complete, on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand):Dark shade pigment using ordinary cement, as per the direction of departmental officers at site.
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering,with all lead and lift m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, with all lead and lift .as per the direction of departmental officers at site.
60.7.4 : DR PACKING FOR APRONS - Rough stone dry packing for apron with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
Appendix G- Steel Bridge over Leading chal in the upstream area - 2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared, as per the direction of departmental officers at site.
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil, as per the direction of departmental officers at site.
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size), as per the direction of departmental officers at site.
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size, as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
10.26.3 : Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.G.I. pipes ,as per the direction of departmental officers at site.
13.52.1 : Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work, as per the direction of departmental officers at site.
Appendix H- Plantation of Trees - 2.6.1 : Earth work in excavation in all classes of soil by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, with all lead and lift, disposed earth to be levelled and neatly dressed, as per the direction of departmental officers at site.
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m, as per the direction of departmental officers at site.
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size), as per the direction of departmental officers at site.
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns, as per the direction of departmental officers at site.
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), as per the direction of departmental officers at site.
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size, as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more, as per the direction of departmental officers at site.
13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand), as per the direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
Appendix I - Side protection works to Leading chal in the upstream area - 2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared, as per the direction of departmental officers at site.
2.6.1 : Earth work in excavation in all classes of soil by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, with all lead and lift, disposed earth to be levelled and neatly dressed, as per the direction of departmental officers at site.
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc, as per the direction of departmental officers at site.
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size),as per the direction of departmental officers at site.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more,as per the direction of departmental officers at site.
SAJI KURUVILA
jmj constructions
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_685712.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .